Goldisthal Pumped Storage Station
| Goldisthal Pumped Storage Station | |
|---|---|
The power station on the banks of the lower reservoir |
|
|
|
|
| Country | Germany |
| Location | Goldisthal |
| Coordinates | 50°30′26″N 11°00′18″E / 50.50722°N 11.00500°ECoordinates: 50°30′26″N 11°00′18″E / 50.50722°N 11.00500°E |
| Status | Operational |
| Construction began | 1997 |
| Commission date | 2003/2004 |
| Owner(s) | Vattenfall |
| Reservoir information | |
| Reservoir capacity | 12,000,000 m3 (9,729 acre·ft) (active) |
| Reservoir capacity | 18,900,000 m3 (15,322 acre·ft) |
| Pumped-storage station information | |
| Pump-generators | 4 x 265 MW Francis pump turbines |
| Hydraulic head | 302 m (991 ft) |
| Power generation information | |
| Installed capacity | 1,060 MW |
| Annual generation | 1,806 GWh |
The Goldisthal Pumped Storage Station is a pumped-storage power station in the Thüringer Mountains at the upper run of the river Schwarza in Goldisthal, Germany. It was constructed between 1997 and 2004. It has an installed capacity of 1,060 MW, the largest hydroelectric power plant in Germany and one of largest Europe.[1]
Contents |
Facility [edit]
The upper reservoir is located at an altitude of 880 m (2,887 ft). It has an active (or usable) capacity of 12 millions m³ and a surface area of 55 hectares. In order to create this basin, the mountain summit was cleared away. This quantity of water is enough for eight hours of operation. This corresponds to a maximally storable electric power quantity of 8.5 GWh with the existing elevator difference between storage basins and turbines. Two 800 m long penstocks, which are bent against the horizontal around 25 degrees serve as a conduit for water transfer. The lower reservoir has a capacity of 18.9 million m ³. The power station contains four 265 MW Francis pump turbines.
Construction [edit]
From the outset planning was very disputed for the building of this power station and led to the broad resistance with environmental protection groups, in particular from the Green League. The project was first considered in 1965 and in 1975 geological investigations were carried out. Plans were halted in 1980/1981 due to funding issues but were reinvigorated in 1988. Construction eventually began in 1997 and the first generators were commissioned in 2003. It was officially opened on 30 September 2003 . In 2004, all four generators were commissioned. The construction costs amounted to 600 million euros.
References [edit]
External links [edit]
- Goldisthal PSPS at Vattenfall