Farringdon station

From Wikipedia, the free encyclopedia
  (Redirected from Farringdon railway station)
Jump to: navigation, search
Farringdon London Underground National Rail
Farringdon station new building open 2012.JPG
The new National Rail entrance, built as part of the Thameslink programme
Farringdon is located in Central London
Farringdon
Farringdon
Location of Farringdon in Central London
Location Farringdon
Local authority London Borough of Islington
Managed by London Underground
Station code ZFD
DfT category E
Number of platforms 4
Accessible Yes [1][2]
Fare zone 1
London Underground annual entry and exit
2010 Increase 16.810 million[3]
2011 Increase 19.02 million[4]
2012 Increase 20.4 million[4]
2013 Increase 21.76 million[4]
National Rail annual entry and exit
2008–09 Decrease 1.173 million[5]
2009–10 Increase 1.492 million[5]
2010–11 Increase 4.632 million[5]
2011–12 Increase 4.943 million[5]
2012–13 Increase 5.041 million[5]
Key dates
10 January 1863 Opened as Farringdon Street
23 December 1865 Station relocated
26 January 1922 Renamed as Farringdon & High Holborn
21 April 1936 Renamed as Farringdon
1 July 1936 Goods yard closed[6]
December 2009 Moorgate branch severed
Listed status
Listed feature Underground station
Listing grade II
Entry number 1298047[7]
Added to list 17 May 1994
Other information
Lists of stations
External links
Portal icon London Transport portal
Portal icon UK Railways portalCoordinates: 51°31′12″N 0°06′19″W / 51.520°N 0.1053°W / 51.520; -0.1053

Farringdon station is a London Underground and National Rail station in Clerkenwell, in the London Borough of Islington, just outside of the City of London. It was opened in 1863 as the terminus of the Metropolitan Railway, which was the world's first underground metro railway line.

The Underground station is now served by the Circle, Hammersmith & City, and Metropolitan lines. Today the National Rail station is one of the less important mainline central London stations, but that is expected to change when it becomes a major interchange station between the two largest transport infrastructure programmes currently under way in London: the Thameslink Programme and Crossrail, both scheduled for completion in 2018.

London Buses routes 63 and night route N63 serve Farringdon station.

History[edit]

The station was opened on 10 January 1863 as the terminus of the original Metropolitan Railway, the world's first underground metro line. The station, initially named Farringdon Street, was originally a short distance from the present station building. The line ran from the Farringdon area to Paddington, a distance of 4 mi (6 km). The station was relocated on 23 December 1865 when the Metropolitan Railway opened an extension to Moorgate. It was renamed Farringdon & High Holborn on 26 January 1922, and its present name was adopted on 21 April 1936.[8] It was built in conjunction with a freight route to take livestock to a depot to its south to supply Smithfield Market; there are cattle ramps onto the street West Smithfield for this purpose. Smithfield was redesignated as a wholesale 'deadmeat' market only before the initiation of services; the freight station was last used in the 1920s but remains in situ.

The Metropolitan Railway's second Farringdon station, 1866.
The station frontage carrying the name Farringdon & High Holborn, 1989.

The lines from Farringdon to King's Cross run alongside the now culverted River Fleet, which was above ground here until 1734.[9] The station building is an unusually well-preserved piece of early 20th-century London Underground architecture; it still has its original signage (with the name Farringdon & High Holborn on the façade) and other indications of the Metropolitan Railway's original main-line style operation, with a sign for a Parcel Office also surviving on the exterior wall.

After the bay platforms at Blackfriars closed in March 2009, Southeastern services that previously terminated at Blackfriars were extended to Kentish Town, St. Albans, Luton or Bedford, calling at this station.[10] First Capital Connect trains to Moorgate ceased at the same time. Trains south of Blackfriars are operated by Southeastern, north of Blackfriars by First Capital Connect.

Current developments[edit]

There are two major rail development projects in progress that involve Farringdon. Crossrail is a new east-west railway scheduled to open in 2018, and the Thameslink Programme is a major upgrade to the existing north-south Thameslink route, enabling longer and more frequent trains, also scheduled to be completed in 2018.

After the completion of Crossrail, Farringdon will be one of the country's busiest stations by number of trains passing through.[11] It will be the only station where passengers can change between Crossrail and Thameslink. A new building, housing a dedicated ticket hall, has been constructed to serve these extra passengers. The new building is to the immediate south of the original station, which itself has been upgraded as part of the programme.

An additional entrance has also been built at the north end of the original station, onto Turnmill Street.

Thameslink upgrade[edit]

A First Capital Connect Class 319 heads south from Farringdon. On the left is the blocked-off branch to Moorgate, closed as part of the Thameslink upgrade.

Farringdon Station has been rebuilt[12] to accommodate longer Thameslink trains and to make other improvements to the station.[13] The existing station building has been refurbished with a new roof canopy covering the north end of all four platforms and a new entrance and concourse facing Turnmill Street. An additional ticket hall has been built on the south side of Cowcross Street providing access to the Thameslink platforms, which have been extended southwards underneath this building, allowing the station to handle 240 m (12-carriage) trains. Platforms have been widened to accommodate increased passenger numbers. This process required the bridge that formed Cowcross Street to be demolished and rebuilt.[14] Cowcross Street will be pedestrianised.[15] Lifts have been provided throughout.

The existing listed ticket hall and concourse have been remodelled, for use by London Underground and Thameslink passengers.[16] Interchange within the station has been improved by removing the interchange bridge and installing new stairs and lifts with access to all four platforms, allowing passengers with impaired mobility to use the station.[17]

It was necessary to build the Thameslink platform extensions to the south, since there is a sharp gradient to the immediate north of the station. This resulted in the two-station branch to Moorgate being permanently closed.[18] The platform extensions cross the former Moorgate line and reach within a few metres of the entrance of the Snow Hill Tunnel.[19] The alternative of realigning both the Thameslink and Circle/Hammersmith & City/Metropolitan lines was impractical as the latter crosses over the former on a bridge almost immediately to the north of the station.[19]

Crossrail development[edit]

The Farringdon Crossrail station is being built between Farringdon and Barbican Underground stations and it will have interchanges with both of them.[20] Access at the Farringdon end will be via the new Thameslink ticket hall. Work is anticipated to be completed in 2018.[21][22] Crossrail will link Farringdon to London City Airport and London Heathrow Airport, the Olympic Park in Stratford, Canary Wharf, Bond Street and Oxford Street, and Maidenhead in the west and Shenfield in the east. The station will also be a hub for cross-London travel, being the only station to be on both the north-south Thameslink service and the east-west Crossrail service.[23]

Dual traction current supply[edit]

Warning to drivers heading south from Farringdon in August 2012

Farringdon station is notable because First Capital Connect trains switch between the 25 kV AC overhead supply used to the north of London and the 750 V DC third rail supply used to the south while standing at the platform. The trains that formerly ran to Moorgate used 25 kV AC throughout their journeys.

Until the start of the Thameslink Programme southbound trains that were unable to switch to DC were taken out of service at Farringdon and stabled at Moorgate to prevent them from blocking the core section of the Thameslink route. As this option is no longer possible the catenary has been extended to City Thameslink to enable these trains to continue to the southbound platform[24] at City Thameslink using AC and then return northwards using the new crossover in Snow Hill Tunnel.[25] The pantograph on southbound trains is normally lowered at Farringdon.

Underground trains serving Farringdon use the four-rail 630 V DC system.

Metropolitan line S Stock train at Farringdon

Services[edit]

Farringdon is in the core of the Thameslink network, and is served by First Capital Connect. These Class 377 Electrostar units operate over the Bedford to Brighton route, whilst Class 319 units operate the remaining services.

The London Underground part of the station is served by the Metropolitan, Hammersmith & City and Circle lines, between King's Cross St. Pancras and Barbican.

Farringdon is also served by First Capital Connect trains from Brighton to Bedford, via Gatwick Airport, or from Luton to Sutton or Wimbledon. The stations on either side are City Thameslink and St Pancras International.

Until 20 March 2009, some First Capital Connect weekday peak-hour trains ran into Moorgate and terminated there rather than continuing south to Blackfriars and beyond. These services were withdrawn to allow the junction at the south end of the station to be removed so that the platforms could be extended to take 12-coach trains.

Passengers can still travel from Farringdon to Barbican and Moorgate using the London Underground service.

Farringdon is in Transport for London's Travelcard Zone 1.

Preceding station   Underground no-text.svg London Underground   Following station
towards Hammersmith
Circle line
towards Edgware Road (via Aldgate)
Hammersmith & City line
towards Barking
Metropolitan line
towards Aldgate
National Rail National Rail
St Pancras International   First Capital Connect
Thameslink
  City Thameslink
Blackfriars on Sundays
Disused railways
King's Cross Thameslink
(before December 2007)
  First Capital Connect
Thameslink
(Moorgate Branch)
  Barbican
King's Cross Metropolitan
or
King's Cross York Road
  British Rail
Eastern Region

City Widened Lines
  Barbican
  Future Development  
Preceding station   Crossrail roundel.svg National Rail logo.svg Crossrail   Following station
Crossrail
Line 1
towards Abbey Wood or Shenfield

In popular culture[edit]

In stream of consciousness lyrics, the electronica group Underworld refer to the station as the "tubehole on Farringdon Street" (sic) in their 1993 track "Dirty Epic".[26]

References[edit]

  1. ^ "Step free Tube Guide" (PDF). Transport for London. Archived from the original on 26 January 2014. 
  2. ^ "London and South East" (pdf). National Rail Enquiries. National Rail. September 2006. Archived from the original on 6 March 2009. 
  3. ^ "Customer metrics: entries and exits: 2010". London Underground performance update. Transport for London. Retrieved 26 December 2012. 
  4. ^ a b c "Multi-year station entry-and-exit figures" (XLS). London Underground station passenger usage data. Transport for London. 2014. Retrieved 27 July 2014. 
  5. ^ a b c d e "Station usage estimates". Rail statistics. Office of Rail Regulation.  Please note: Some methodology may vary year on year.
  6. ^ Hardy, Brian, ed. (March 2011). "How it used to be - freight on The Underground 50 years ago". Underground News (London Underground Railway Society) (591): 175–183. ISSN 0306-8617. 
  7. ^ "Farringdon". The National Heritage List for England. English Heritage. Archived from the original on 17 August 2013. 
  8. ^ Rose, Douglas (1999). The London Underground: A diagrammatic history. Capital Transport Publishing. ISBN 1-85414-219-4. 
  9. ^ "The Farringdon Wards of the City of London ... some notes on their history" p5: T Sharp 2000
  10. ^ "Train times 22 March - 16 May 2009 Thameslink route" (PDF). First Capital Connect. Archived from the original on 2009-04-19. 
  11. ^ "Farringdon foundations laid" (PDF). Railway Herald. Archived from the original on 2011-07-15. "See page 7" 
  12. ^ "Whats happening at Farringdon?". Network Rail. Archived from the original on 2011-06-23. 
  13. ^ "The new Farringdon station". Network Rail. Archived from the original on 2012-10-08. 
  14. ^ Network Rail (2004a) - pg.27, paragraph 2.6.5
  15. ^ "Thameslink 2000 Environmental Statement: Addendum" (PDF). Network Rail. 1 July 2005. Archived from the original on 2007-09-25. "See page 15, paragraph 2.2.1" 
  16. ^ Network Rail (2004a) - page 27, paragraph 2.6.3
  17. ^ Network Rail (2004a) - pg.27, paragraph 2.6.4
  18. ^ Network Rail (2005a) - pg.9, paragraph 2.1.1
  19. ^ a b Network Rail (2005a) - pg.9, paragraph 2.1.5
  20. ^ "Farringdon" (PDF). Crossrail. 28 October 2006. Archived from the original on 2007-09-28. 
  21. ^ "Crossrail website". Crossrail. Archived from the original on 2010-04-23. 
  22. ^ "Capital's key services protected, says Johnson". The Press Association. 20 October 2010. 
  23. ^ "Farringdon Station". Crossrail. Archived from the original on 2011-04-30. 
  24. ^ Network Rail - 'Kent & Sussex Sectional Appendix', LOR S0280, Seq 001, "Farringdon to City Thameslink" (last updated 31 December 2010)
  25. ^ "City Thameslink ('Powered Up' section)". Thameslink Programme FAQ. Archived from the original on 2010-03-30. 
  26. ^ "Underworld – Dirty Epic". SongMeanings. Archived from the original on 2010-08-18. 