Official nameHaddam Neck Nuclear Power Plant
CountryUnited States
LocationHaddam, Middlesex County, Connecticut
Coordinates41°28′56″N 72°29′54″W / 41.48222°N 72.49833°W / 41.48222; -72.49833
StatusDecommissioned
Construction beganMay 1, 1964
Commission dateJanuary 1, 1968
Decommission dateDecember 5, 1996
OwnerConnecticut Yankee Atomic Power Company
OperatorConnecticut Yankee Atomic Power Company
Nuclear power station
Reactor typePWR
Reactor supplierWestinghouse
Cooling sourceConnecticut River
Thermal capacity1 × 1825 MWth
Power generation
Units decommissioned1 × 560 MW
Capacity factor73.5% (lifetime)
External links
WebsiteConnecticut Yankee
CommonsRelated media on Commons

Connecticut Yankee Nuclear Power Plant (CY) was a nuclear power plant located in Haddam Neck, Connecticut, The Power plant is on the Connecticut River, nearby is the Haddam Neck swing bridge. that was commissioned in 1968, ceased electricity production in 1996, and was decommissioned by 2004. The reason for the closure was because operation of the nuclear power station was no longer cost effective.[1] The plant had a capacity of 582MW.[2] Demolition of the containment dome was completed the week of July 17, 2006.

Kenneth Nichols, the deputy to Leslie Groves on the Manhattan Project, was a consultant for the Connecticut Yankee and Yankee Rowe nuclear power plants. He said that while the plants were considered "experimental" and were not expected to be competitive with coal and oil, they "became competitive because of inflation … and the large increase in price of coal and oil." The Connecticut Yankee plant was estimated to cost $100 million.[3]

See also

References

  1. ^ Ravo, Nick (10 October 1996). "Connecticut Atom Plant Likely to Close". The New York Times.
  2. ^ "SEC Info - Connecticut Light & Power Co - 8-K - For 7/22/96". SEC Info Website. Retrieved 2008-07-04.
  3. ^ Nichols, Kenneth David (1987). The Road to Trinity: A Personal Account of How America's Nuclear Policies Were Made. New York: William Morrow and Company. p. 344. ISBN 0-688-06910-X. OCLC 15223648.