Huxley Hill Wind Farm
| Huxley Hill Wind Farm | |
|---|---|
|
|
|
| Country | Australia |
| Location | King Island, Tasmania |
| Coordinates | 39°56′29″S 143°52′26″E / 39.94127825°S 143.87395767°ECoordinates: 39°56′29″S 143°52′26″E / 39.94127825°S 143.87395767°E |
| Status | Operational |
| Commission date | 1998 |
| Owner(s) | Hydro Tasmania |
| Turbine information | |
| Turbines | 3 X 250 kW 2 X 850 |
| Manufacturer(s) | Nordex Vestas |
| Model(s) | N26 |
| Wind farm information | |
| Type | onshore |
| Power generation information | |
| Installed capacity | 2.5 MW |
Huxley Hill Wind Farm (also known as the King Island Wind Farm) is a wind power station at King Island, Tasmania, Australia, of around 1600 residents, owned by Hydro Tasmania, which supplements the four diesel generators with a combined capacity of 6 MW at Currie Power Station. King Island also has a 100 kW solar capacity provided with monocrystaline solar panels on dual-axis arrays.
The wind farm started generating in 1998, initially with three 250 kW Nordex N26 wind turbines at a cost of $2.5 M ($3,300/kW) [1], then in 2003 with two 850 kW Vestas Turbines, to provide a total wind generating capacity of 2.5 MW of electricity. Wind generation provides around 35% of the annual generation. [2]
As a declared Community Service Obligation, the Tasmanian Government provides around $7 million per annum in funding support for the electricity supply equivalent to around $2,500 per resident per annum. [3]
[edit] Flow battery storage
During the 2003 expansion a vanadium redox flow battery was installed at a cost of $4M (or $20,000 per kW)[4], containing 55,000 litres of vanadium based electrolyte—one of the first such installations on a wind farm. However as of 2008, the battery is no longer operational [5]. This allowed up to 800 kWh of surplus electricity to be stored. The battery has an output power of 200 kW, making up around 3% of total capacity, and could be used to smooth the substantial variability in wind output over minutes to hours. When used in conjunction with a variable resistive load, a higher wind penetration is possible, permitting the substantial second to second variability to be controlled with the resistor, reducing the need to spill excess wind through throttling of the turbines. A short-term peak output of 400 kW can be supplied. As a result there has been a substantial reduction in the use of diesel fuel, however the full diesel capacity must be maintained, including the need to maintain spinning reserve for system security.[6]
[edit] See also
[edit] References
- ^ ABS - Feature Article - King Island wind farm
- ^ Hydro Tasmania - Currie Power Station
- ^ Hydro Tasmania - Powering the Bass Strait islands
- ^ http://ssis.arts.unsw.edu.au/tsw/REcant.html
- ^ Bass Strait Islands Electricity Price Inquiry 2008
- ^ King Island - Towards a sustainable energy future - presentation
|
|||||||||||||||||||||||
|
|||||||||||||||||||||||||||||