Jump to content

Mexico City Metro overpass collapse

Coordinates: 19°18′18″N 99°03′41″W / 19.3049°N 99.0613°W / 19.3049; -99.0613
From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Tbhotch (talk | contribs) at 17:00, 17 October 2023. The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Mexico City Metro overpass collapse
The bridge lies collapsed in a V-shape, with two train cars on each side of the tracks.
Investigators on site the night of the collapse
Map
Details
Date3 May 2021 (2021-05-03)
22:22 CDT (UTC-5)
LocationTezoncoOlivos elevated interstation
Tláhuac Avenue, Tláhuac, Mexico City
Coordinates19°18′18″N 99°03′41″W / 19.3049°N 99.0613°W / 19.3049; -99.0613
CountryMexico
LineLine 12
OperatorSistema de Transporte Colectivo (STC)
Incident typeRailway collapse
CauseLack of functional studs and poor welds that led to fatigue in the collapse point
Statistics
Trains1
Vehicles1
Crew1[2]
Deaths26[1]
Injured98[1]

On 3 May 2021, at 22:22 CDT (UTC−5), a girder overpass in the borough of Tláhuac carrying Line 12 of the Mexico City Metro collapsed beneath a passing train. The overpass and the last two cars of the train fell onto Tláhuac Avenue near Olivos station, killing 26 people and injuring 98 others. It was the Metro's deadliest accident in almost fifty years.

The line experienced technical and structural problems that led to a partial closure of the elevated section where the accident occurred between 2014 and 2015. An earthquake in 2017 further damaged the span; although it was repaired within a few months, residents reported problems still existed years later. The line was announced in 2007 as an underground line with the possibility of operating rubber-tired trains because of the instability of the city's soil. The line was scheduled to be opened by 2010 but due to the budget and time constraints, the project was modified to operate both underground and overground with steel-wheeled trains, which researchers have named as one of the causes of track instabilities and damage since the beginning of the line's operations. Empresas ICA, the company that built the system's other lines, constructed it with Alstom Mexicana and Grupo Carso—the latter owned by Carlos Slim.

Claudia Sheinbaum, mayor of the city, hired the Norwegian risk management firm Det Norske Veritas (DNV) to investigate the causes of the collapse; preliminary investigations found it was related to deficiencies in the construction of the bridge, and a lack of functional studs and poor-quality welds that led to fatigue in the collapsed beam. Further investigations led them to conclude the bridge was designed and built without quality standards, that the construction and the line's design changes had been inadequately supervised, that there was a lack of fixing and safety elements, and that periodic maintenance checks that would have detected the girder buckling had not been done—the last statement being contested by the city government.

Carso, the company responsible for the construction of the collapsed section, denied any wrongdoing but Slim agreed with the government of Mexico to repair the section free of charge. In December 2021, the office of the city's attorney general filed charges against ten former officials—including the project director—who were involved in the construction and supervision of the project in December 2021; as of November 2024, these are awaiting trial for manslaughter, injury, and property damage.

Background

Metro system

The Sistema de Transporte Colectivo (STC) operates the Mexico City Metro,[3] one of the world's busiest urban transportation systems that carries around 4.5 million passengers a day.[4][5] STC, which commenced operations in 1969, is the second-largest metro system in North America after the New York City Subway system.[6]

Prior to the collapse, the rail system had shown signs of deterioration, and concerns about its maintenance were raised.[7][8] In March 2020, two trains collided at Tacubaya station after one driver failed to follow parking protocols, causing the train's brakes to fail.[9] In January 2021, a fire in the Metro's downtown headquarters killed a police officer, hospitalized 30 people,[6][7] and took six subway lines out of service for several days.[10][11] In April, Line 4 was closed after a fire on the tracks.[12]

In December 2018, the recently appointed mayor of Mexico City Claudia Sheinbaum appointed Florencia Serranía to the position of STC general director. Serranía had served in the same position from 2004 to 2006 during the governorship of Andrés Manuel López Obrador, who was President of Mexico when the collapse happened.[13] From 2020 to April 2021, the post of STC deputy director-general of maintenance was vacant and Serranía assigned herself as manager of the position.[14][15]

Line 12

A map showing the route and stations of Line 12
Line 12 map

Line 12, also known as the Golden Line in reference to its color on the system map, runs from south-central Mexico City to the semi-rural, southeastern borough of Tláhuac, serving around 350,000 passengers per day.[8] As of November 2024, it is the newest line on the Metro.[7] It was constructed by Empresas ICA in association with Alstom Mexicana and Grupo Carso.[16] The head of government of Mexico City Marcelo Ebrard announced the line in August 2007,[17] and construction began in September 2008.[18] The opening was expected to coincide with the 200th anniversary of Mexico's independence in 2010,[19][20] but multiple construction delays postponed its inauguration by Ebrard and president Felipe Calderón to October 2012.[7][21][22] The project's cost of MX$26 billion (US$1.29 billion as of 2021) exceeded projections by about 50 percent.[21][23]

Line 12 runs underground through central parts of the city and is elevated in outlying areas.[24] The line was originally planned to be built mostly underground, and was to have 23 stations—20 of them from Mixcoac to Nopalera underground; and the last three—Zapotitlán, Tlaltenco and Tláhuac—were planned as at-grade stations.[25] Due to budget constraints, the project was modified to have nine underground stations from Mixcoac to Atlalilco, nine elevated stations from Culhuacán to Zapotitlán, and Tlaltenco and Tláhuac as at-grade stations.[19] The elevated inter-station sections were built with concrete columns that carry two parallel metal beams to support the girders; the foundations are built on rocky soil.[26]: 54 

Rolling stock

A steel-wheeled train leaves a station.
An outbound FE-10 at Calle 11 station

The FE-10 train model, which was manufactured by Construcciones y Auxiliar de Ferrocarriles (CAF), is exclusively used on Line 12. The FE-10 uses steel wheels, whereas other lines in the system, with the exception of Line A, use rubber tires. Francisco Bojórquez, then-general director of the Metro system, recommended using rubber tires, which he considered to be a more-secure option but an internal labor commission disagreed with his opinion and supported the use of less-costly steel wheels.[27] Line 12 was designed in a similar way to Line A, taking into consideration the specifications of Bombardier trains, which have a width of 2.50 meters (8 ft 2 in) and a weight of 170 metric tons (170 long tons; 190 short tons) per railcar. The FE-10 trains are wider and heavier, being 2.80 meters (9 ft 2 in) wide and weighing 240 metric tons (240 long tons; 260 short tons) per railcar.[28][29] FE-10 trains have a capacity of 1,900 passengers and are gangway models, allowing users to move between cars.[26]: 40 

CAF received a concession for the trains from 2010 to 2026 with a US$1.588 billion contract; it was the first time STC did not directly buy the trains.[30] SYSTRA, a multinational engineering and consulting group, wrote train operations were within the accepted safety limits.[31] Technischer Überwachungsverein recommended replacing the trains due to excessive wear of the wheels and rails caused by the mismatch between both.[32]

Line 12 issues

A picture of Line 12's overground track with a train passing by.
The OlivosTezonco viaduct in 2016. The accident occurred near the Vips and Walmart signs, which can be seen on the far left.

From the start of service, Line 12 experienced problems with trains on elevated sections. Before the start of pre-operational testing with trains, topographic monitoring detected subsidence on several columns.[29] Personnel recorded vibrations on the tracks in the Tláhuac borough area. Passenger testing began in June 2012; in the subsequent months, the Metro system recorded damage to around 10,000 ties due to vibrations.[29] The operations necessitated speeds as low as 5 km/h (3.1 mph) on some segments; a congressional report noted coupling the unprotected rails with wheels that do not meet the required standards could cause trains to derail.[7][21] In March 2014, the elevated section was closed for 20 months for repairs of technical and structural faults.[7][33] The government of the city created a special board to investigate the causes of the problems and hold officials accountable for the errors that led to the partial closure.[34] Among those investigated was Ebrard, who went into self-imposed exile in France in 2015, saying he was the target of a political vendetta created by Miguel Ángel Mancera, his successor.[35][36][37] Thirty-three officials and ex-officials, including Enrique Horcasitas, the director of the Line 12 project, were sanctioned with disqualifications from public work, fines, or both.[38]

In 2014, the government of Mancera hired SYSTRA to independently submit a report on their investigation. After the group reviewed over 2,900 documents and tested the tracks,[39] the team concluded errors were made during the "planning, design, construction and operation" of the line.[40] In a non-public report published by SinEmbargo.mx after the collapse, SYSTRA added the wear and tear of the work was unusual for an up-to-two-years-old project, which they attributed to "mediocre quality" works. The group concluded to avoid future problems, the Metro system would need to correct the origin of the wear because repairs would be temporary fixes and the defects would return. They informed governmental authorities it would not be possible to permanently solve the problems and suggested to the creation of a maintenance manual based on the needs of the line to perpetually maintain it.[41]

In 2015, the Superior Auditor of the Federation (Auditoría Superior de la Federación; ASF) concluded the construction process presented 12 irregularities, including the incompatibility between the train wheels and the rails that could cause track instabilities, and that train operations were within the accepted safety limit.[42] According to Florencia Serranía, in 2016, the French company Tricaud Societé Organisé (TSO) was contracted to maintain daily operating conditions of the line's fixed installations and did not report any concerns before the collapse.[43] The cost to address these problems was over MX$1.2 billion.[44]

The 2017 Mw7.1 Puebla earthquake damaged the line's tracks and forced six stations, from Tezonco station to the eastern terminal, to temporarily close.[24][45] Tezonco and Olivos stations were reopened three days later; Olivos served as the provisional terminal station for about a month while the other stations underwent repairs.[46][47] Experts told Associated Press reporters the line needed to be closed and thoroughly inspected rather than being reinforced.[24] The ASF made observations of damage to the section that ultimately collapsed.[48] Following the earthquake, residents had reported the structure showed visible structural cracks. Transport authorities made repairs following these complaints.[4] They also repaired a column between Olivos and Nopalera stations that showed cracks in its base in January 2018.[49][50] Before the 2020 COVID-19 pandemic, residents provided photographs and videos to the authorities for them to review the bridge, which the residents perceived was buckling and that the structure was moving abnormally as trains passed by.[51] By the end of 2019, engineering company Ingeniería, Servicios y Sistemas Aplicados (ISSA) conducted a study of the structural and geotechnical behavior of the overpass, finding no risk to the line's operation.[43]

Collapse

Multiple concrete columns and girders under construction
Line 12 bridge under construction in 2010 a few meters away from Olivos station. The accident occurred when a steel girder similar to those pictured collapsed.

On 3 May 2021 at 22:22 CDT (UTC−5),[52] an eastbound train was passing on the track between Olivos and Tezonco stations in Tláhuac.[53] Around 220 meters (720 ft) before reaching Olivos station,[54] the section between columns 12 and 13[55] collapsed when its girder failed and broke in half, causing the rear two train cars to fall off the track.[56][57] The fallen cars were suspended in a V-shape with one car hitting the ground and the other left dangling.[21][58] Debris fell onto an automobile traveling on Tláhuac Avenue, killing the driver and injuring his wife.[59] The overpass is about 5 meters (16 ft) above ground level but was situated above a concrete median strip, which minimized casualties among motorists and pedestrians on the ground.[60]

A total of 26 people—15 of whom died at the scene—died in the collapse;[61] and 98 others were hospitalized.[1] It was the Metro's deadliest incident since 1975, when a collision between two trains killed 31 passengers;[62] it was also the system's third fatal accident in 14 months.[56] After the collapse, 22 people were reported missing.[63] By 6 May, the number of unaccounted-for people decreased to five.[64] According to the city government, it is likely none of them were on board the train because they had been missing since days before the accident.[65]

According to Rodrígo García, the driver of the crashed train, meters before arriving at Olivos station he perceived a jolt in the train, after which his control board indicated a power failure. García activated the emergency brake, left the cab, and saw smoke and passengers leaving the train in the last car. The control center asked him to verify the situation and to reassure the passengers if necessary. He was subsequently notified of the collapse. In the fifth-and-last-available car, García found injured and unconscious people. He estimated the train was three-quarters full.[66]

The STC warned residents to avoid the area.[67] Immediately, witnesses began rescue efforts[51][68] and were later joined by first-response teams.[69][70] Neighbors offered rescuers coffee, water, and bread.[71][72] A shopping mall in the zone emptied its parking lot and allowed authorities to set up a control post.[73] Rescue efforts were suspended after a few hours because the structure was unstable.[74] A crane was dispatched to hoist sections of the train while search-and-rescue teams searched for survivors.[75] The first train car was removed the next day at 09:20 CDT and the other before 14:00 that day.[73] The debris had been removed by the end of May.[76][77]

Immediate aftermath

One of the railcars is being lifted by a crane. Behind it, the second railcar still hanging. Below them, a car is seen below the debris.
A railcar being lifted the day after the accident

Service on the entirety of Line 12 was suspended.[78][79] The following day, the line was replaced with 490 city buses, which were insufficient to meet passenger demand. To complement the service, the city contracted buses from the company Autobuses de Oriente,[80] and approved temporary routes toward Tasqueña, Universidad,[81] Atlalilco,[82] and Coyuya metro stations.[83] The federal government declared three days of national mourning.[84] Social media users reported structural damage at other elevated stations, including Oceanía, Consulado, and Pantitlán; Sheinbaum said the stations would be examined.[85] The general secretary of the Mexican Union of Metro Workers announced around 8,000 workers would go on strike due to unsafe working conditions.[6][62]

The office of the federal Attorney General (FGR), its Mexico City counterpart (FGJCDMX) headed by Ernestina Godoy Ramos, and Norwegian risk management firm Det Norske Veritas (DNV) were appointed to investigate the collapse.[86][87] Sheinbaum said the families of those who were killed would receive MX$700,000 (US$35,000) each, including MX$50,000 (US$2,500) from the city and MX$650,000 (US$32,650) from the Metro.[86] The compensation was later increased to MX$1,870,000 per family.[88]

When Serranía was asked about satellite images that showed the collapsed section was slightly warped, she said; "There is no such information, it is not true".[43] National Regeneration Movement (MORENA), the ruling party of Mexico, voted against creating a special commission to investigate the collapse, calling it a "scavenger" proposal because the collapse had no "urgent and obvious resolution".[89] Sheinbaum and Ebrard, the then-current and former heads of government of Mexico City, are protégés of president López Obrador and have been considered leading candidates of MORENA for the 2024 presidential election.[90] According to international journalists, the collapse may affect their presidential campaigns because Ebrard had overseen the construction of Line 12, which was considered his "signature infrastructure project", while Sheinbaum had over two years to address concerns regarding the line's condition and to ensure the line was properly maintained.[6][23][90]

Reactions

Minutes after the collapse, Sheinbaum arrived at the accident site.[91] Ebrard, the Secretary of Foreign Affairs when the incident happened, said on Twitter; "What happened today in the Metro is a terrible tragedy ... My sympathy to the victims and their families".[92] The following morning, president López Obrador gave his condolences and said; "Nothing will be hidden, we should not fall into speculations ... no accusations will be made without evidence".[56][93] Carlos Slim's Grupo Carso, the main constructor of the Periférico Oriente–Zapotitlán section, announced they would wait for the official expert analyses before offering any statement on the incident.[94][95]

Protests and tributes

Twenty-six crosses with the names of the deceased are on the protective fence of Olivos station.
Day of the Dead altars in honor of the victims at Olivos station

In the days following the collapse, protesters who were upset over the incident and the authorities' responses vandalized several Metro stations, breaking glass platform partitions and painting slogans such as "It wasn't an accident—It was negligence" on station walls.[96][97] Demonstrators marched from Periférico Oriente station to the accident site carrying banners that read "It was not an accident, those responsible have first and last names" and "Corruption kills and the dead are always the people".[98] Residents set up an altar in a shopping mall near the site of the collapse.[99] On 7 May, hundreds of protesters demanding justice held a vigil at the scene of the accident.[100]

For the Day of the Dead observance in 2021, local residents called on others to place a thematic altar called "Train to Mictlān".[101] On the eve of the first anniversary of the collapse, the National Action Party (PAN), an opposition party, placed an anti-monument on Paseo de la Reforma in front of the Antimonumento +43 memorial. The PAN anti-monument references the overpass collapse and includes the legends "#FueMorena" (#ItWasMorena) and "La tragedia de la Línea 12" (The tragedy of Line 12) on a wine-colored plinth, referencing MORENA's institutional colors.[102] On the anniversary of the collapse, family members, survivors, and residents visited the site, where they placed altars and candles. They told journalists they would ask the city council for permission to place a memorial in front of the collapsed area.[103]

Investigations

DNV report

A damaged concrete slab showing incorrect distances in relation to stud placement
A girder with multiple poorly welded studs.
A broken stud due to a poor welding work
Some photographs from the first DMV report explaining the root cause of the collapse. They show examples of improperly executed welds (bottom) and incorrect stud distribution (top and center).

On 5 May 2022, the government of the city contracted DNV to conduct a detailed, independent investigation into the collapse.[104] It was decided to split it into three parts and each would receive a payment: the first part, which cost 8,169,343 pesos, would discuss the preliminary causes that led to the accident; the second part was to include the immediate cause and cost 5,049,743 pesos; and the final part, costing 9,394,914 pesos, would include the root cause and recommendations for the line's reopening.[105][106] According to the contract, DNV was allowed "to collect information for documentary analyses, covering design, construction, rehabilitation, intervention, operation, maintenance and supervision" of the line until the date of the collapse.[107]

DNV published the first part of the report on 16 June 2021; it found structural faults linked to six construction deficiencies:[108]

  • A poor welding process of Nelson studs
  • Porosity and lack of union in the stud–beam joint
  • Lack of Nelson studs in the beams that span the bridge assembly
  • Different types of concrete were used on the girder
  • Unfinished and/or improperly executed welds
  • Supervision and dimensional control in fillet welds

DNV investigated the appropriateness of the design and materials used for the line; whether the structure's performance fulfilled the design requirements; and whether the operations, repairs, and renovations had affected the bridge.[108] The group reported fewer studs than required to support the structure had been used, and that the concrete that covered them might have been faulty.[109] The firm also noted in August 2010, supervisors issued an alert related to the construction of the Tezonco–Olivos overpass stating only ten reinforcement bars were to be used in the bridge, although the project plans originally specified twenty of them.[110] According to El Financiero, the report excluded four additional lines of research; "lateral-torsional buckling of the steel beams", "crushing of the concrete slab", "influence of loads from the railroad system", and "lack of infrastructure maintenance".[111]

DNV was expected to deliver the second part of the report on 14 July 2021,[105][112] however, the group postponed it until 7 September that year. In the 180-page investigation, DNV concluded the collapse was caused by the lack of functional Nelson studs in the stretch, which led to the buckling of the north and south beams. This led the girders to work independently from each other in conditions for which they were not created, driving the distortion to the central transverse frame and causing fatigue in the support. Poor distribution of the existing studs and poor welds in the zone further contributed to the collapse.[113][114]

The third part of the report was expected in August 2021[105] but it was delivered on 28 February the following year.[115] The city's government rejected the report's conclusions and reserved its publication. Sheinbaum acknowledged the report on 4 May 2022 and said it was declined because it was a "deficient, poorly produced, ... tendentious and false" document that presented "technical issues"; that it serves the country's opposition parties; that DNV unilaterally changed the methodology the group originally presented when it was hired; and she said the company had a conflict of interest because one of DNV's lawyers had previously litigated against López Obrador. She also announced a civil lawsuit against DNV and that the firm would not receive a payment for the last part of the report.[116][117][118] Andrés Lajous, the head of the city's Secretary of Mobility, explained that the change in the report's methodology referred to DNV's decision to "plant maintenance" as a cause of the collapse.[119] DNV said their report was delivered "in accordance with the agreed RCA [root cause analysis] methodology and to strict internal quality and revision procedures".[107] According to journalist investigations, DNV's lawyer was hired in 2019.[120]

On 9 May 2022, the Spanish newspaper El País published part of the third report. DNV concluded the root cause of the accident was the bridge's design's non-compliance with the standards for bridge construction; a lack of certification by an independent entity—including deficient supervision and changes to the original design; misplaced, poorly welded, or missing studs throughout the girders; and lack of maintenance inspections from 2012 to 2019, even though the manual delivered by ICA–Carso–Alstom recommended thorough annual inspections.[121][122] The city government released the report two days later and explained in a conference the discrepancies they found in it. Officials said they opposed the report because DNV did not compare the collapsed section with similar segments; because the firm used Google tools—including Google Street View—despite the existence of a disclaimer that said data may not reflect actual conditions; because DNV initially stated the deformations were not visible to the naked eye but later said the opposite by using Google Street View images; because the ICA–Carso–Alstom maintenance manual did not establish methodologies for deformation criteria; because the report initially says no maintenance reports were delivered and then acknowledged there are reports for 2019 and 2020; and because the group did not adhere to the requested methodology.[123] Sheinbaum announced the contract with DNV would be rescinded and a group of engineers would be hired to "present the whole truth".[124]

Other investigations

Photograph of a concrete bridge above an avenue
Concrete girders used by ICA (pictured near Zapotitlán station). The College of Civil Engineers of Mexico found, unlike the steel girders used by Carso, of which all presented vulnerabilities, these showed "minor and common deficiencies" along the overpass.[125]

Three days before DNV released its report, journalists from The New York Times (NYT) published an investigation. The NYT report said the collapse was due to a chain of errors originating in its planning; that the line was hurriedly built as the end of Ebrard's administration was approaching; that the steel studs connecting steel to a slab of concrete failed due to poor-quality welds and the failure to remove ceramic rings; that the city had approved poor-quality work; and that after the 2017 earthquake, audits revealed errors in the original construction—including missing steel components and improperly poured concrete.[126] Sheinbaum criticized the NYT article and said she did not leak information to a journal that denounced the Fourth Transformation—the president's political platform.[127] Ebrard said the collapse was caused by the lack of maintenance rather than by structural faults.[128]

In their investigation, the FGJCDMX found similar results to those of DNV's first report. According to the FGJCDMX report, shear bolts that joined the concrete slabs to the beams were misplaced and in some cases, the bolts and beams were not fused, leading to distortion-induced fatigue. The attorney concluded the collapse occurred when the eastbound beam suddenly yielded and dragged the westbound beam in 1.9 seconds.[129][130] According to a study carried out by specialists hired by the attorney general's office, the collapsed section had 65 percent of the required bolts.[131] According to a related study, specialists could not find evidence of inspection reports of problems related to the bridge. The same study said the existing malformations and defects would have been detected if these examinations had been carried out in a specialized manner through appropriate maintenance.[132]

The College of Civil Engineers of Mexico (Colegio de Ingenieros Civiles de México; CICM) conducted independent studies of Line 12, except for the collapsed area. They observed the bridge has two types of girders: from Culhuacán to Calle 11 stations—built by ICA—[125]the section uses concrete girders and from Calle 11 to Zapotitlán stations—built by Carso—[94][125]the overpass uses steel girders. They also found 68 percent of the elevated section had minor and common deficiencies. In comparison, the remaining 32 percent—all within the section between Periférico Oriente and Zapotitlán stations—presented vulnerabilities that would require additional analyses. These vulnerabilities include poor welds, improper spacing between beams, fissures in columns and beams, and irregularities in the steel structure support.[125][133]

Planned reopening

The bridge of the subway system with its respective missing section.
The collapse site in January 2022 prior to the start of reconstruction work

According to Sheinbaum, reconstruction of the collapsed section was expected to be completed by the end of 2022.[134] A week after the collapse, STC considered reopening only the underground section.[135] In their report, the CICM recommended against reopening unless a reinforcement and rehabilitation project is conducted.[136] The institute also advised against reopening the underground section because the railway workshops, which are needed for train maintenance, are located after Tláhuac station.[137]

In June 2021, Sheinbaum discussed with ICA and Carso the possibility of them paying for the reconstruction of the elevated section.[138] On 22 June, López Obrador met with Sheinbaum and Slim, and they agreed Slim would help with the reconstruction, which López Obrador said should be carried out "as soon as possible",[139] and "that within a year at the latest, Line 12 [would] be back in operation with full safety".[140] A week later, López Obrador said Carso agreed to rebuild the collapsed section free of charge,[141][142] and Slim commented:

I am convinced that [the line] was made with the best structural engineers of Mexico, who did the calculations, the design, and if you recall it, in October 2012, around November ... the project was approved, which was performed by international experts, and for that, I am convinced that it has no inherent vices. So much so that the President of the Republic, the head of government and the head of government-elect boarded it, and they invited us and lots of people to travel, we traveled around 12 kilometers [7.5 miles].[a]

Reconstruction work on the collapsed section started on 16 February 2022.[144] A total of 6.7 km (4.2 mi) will be strengthened with column reinforcements and supports based on struts, diaphragms, and tensors; and girder located 200 metres (660 ft) from the accident site will be dismantled and rebuilt.[145] According to the Guacamaya Leaks [es], multiple Internet leaks of classified documents of the Secretariat of National Defense by the hacktivist group Guacamaya [es], Mexico City authorities asked the army to donate 20,000 t (20,000 long tons; 22,000 short tons) of steel to reinforce the girders in the elevated section of the line, which was originally intended for the canceled Texcoco Airport; the army provided 13,000 t (13,000 long tons; 14,000 short tons).[146] Sheinbaum confirmed the leaked information and said the material that was not used in the construction of Felipe Ángeles International Airport was used for the reinforcement of Line 12.[147]

The subway section of Line 12, which runs from Mixcoac to Atlalilco stations, reopened on 15 January 2023.[148] In preparation for the reopening, 15,000 ties and rails in several interstation tunnels were replaced, leaks were repaired, and the track ballast was replaced with a firmer material. The section will operate with 13 trains and will be patrolled by members of the National Guard—the gendarmerie force command of the Secretariat of National Defense—placed inside all of the metro stations days after the 2023 Mexico City Metro train crash occurred; Sheinbaum said the system was under attack from saboteurs.[149] The next section, running from Culhuacán to Periférico Oriente stations, opened on 15 July 2023.[150]

Aftermath and litigation

After the release of the first DNV report on the collapse, Grupo Carso lost 7.8 billion pesos on the Mexican Stock Exchange.[151] The company lost a further 2.7 billion pesos after they announced they would rebuild the collapsed section.[152] Florencia Serranía was removed from her position on 28 June 2021 and was replaced by Guillermo Calderón, the Servicio de Transportes Eléctricos general director.[153] Days before the delivery of its second report, DNV filed a complaint with the FGJCDMX due to a breach in the chain of custody of a package containing evidence that was sent to the United States for further studies. When the package returned to Mexico, the box containing the samples had been tampered with, potentially affecting the investigation.[154]

In August 2021, the FGJCDMX began an investigation of eleven welders and two supervisors.[155] In October that year, the office announced charges of manslaughter, injury, and property damage would be brought against Line 12 project director Enrique Horcasitas, and nine former officials and supervisors—several of whom were disqualified in 2014 and 2015 from holding any public office in Mexico City—for their participation in the planning and construction of the line.[156][157] Horcasitas' defense said the errors occurred when the city wanted to modify the original project—including the contracting of companies other than those stipulated—and that the line's infrastructure had not been properly maintained since its opening.[158] According to the attorney, who also defended four others, the Spanish version of DNV's report omits information related to maintenance on the line.[159] The ten ex-officials were formally charged in December 2021 and, as of January 2023, are awaiting trial.[160]

Carso estimated the reconstruction and reinforcement of the collapsed bridge will cost the company 800 million pesos.[161] In November 2021, the group said in 2010 it subcontracted the stud-welding company J. J. Jiménez, S. A. de C. V. and that Carso subsequently supervised the work through a verification system that evaluated the welding of the studs, their alignment, and their final positions.[162]

By February 2022, 80 percent of those involved had received compensation from Carso's CICSA division in a deal in which no-one would take legal action or request further sums of money in the future.[163] By May that year, the amount had increased to 90 percent.[164] The range of compensation varied according to the seriousness of the injuries from 450,000 pesos (US$21,600) to six million pesos (US$290,000)—the latter for the families of the dead victims. The company also reserved the right to demand reimbursement of the compensation paid to the victims from those found legally responsible for the collapse, and to take legal action against responsible parties.[163][165][166] In February 2022, the remaining parties who had not signed the compensation deal were in the process of taking legal action against Carso.[167]

Notes

  1. ^ Original text in Spanish: "... estoy convencido de que la hicieron los mejores calculistas de México, hicieron los cálculos, el diseño y si recordarán en octubre de 2012, por ahí de noviembre [...], se dio el visto bueno al proyecto, lo que se había hecho por expertos internacionales, lo cual estoy convencido que desde su origen no tiene vicios. Tan es así que se subió el presidente de la República, el jefe de Gobierno y el jefe de Gobierno electo y nos invitaron a muchas gentes a recorrer, recorrimos como 12 kilómetros".[143]

References

  1. ^ a b c Piña, Jessica (2 May 2022). "A un año del accidente de la Línea 12 del metro" [A year after Metro Line 12's accident]. MVS Noticias. Archived from the original on 2 May 2022. Retrieved 7 May 2022.
  2. ^ Olvera, Dulce (4 May 2021). "El conductor del tren de la L12 está hospitalizado. Trabajadores exigen revisar todo el Metro" [The driver of the L12 train is hospitalized. Workers demand to overhaul the entire Metro]. SinEmbargo (in Spanish). Archived from the original on 5 May 2021. Retrieved 5 May 2021.
  3. ^ "Mexico City Rapid Transit Metro, Mexico - Railway Technology". Railway Technology. Archived from the original on 6 May 2021. Retrieved 5 May 2021.
  4. ^ a b "Mexico City metro overpass collapse kills 23". BBC News. 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  5. ^ "Afluencia de estación por línea 2019" [Station traffic per line 2019] (in Spanish). Sistema de Transporte Colectivo Metro. 2020. Archived from the original on 8 April 2020. Retrieved 4 May 2021.
  6. ^ a b c d Sheridan, Mary Beth (4 May 2021). "Mexico City subway overpass collapses; at least 13 dead as metro cars topple". The Washington Post. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  7. ^ a b c d e f Lopez, Oscar; Ives, Mike; Taylor, Derrick Bryson (4 May 2021). "Mexico City's metro has been plagued by problems". The New York Times. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  8. ^ a b Agren, David (4 May 2021). "Anger mounts as death toll from Mexico metro overpass collapse rises to 24". The Guardian. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  9. ^ Navarro, Israel; Alzaga, Ignacio (1 April 2021). "Choque del Metro Tacubaya, por falla humana; enjuiciarán a dos" [Tacubaya station crash caused by human error; two to be prosecuted]. Milenio (in Spanish). Mexico City. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  10. ^ "Reabren líneas 4, 5 y 6 del Metro, el servicio es lento" [Lines 4, 5 and 6 are reopened, service is slow]. Excélsior (in Spanish). 12 January 2021. Archived from the original on 6 May 2021. Retrieved 6 May 2021.
  11. ^ "Ya hay fechas para reabrir las líneas 1, 2 y 3 del Metro" [There are already dates for reopening Metro Lines 1, 2 and 3]. Chilango (in Spanish). 17 January 2021. Archived from the original on 7 May 2021. Retrieved 6 May 2021.
  12. ^ Pantoja, Sara (23 April 2021). "Incendio deja sin servicio "hasta nuevo aviso" la Línea 4 del Metro" [Fire leaves Metro Line 4 without service "until further notice"]. Proceso (in Spanish). Archived from the original on 5 May 2021. Retrieved 5 May 2021.
  13. ^ "Ella es Florencia Serranía, próxima dirigente del Metro de la CDMX" [She is Florencia Serranía, the next head of the CDMX Metro]. El Financiero (in Spanish). 20 November 2018. Archived from the original on 24 June 2021. Retrieved 23 June 2021.
  14. ^ Navarrete, Shelma (4 May 2021). "STC Metro mantuvo vacante un año la subdirección de Mantenimiento" [STC Metro kept the Deputy Directorate of Maintenance vacant for a year]. Expansión (in Spanish). Archived from the original on 24 June 2021. Retrieved 23 June 2021.
  15. ^ Escalona, Hilda (30 April 2021). "Un año después, el Metro ya tiene encargado de mantenimiento" [A year later, Metro now has a maintenance manager]. El Sol de México (in Spanish). Archived from the original on 24 June 2021. Retrieved 23 June 2021.
  16. ^ "¿Quién construyó la línea 12 del Metro?" [Who built Line 12?]. Expansión (in Spanish). 11 March 2014. Archived from the original on 2 July 2020. Retrieved 4 May 2021.
  17. ^ Bolaños, Ángel; Quintero, Josefina (9 August 2007). "Presentó Ebrard el proyecto de la línea 12 del Metro, que irá de Tláhuac a Mixcoac" [Ebrard presented the project for Metro line 12, which will run from Tláhuac to Mixcoac]. La Jornada (in Spanish). Archived from the original on 26 February 2021. Retrieved 20 June 2021.
  18. ^ Castillejos, Jessica (21 September 2008). "Línea 12 arranca construcción a vapor" [Line 12 starts with steaming construction]. Excélsior (in Spanish). Archived from the original on 9 December 2008. Retrieved 4 May 2021.
  19. ^ a b Zamarrón, Israel (6 May 2021). "Línea 12 debió ser subterránea, pero por ahorrar dinero, se hizo tramo elevado" [Line 12 should have been subway, but in order to save money, an elevated section was built]. Forbes México (in Spanish). Archived from the original on 18 June 2021. Retrieved 18 June 2021.
  20. ^ Salgado, Agustín (28 November 2009). "Tramo subterráneo de la línea 12 del Metro obliga a innovar tecnología" [Subway section of Metro Line 12 forces to innovate technology]. La Jornada (in Spanish). Archived from the original on 24 June 2021. Retrieved 20 June 2021.
  21. ^ a b c d Stevenson, Mark (5 May 2021). "Mexico City subway collapse was a tragedy foretold". Associated Press. Archived from the original on 5 May 2021. Retrieved 6 May 2021.
  22. ^ "Calderón y Ebrard inauguran Línea 12 del Metro" [Calderón and Ebrard inaugurate Metro Line 12]. El Economista (in Spanish). Notimex. 30 October 2012. Archived from the original on 5 May 2021.
  23. ^ a b "Mexico City 'Golden Line' under suspicion after crash". France 24. 4 May 2021. Archived from the original on 6 May 2021. Retrieved 6 May 2021.
  24. ^ a b c Castillo, E. Eduardo; Verza, Maria (8 May 2021). "Survivor of Mexico City subway collapse reflects on decision to change cars". WTVD. AP. Archived from the original on 9 May 2021. Retrieved 9 May 2021.
  25. ^ Rosas, Obed (18 June 2021). "L12 va a su tercer remiendo en 7 años en zona que no debió existir" [L12 goes to its third patch in 7 years in an area that should not exist]. SinEmbargo (in Spanish). Archived from the original on 18 June 2021. Retrieved 18 June 2021.
  26. ^ a b Empresas ICA; Grupo Colinas del Buen (October 2012). Anaya González, Daniel (ed.). "Infraestructura: Línea 12 del Metro". Revista Vector (in Spanish). No. 2. ISSN 1909-7891 – via Issuu.
  27. ^ "Una elección contradictoria; Trenes de la Línea 12" [A contradictory election; Line 12 trains]. Excélsior. Mexico City. 7 July 2014. Archived from the original on 20 May 2021. Retrieved 7 September 2021.
  28. ^ "Línea 12: rentó Ebrard trenes más anchos, sin licitar, y reservó datos" [Line 12: Ebrard rented wider trains, without bidding, and reserved data]. La Razón (in Spanish). 13 March 2014. Archived from the original on 5 May 2021. Retrieved 25 September 2021.
  29. ^ a b c Celis, Darío (7 May 2021). "El desastre de la Línea 12". El Financiero (in Spanish). Archived from the original on 18 May 2021. Retrieved 25 September 2021.
  30. ^ Sarabia, Dalila (15 June 2021). "CDMX aún debe 500 mdd por renta de trenes de Línea 12, aunque no den servicio" [Mexico City still owes 500 million pesos for rental of Line 12 trains, even though they don't provide service]. Animal Político (in Spanish). Archived from the original on 17 June 2021. Retrieved 7 September 2021.
  31. ^ Montes, Rafael (8 May 2021). "Estudio francés rechazó daños a la estructura por vibración de trenes" [French report rejected damages to structure due to trains vibrations]. Milenio. Mexico City. Archived from the original on 8 September 2021. Retrieved 8 September 2021.
  32. ^ "Empresa que rehabilita Linea 12 sugiere cambiar los trenes" [Company that rehabilitates Line 12 suggests replacing the trains]. Eje Central (in Spanish). 20 January 2020. Archived from the original on 4 May 2021. Retrieved 8 September 2021.
  33. ^ Rodea, Felipe (29 November 2015). "Mancera reabre Línea 12 del Metro" [Mancera reopens Metro's Line 12]. El Financiero (in Spanish). Archived from the original on 4 July 2020. Retrieved 3 May 2021.
  34. ^ Ramírez, Kenya (18 March 2014). "Lista la Comisión Investigadora de la Línea 12 en la ALDF" [Line 12 Investigation Commission in the ALDF is ready]. Excélsior (in Spanish). Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  35. ^ "Ebrard niega autoexilio en París: dejó México por calumnias en su contra, dice" [Ebrard denies self-imposed exile in Paris: he left Mexico because of slander against him, he says]. Animal Político (in Spanish). 13 August 2018. Archived from the original on 10 September 2021. Retrieved 10 September 2021.
  36. ^ Rodea, Felipe (25 June 2015). "Ebrard huye por temor a 'fuerte venganza'" [Ebrard flees for fear of 'strong revenge']. El Financiero (in Spanish). Archived from the original on 10 September 2021. Retrieved 10 September 2021.
  37. ^ Valero, Marlene (1 February 2018). "¿Por qué se 'exilió' Marcelo Ebrard en Francia?" [Why did Marcelo Ebrard 'go into exile' in France?]. La Silla Rota (in Spanish). Archived from the original on 10 September 2021. Retrieved 10 September 2021.
  38. ^ Montes, Rafael (9 September 2014). "Horcasitas es inhabilitado 20 años por Línea 12" [Horcasitas is disqualified for 20 years for Line 12]. El Financiero (in Spanish). Archived from the original on 11 May 2021. Retrieved 19 October 2021.
  39. ^ "Línea 12 del Metro falló en diseño y construcción" [Metro Line 12 failed in design and construction]. Forbes (in Spanish). 5 September 2014. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  40. ^ "Cronología y fechas clave en la Línea 12 del Metro" [Chronology and key dates on Metro Line 12]. El Universal (in Spanish). Mexico City. 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  41. ^ Barragán, Daniela (17 May 2021). "Informe de 2014, oculto por años, revelaba ya el desastre de la L12" [2014 report, hidden for years, already revealed L12 disaster]. SinEmbargo. Archived from the original on 17 May 2021. Retrieved 25 December 2021.
  42. ^ González, Isabella (4 May 2021). "Las irregularidades de la Línea 12" [Line 12 irregularities]. LatinUS. Archived from the original on 5 May 2021. Retrieved 4 May 2021.
  43. ^ a b c Hernández, Eduardo (4 May 2021). "Florencia Serranía asegura que no tenían reportes de afectaciones en la Línea 12" [Florencia Serranía assures that there were no reports of damages to Line 12]. El Universal. Mexico City. Archived from the original on 5 May 2021. Retrieved 5 May 2021.
  44. ^ "La Línea 12 del Metro de la CDMX es la más costosa en la historia" [CDMX Metro Line 12 is the most expensive in history]. Expansión (in Spanish). 17 August 2017. Archived from the original on 24 June 2021. Retrieved 24 June 2021.
  45. ^ Hernández, Eduardo (21 September 2017). "Vecinos temen colapso de Línea 12 del Metro por sismo" [Neighbors fear a collapse of Metro Line 12 due to earthquake]. El Universal (in Spanish). Mexico City. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  46. ^ "Metro reanuda servicio en Tezonco y Olivos de la Línea 12" [Metro resumes service in Tezonco and Olivos from Line 12]. La Crónica de Hoy (in Spanish). Notimex. 22 September 2017. Archived from the original on 5 September 2019.
  47. ^ "Metro reabre tramo dañado de Línea 12" [Metro reopens the damaged section of Line 12]. El Heraldo de México (in Spanish). 30 October 2017. Archived from the original on 3 March 2018. Retrieved 4 May 2021.
  48. ^ "Reportaron errores y daños antes y después del sismo de la Línea 12 del Metro" [Errors and damage reported before and after the earthquake on Metro Line 12] (in Spanish). Mexico City: Canal 44. Archived from the original on 6 May 2021. Retrieved 22 June 2021.
  49. ^ "Vecinos de la Línea 12 alertaron por grietas... en 2017" [Line 12 neighbors warned about cracks... in 2017]. Chilango (in Spanish). 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  50. ^ Sistema de Transporte Colectivo [@MetroCDMX] (9 January 2018). "Se concluyeron los trabajos de reforzamiento realizados en la Columna 69 entre #Olivos y #Nopalera de #L12" [Reinforcement works carried out on Column 69 between #Olivos and #Nopalera of #L12 were concluded.] (Tweet) (in Spanish). Archived from the original on 4 May 2021. Retrieved 4 May 2021 – via Twitter.
  51. ^ a b Fuentes, David (4 May 2021). "Otra vez brota la solidaridad de extraños por accidente en Línea 12 del Metro" [Once again, solidarity from strangers in the aftermath of the accident on Metro Line 12]. El Universal. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  52. ^ Pantoja, Sara (2 May 2022). "Víctimas denuncian abandono del gobierno de Sheinbaum a un año del colapso en la Línea 12" [Victims denounce abandonment by Sheinbaum's government one year after Line 12 collapse]. Proceso (in Spanish). Archived from the original on 5 May 2022. Retrieved 5 May 2022.
  53. ^ "Accidente Metro CDMX Línea 12: Resumen de noticias, número de víctimas y daños por colapso en estación Olivos" [Metro CDMX Line 12 Accident: News summary, number of victims and damages due to collapse at Olivos station]. Marca (in Spanish). 5 May 2021. Archived from the original on 24 June 2021. Retrieved 23 June 2021.
  54. ^ "Qué provocó la tragedia en la Línea 12: estas serían las causas del desplome de un tramo del Metro de la CDMX" [What caused the tragedy on Line 12: these could be the causes of the collapse of a section of the CDMX subway system]. Infobae (in Spanish). 4 May 2021. Archived from the original on 5 May 2021. Retrieved 4 May 2021.
  55. ^ Estrada G., María de los Ángeles; Granados Gómez, Juan Pablo (18 June 2021). "#ColumnaInvitada – La tragedia de la Línea 12 del Metro sigue sin responsables" [#GuestColumn – Metro Line 12 tragedy remains unaccountable]. Expansión (in Spanish). Archived from the original on 18 June 2021. Retrieved 19 June 2021.
  56. ^ a b c McDonnell, Patrick J.; Sánchez, Cecilia (9 May 2021). "Her 12-year-old son took Metro to buy her a Mother's Day present. He never returned". Los Angeles Times. Archived from the original on 9 May 2021. Retrieved 10 May 2021.
  57. ^ "Puente del Metro cae en estaciones Olivos y Tezonco de la Línea 12" [Metro bridge falls at Olivos and Tezonco stations of Line 12]. Milenio (in Spanish). 3 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  58. ^ Diaz, Jaclyn; Neumann, Scott (4 May 2021). "Mexico City Metro Train Derails, Killing At Least 23 And Injuring Dozens". NPR.com. Archived from the original on 6 May 2021. Retrieved 6 May 2021.
  59. ^ Nila, Gabriela (4 May 2021). "Confirman muerte de conductor de coche aplastado por desplome de metro Olivos; viajaba con su esposa" [Confirmed death of driver of the crushed car by Olivos subway collapse; he was traveling with his wife]. Noticieros Televisa (in Spanish). Archived from the original on 5 May 2021. Retrieved 4 May 2021.
  60. ^ Sánchez, Fabiola (4 May 2021). "Overpass collapse on Mexico City metro kills at least 24". Associated Press. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  61. ^ Andrew Herrera, Karina (4 May 2021). "Suman 15 muertos y 34 hospitalizados por desplome de trabe en Línea 12: Sheinbaum" [15 dead and 34 hospitalized due to collapse of Line 12 bridge beam: Sheinbaum]. Noticieros Televisa (in Spanish). Archived from the original on 4 May 2021. Retrieved 19 October 2021.
  62. ^ a b McDonnell, Patrick J.; Linthicum, Kate; Sánchez, Cecilia (4 May 2021). "In Mexico, a deadly train wreck that many saw coming". Los Angeles Times. Mexico City. Archived from the original on 4 May 2021. Retrieved 5 May 2021.
  63. ^ "Identifican a Brandon, de 12 años entre fallecidos por colapso en el Metro; 22 personas siguen desaparecidas" [Brandon, 12 years, identified among those killed by the collapse in the Metro; 22 people are still missing]. Animal Político (in Spanish). 4 May 2021. Archived from the original on 5 May 2021. Retrieved 6 May 2021.
  64. ^ "Línea 12 del Metro: Aún hay 5 personas desaparecidas" [Metro Line 12: There are still 5 missing people]. La Razón. 6 May 2021. Archived from the original on 7 May 2021. Retrieved 8 May 2021.
  65. ^ Pantoja, Sara (6 May 2021). "CDMX asegura que cinco personas desaparecidas no tienen relación con colapso en L-12" [CDMX assures that five missing persons are not related to L-12 collapse]. Proceso (in Spanish). Mexico City. Archived from the original on 24 June 2021. Retrieved 19 June 2021.
  66. ^ Camhaji, Elías (7 May 2021). "El conductor de metro que sobrevivió a la tragedia de la Línea 12: 'Nunca esperas que te pase algo así'" [Metro driver who survived Line 12 tragedy: 'You never expect something like this happens to you']. El País (in Spanish). Archived from the original on 15 June 2021. Retrieved 19 October 2021.
  67. ^ "What We Know About the Mexico City Train Crash". The New York Times. 4 May 2021. ISSN 0362-4331. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  68. ^ "Puente se desploma con todo y tren del Metro en estación Olivos de la L12, en la CDMX" [Bridge collapses with a Metro train at Olivos station of L12, in Mexico City]. Diario de Colima (in Spanish). 3 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  69. ^ "Survivors Helped From Wreckage After Deadly Mexico City Overpass Collapse". Yahoo!. 4 May 2021. Archived from the original on 5 May 2021. Retrieved 4 May 2021.
  70. ^ Patiño, Daniela (4 May 2021). "Hay gente aplastada bajo las estructuras del Metro. Sacarlas va a tardar, dice miembro de los Topos en México" [There are people crushed under the Metro structures. Getting them out is going to take time, says member of the Topos in Mexico]. CNN en Español (in Spanish). Archived from the original on 24 June 2021. Retrieved 24 June 2021.
  71. ^ Rodríguez, Juan Carlos (4 May 2021). "Todos parecían estar muertos" [Everyone seemed to be dead]. Eje Central (in Spanish). Archived from the original on 5 May 2021. Retrieved 5 May 2021.
  72. ^ "¡Solidaridad presente! Así se unieron las personas tras colapso de la Línea 12 del Metro" [Solidarity present! How people came together after the collapse of Metro Line 12]. Publimetro (in Spanish). 4 May 2021. Archived from the original on 5 May 2021. Retrieved 5 May 2021.
  73. ^ a b Rodríguez, Darinka; Vaerla, Micaela; Arroyo, Lorena (4 May 2021). "'Resistan tantito': la solidaridad de los vecinos de Tláhuac minutos después del derrumbe del metro" ['Hold on a little more': the solidarity of Tláhuac residents minutes after the subway collapse]. El País (in Spanish). Mexico. Archived from the original on 5 May 2021. Retrieved 5 May 2021.
  74. ^ "Claudia Sheinbaum informa suspensión en maniobras de rescate; 'estructura está muy débil'" [Claudia Sheinbaum reports suspension of rescue maneuvers; 'structure is too weak']. El Heraldo de México (in Spanish). 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  75. ^ "Mexico City rail overpass collapses, killing 20 people". Reuters. 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  76. ^ "Concluyen retiro de estructura tras tragedia en Metro de CDMX" [Removal of structure after tragedy in CDMX Metro completed]. El Informador (in Spanish). 31 May 2021. Archived from the original on 24 June 2021. Retrieved 23 June 2021.
  77. ^ "Remoción en Línea 12 de Metro CDMX deja 3 trabajadores heridos" [Removal on Line 12 of Metro CDMX leaves three workers injured]. Azteca Noticias (in Spanish). TV Azteca. 28 May 2021. Archived from the original on 24 June 2021. Retrieved 23 June 2021.
  78. ^ "Mexico City metro overpass collapse kills 23". BBC News. 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  79. ^ "Cierran toda la Línea 12 del Metro; RTP brindará servicio de apoyo" [All Metro Line 12 is closed; RTP will provide back-up service]. Chilango (in Spanish). 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  80. ^ "CdMx suma camiones ADO a transporte emergente por accidente en L12 del Metro" [Mexico City adds ADO buses to emergency transportation due to accident in L12 of the Metro]. Milenio (in Spanish). Mexico City. 5 May 2021. Archived from the original on 5 May 2021. Retrieved 5 May 2021.
  81. ^ Lorenzana, Israel (5 May 2021). "Usuarios buscan rutas por suspensión de L12" [Riders look for routes after Line 12 suspension]. Siete24. Mexico City. Archived from the original on 5 May 2021. Retrieved 6 May 2021.
  82. ^ Morales, Amallely (26 May 2021). "Corre Metrobús emergente en Tláhuac" [Emergent Metrobús route runs along Tláhuac]. Reforma (in Spanish). Archived from the original on 10 September 2021. Retrieved 26 May 2021.
  83. ^ "Anuncian nueva ruta de Metrobús para la Línea 12 de Tláhuac a Coyuya" [New Metrobús route for Line 12 from Tláhuac to Coyuya announced] (in Spanish). ADN 40. 18 June 2021. Archived from the original on 24 June 2021. Retrieved 19 June 2021.
  84. ^ "AMLO decreta tres días de luto nacional por accidente en Línea 12 del Metro" [AMLO decrees three days of national mourning for accident on Metro Line 12]. El Universal (in Spanish). 5 May 2021. Archived from the original on 5 May 2021. Retrieved 5 May 2021.
  85. ^ Hernández, Eduardo (4 May 2021). "Se revisarán denuncias por cuarteaduras en Metro Oceanía y Pantitlán: Sheinbaum" [Complaints about cracks in Oceania and Pantitlan stations will be reviewed: Sheinbaum]. El Universal (in Spanish). Archived from the original on 5 May 2021. Retrieved 5 May 2021.
  86. ^ a b "Mexico City metro collapse victims' families to get compensation". Al Jazeera. 8 May 2021. Archived from the original on 10 May 2021. Retrieved 10 May 2021.
  87. ^ Parsons, Jim (9 May 2021). "Forensics Firm DNV Tapped to Probe Mexico City Subway Collapse". Engineering News-Record. Archived from the original on 10 May 2021. Retrieved 10 May 2021.
  88. ^ Vargas Isita, Héctor (3 September 2021). "Dan más de 48 millones de pesos a familias de víctimas del desplome de L12 del Metro" [More than 48 million pesos given to families of victims of the L12 Metro collapse]. Noticieros Televisa (in Spanish). Archived from the original on 7 September 2021. Retrieved 8 September 2021.
  89. ^ Gamboa, Víctor (6 May 2021). "Morena frena creación de una Comisión Investigadora del colapso de Metro Olivos" [Morena stops the creation of a Investigative Commission into the collapse of Olivos station]. El Universal (in Spanish). Archived from the original on 8 May 2021. Retrieved 8 May 2021.
  90. ^ a b "Mexico president hits back at critics over metro crash". France 24. Mexico City. 6 May 2021. Archived from the original on 6 May 2021. Retrieved 6 May 2021.
  91. ^ "Claudia Sheinbaum se traslada al lugar del accidente, en la Línea 12 del Metro" [Claudia Sheinbaum moves to the scene of the accident on Metro Line 12]. Milenio (in Spanish). Mexico City. 3 May 2021. Archived from the original on 4 May 2021. Retrieved 5 May 2021.
  92. ^ Castillo, Eduardo; Verza, María (4 May 2021). "'Lo ocurrido hoy en el Metro es una terrible tragedia'" [What happened today on the Metro is a terrible tragedy]. Chicago Tribune (in Spanish). Archived from the original on 5 May 2021. Retrieved 5 May 2021.
  93. ^ Lozano, Nayelo (4 May 2021). "AMLO respalda a Sheinbaum tras colapso en L12: no se ocultará nada, no se acusará sin pruebas" [AMLO backs Sheinbaum after L12 collapse: nothing will be hidden, no accusations will be made without evidence]. Político MX. Archived from the original on 4 May 2021. Retrieved 5 May 2021.
  94. ^ a b "Esperaremos a los peritajes oficiales: Carso" [We will wait the official expertises: Carso]. Aristegui Noticias (in Spanish). 4 May 2021. Archived from the original on 4 May 2021. Retrieved 5 May 2021.
  95. ^ Sánchez, Axel (4 May 2021). "Grupo Carso esperará los peritajes tras colapso en Línea 12 del Metro" [Grupo Carso will wait for the official expertises after Metro Line 12 collapse]. El Financiero (in Spanish). Archived from the original on 4 May 2021. Retrieved 5 May 2021.
  96. ^ "Feministas y encapuchados protestan por accidente en el Metro CDMX" [Feminists and hooded demonstrator protest accident in the CDMX Metro]. Azteca Noticias (in Spanish). 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
  97. ^ "Colectivos feministas protestan en Metro Chabacano; policías ingresan a estación" [Feminist collectives protest at Chabacano station; police enter station]. Milenio (in Spanish). Mexico City. 7 May 2021. Archived from the original on 8 May 2021. Retrieved 8 May 2021.
  98. ^ Quintero M., Josefina (4 May 2021). "Con marcha exigen castigo a responsables de accidente en L12" [March to demand punishment of those responsible for L12 accident]. La Jornada (in Spanish). Mexico City. Archived from the original on 5 May 2021. Retrieved 4 May 2021.
  99. ^ Espino, Manuel; Ruiz, Kevin (4 May 2021). "Colocan altar en memoria de las personas fallecidas en accidente de Línea 12 del Metro" [Altar placed in memory of those killed in Metro Line 12 crash]. El Universal (in Spanish). Archived from the original on 8 May 2021. Retrieved 8 May 2021.
  100. ^ "Mexico City metro: Hundreds protest at scene of deadly rail collapse". BBC News. 9 May 2021. Archived from the original on 9 May 2021. Retrieved 10 May 2021.
  101. ^ Osorio, Karen (28 October 2021). "Tren al Mictlán: convocan a ofrenda de Día de Muertos para víctimas en colapso de L12" [Train to Mictlán: Day of the Dead offering for victims of L12 collapse called for]. Debate (in Spanish). Archived from the original on 4 November 2021. Retrieved 2 May 2022.
  102. ^ "#FueMorena: PAN CDMX coloca antimonumento por víctimas de la Línea 12 del Metro" [#FueMorena: PAN CDMX places anti-monument in honor to the victims of Line 12]. El Financiero (in Spanish). 2 May 2022. Archived from the original on 3 May 2022. Retrieved 2 May 2022.
  103. ^ Guzmán, Sharenii (3 May 2022). "A un año de la caída de la Línea 12, sobrevivientes y familiares de personas fallecidas anuncian un memorial" [One year after Line 12's collapse, survivors and relatives of those who died announce a memorial]. Animal Político (in Spanish). Archived from the original on 4 May 2022. Retrieved 5 May 2022.
  104. ^ "El día que Claudia Sheinbaum expresó su confianza a DNV para 'llegar al fondo' del colapso de la Línea 12" [The day Claudia Sheinbaum expressed her confidence in DNV to "get to the bottom" of the collapse of Line 12]. Infobae (in Spanish). 5 May 2022. Archived from the original on 8 May 2022. Retrieved 11 May 2022.
  105. ^ a b c Cervantes, Mariana (17 June 2021). "¿Qué son la causa inmediata y la causa raíz, explicaciones del colapso en Línea 12 del Metro?" [What are the immediate cause and root cause explanations for the collapse of Metro Line 12?]. Radio Fórmula (in Spanish). Archived from the original on 19 June 2021. Retrieved 20 June 2021.
  106. ^ "Pactaron tres pagos por informes de DNV" [Three payments were pacted for DNV reports]. MSN (in Spanish). El Universal. 5 May 2022. Archived from the original on 12 May 2022. Retrieved 11 May 2022.
  107. ^ a b Gómez Leyva, Ciro (6 May 2022). "Gobierno CDMX inicia demanda contra empresa noruega DNV" [Mexico City Government initiates lawsuit against Norwegian company DNV]. Imagen Televisión. Archived from the original on 12 May 2022. Retrieved 11 May 2022.
  108. ^ a b Vela, Daniel Saúl; Alzaga, Ignacio (16 June 2021). "Peritaje Línea 12: Estas son las 6 deficiencias en la construcción que se encontraron" [Line 12 survey: These are the 6 construction deficiencies that were found]. El Financiero (in Spanish). Archived from the original on 17 June 2021. Retrieved 20 June 2021.
  109. ^ Stevenson, Mark (16 June 2021). "Report blames poor welds for Mexico City subway collapse". Associated Press. Archived from the original on 24 June 2021. Retrieved 21 June 2021.
  110. ^ Vela, Daniel Saúl; Alzaga, Ignacio (18 June 2021). "Otra revelación del peritaje de la Línea 12: se buscó usar menos varilla" [Another revelation from the Line 12 expert report: less rebar was to be used]. El Financiero (in Spanish). Archived from the original on 19 June 2021. Retrieved 20 June 2021.
  111. ^ Vela, Daniel Saúl; Alzaga, Ignacio (17 June 2021). "Peritaje Línea 12: suprimen de 'última hora' el tema del mantenimiento" [Line 12 expertise: maintenance issue removed at 'last minute'.]. El Financiero (in Spanish). Archived from the original on 17 June 2021. Retrieved 20 June 2021.
  112. ^ Ramos, Rolando (16 June 2021). "Informe preliminar de DNV revela deficiencias en la Línea Dorada" [Preliminary DNV report reveals deficiencies in the Golden Line]. El Economista (in Spanish). Archived from the original on 21 June 2021. Retrieved 20 June 2021.
  113. ^ "Missing bolts contributed to Mexico City metro collapse: Report". Al Jazeera. 7 September 2021. Archived from the original on 8 September 2021. Retrieved 8 September 2021.
  114. ^ "Report blames poor welds for Mexico City subway collapse". ABC News. Associated Press. 7 September 2021. Archived from the original on 7 September 2021. Retrieved 8 September 2021.
  115. ^ Rodríguez, Iván (5 May 2022). "Gobierno de CDMX rescinde contrato y demanda a DNV" [Government of Mexico City rescinds contract and sues DNV]. El Economista (in Spanish). Archived from the original on 5 May 2022. Retrieved 7 May 2022.
  116. ^ Camhaji, Elías (4 May 2022). "El Gobierno de Ciudad de México demanda a DNV, la empresa encargada de los peritajes de la Línea 12" [Mexico City Government sues DNV, the company in charge of the Line 12 surveys]. El País (in Spanish). Archived from the original on 5 May 2022. Retrieved 5 May 2022.
  117. ^ "Sheinbaum demandará a DNV por peritaje 'tendencioso y falso' del desplome de la Línea 12" [Sheinbaum to sue DNV for 'biased and false' report on Line 12 collapse]. Proceso (in Spanish). 4 May 2022. Archived from the original on 4 May 2022. Retrieved 5 May 2022.
  118. ^ Camhaji, Elías (11 May 2022). "El Gobierno de Sheinbaum hace público el informe de DNV que adelantó EL PAÍS sobre el colapso en la Línea 12" [Sheinbaum's government makes public the DNV report that El País published about the collapse of Line 12]. El País (in Spanish). Archived from the original on 11 May 2022. Retrieved 11 May 2022.
  119. ^ Yaes, Brenda (5 May 2022). "Informe de DNV sobre L12 "nos sembró el mantenimiento", acusa Andrés Lajous" [DNV report on L12 "planted maintenance", accuses Andrés Lajous]. Expansión (in Spanish). Archived from the original on 5 May 2022. Retrieved 5 May 2022.
  120. ^ Buendía, Eduardo (6 May 2022). "¿Quién es Héctor Salomón, abogado de DNV acusado por Sheinbaum de trabajar para Peña Nieto?" [Who is Héctor Salomón, DNV's lawyer accused by Sheinbaum of working for Peña Nieto?]. Milenio (in Spanish). Mexico City. Archived from the original on 7 May 2022. Retrieved 11 May 2022.
  121. ^ Zerega, Georgina; Camhaji, Elías; Manetto, Francesco (9 May 2022). "El peritaje final de DNV señala fallas en las inspecciones y el mantenimiento como causas concurrentes en la tragedia de la Línea 12" [DNV's final expert report points out failures in inspections and maintenance as concurrent causes of the Line 12 tragedy]. El País (in Spanish). Archived from the original on 11 May 2022. Retrieved 11 May 2022.
  122. ^ "El País revela el peritaje final de DNV a la Línea 12 del Metro; fallas en el mantenimiento, entre las causas del accidente" [El País reveals DNV's final assessment of Metro Line 12; maintenance failures among causes of accident]. SDP Noticias (in Spanish). 9 May 2022. Archived from the original on 10 May 2022. Retrieved 11 May 2022.
  123. ^ "Colapso de Línea 12: Estas inconsistencias detectó el Gobierno de CDMX en el dictamen final de DNV" [Collapse of Line 12: These inconsistencies detected by the Government of CDMX in DNV's final report]. El Financiero (in Spanish). 11 May 2022. Retrieved 11 May 2022.
  124. ^ "Sheinbaum busca nuevo peritaje sobre colapso en la Línea 12 con 'ingenieros de calidad'" [Sheinbaum seeks new expertise on Line 12 collapse with 'quality engineers']. Proceso (in Spanish). 6 May 2022. Archived from the original on 9 May 2022. Retrieved 11 May 2022.
  125. ^ a b c d El Universal (19 June 2021). "Metro CDMX: Línea 12 no puede reabrir; detectan más fallas" [Mexico City Metro: Line 12 cannot reopen; more failures detected]. El Imparcial (in Spanish). Mexico City. Archived from the original on 20 June 2021. Retrieved 21 June 2021.
  126. ^ Kitroeff, Natalie; Abi-Habib, Maria; Glanz, James; Lopez, Oscar; Cai, Wiyi; Grothjan, Evan; Peyton, Miles; Cegarra, Alejandro (13 June 2021). "Why the Mexico City Metro Collapsed". The New York Times. Archived from the original on 20 June 2021. Retrieved 20 June 2021.
  127. ^ "Sheinbaum cuestiona intereses ocultos en revelación de NYT sobre L-12" [Sheinbaum questions hidden interests in NYT's L-12 revelation]. Forbes (in Spanish). Mexico City. 13 June 2021. Archived from the original on 23 June 2021. Retrieved 20 June 2021.
  128. ^ Wong, Alma Paola; Vega, Carlos (14 June 2021). "Problemas en L12 del Metro, por falta notoria de mantenimiento en vías: Ebrard a NYT" [Problems in L12 of the Metro, due to a notorious lack of track maintenance: Ebrard to NYT] (in Spanish). Archived from the original on 24 June 2021. Retrieved 20 June 2021.
  129. ^ Paredes, Ariana (15 October 2021). "L12: los pernos Nelson, otra vez" [L12: Nelson studs, again]. El Universal (in Spanish). Mexico City. Archived from the original on 17 October 2021. Retrieved 18 October 2021.
  130. ^ "En L12, el colapso fue fundamentalmente por errores en construcción: Fiscalía capitalina" [On L12, the collapse was fundamentally due to construction errors: CDMX Attorney General]. El Universal (in Spanish). 14 October 2021. Archived from the original on 15 October 2021. Retrieved 18 October 2021.
  131. ^ "Third of required bolts missing from collapsed Mexico City metro section – study". Bnamericas. 10 January 2022. Archived from the original on 10 February 2022. Retrieved 10 February 2022.
  132. ^ "Another study finds maintenance errors at collapsed Mexico City metro line". Bnamericas. 24 January 2022. Archived from the original on 10 February 2022. Retrieved 10 February 2022.
  133. ^ Mandujano Tovar, Rocío (17 June 2021). "Colegio de Ingenieros Civiles de México detecta deficiencias en 32% de L12 del Metro CDMX" [College of Civil Engineers of Mexico detects deficiencies in 32% of L12 of Metro CDMX]. Noticieros Televisa (in Spanish). Archived from the original on 19 June 2021. Retrieved 21 June 2021.
  134. ^ "Para 2022 se terminará reconstrucción de Línea 12 del Metro: Sheinbaum" [Metro Line 12 reconstruction to be completed by 2022: Sheinbaum]. Milenio (in Spanish). Mexico City. 8 December 2021. Archived from the original on 9 December 2021. Retrieved 17 December 2021.
  135. ^ Mora, Karla (13 May 2021). "Línea 12 del Metro: Perfilan plan para abrir tramo subterráneo" [Metro Line 12: Plan to reopen underground section profiled]. La Razón (in Spanish). Archived from the original on 24 June 2021. Retrieved 23 June 2021.
  136. ^ "Colegio de Ingenieros recomienda no reiniciar operaciones en L12; detecta fisuras y filtraciones" [College of Engineers recommends to not restart operations at L12; fissures and leakage detected]. Animal Político (in Spanish). 17 June 2021. Archived from the original on 24 June 2021. Retrieved 23 June 2021.
  137. ^ "Parte subterránea de L12 del Metro no podrá ser reabierta: Colegio de Ingenieros Civiles de México" [Underground part of Metro's L12 cannot be reopened: College of Civil Engineers of Mexico]. Megalópolis MX (in Spanish). 18 June 2021. Archived from the original on 24 June 2021. Retrieved 23 June 2021.
  138. ^ Zamarrón, Israel (18 June 2021). "Sheinbaum busca que ICA y Slim aporten dinero para rehabilitar Línea 12" [Sheinbaum seeks ICA and Slim to contribute money to rehabilitate Line 12]. Forbes (in Spanish). Mexico City. Archived from the original on 24 June 2021. Retrieved 23 June 2021.
  139. ^ Jiménez, Néstor; Martínez, Fabiola (23 June 2021). "Slim, con voluntad para apoyar reconstrucción de la L-12: AMLO" [Slim willing to support reconstruction of L-12: AMLO]. La Jornada (in Spanish). Archived from the original on 23 June 2021. Retrieved 23 June 2021.
  140. ^ Pedro Domínguez (24 June 2021). "A más tardar en un año estará operando la Línea 12 del Metro de CdMx, dice AMLO" [Line 12 of Mexico City's Metro to be operational within a year at the latest, says AMLO]. Milenio. Mexico City. Archived from the original on 27 June 2021. Retrieved 27 June 2021.
  141. ^ "Slim pagará reconstrucción del tramo colapsado de Línea 12, no le costará al pueblo, dice AMLO" [Slim will pay for the reconstruction of Line 12 collapsed section, it will not cost the people, says AMLO]. Animal Político (in Spanish). 30 June 2021. Archived from the original on 30 June 2021. Retrieved 30 June 2021.
  142. ^ García Soto, Salvador (30 June 2021). "Slim pagará, pero defiende la obra de L12" [Slim will pay, but defends Line 12's construction]. El Universal (in Spanish). Archived from the original on 30 June 2021. Retrieved 30 June 2021.
  143. ^ "Carlos Slim Helú: la Línea 12, sin vicios de origen en su construcción" [Carlos Slim Helú: Line 12, without inherent vices in its construction]. Expansión (in Spanish). 29 June 2021. Archived from the original on 30 June 2021. Retrieved 30 June 2021.
  144. ^ Argüelles, Efrén (16 February 2022). "Línea 12 del Metro: Inicia reconstrucción en zona cero tras desplome" [Metro Line 12: Reconstruction begins at ground zero after collapse]. Excélsior (in Spanish). Mexico City. Archived from the original on 17 February 2022. Retrieved 21 February 2022.
  145. ^ Corona, Salvador (7 March 2022). "Reconstruirán otro tramo de la parte elevada de la Línea 12" [Another section of the elevated part of Line 12 will be rebuilt]. El Universal (in Spanish). Mexico City. Archived from the original on 7 March 2022. Retrieved 15 March 2022.
  146. ^ "Reconstrucción de la Línea 12 del Metro CDMX se realiza con acero del Aeropuerto de Texcoco" [Reconstruction of Line 12 of the Mexico City Metro to be carried out with steel from Texcoco Airport]. Infobae (in Spanish). 17 October 2022. Retrieved 28 October 2022.
  147. ^ Jiménez, Adrián (13 October 2022). "Acero del aeropuerto de Texcoco se utiliza en reforzamiento de L12, confirma Sheinbaum" [Steel from Texcoco Airport to be used in L12 reinforcement, confirms Sheinbaum]. MVS Noticias (in Spanish). Retrieved 28 October 2022.
  148. ^ Navarrete, Shelma (15 January 2023). "A 20 meses del desplome de la Línea 12, reabren tramo Mixcoac-Atlalilco". Expansión (in Spanish). Archived from the original on 15 January 2023. Retrieved 15 January 2023.
  149. ^ "Metro Línea 12 reabrió tramo subterráneo; Sheinbaum recalcó que por 'eventos malintencionados' involucraron a la GN" [Metro Line 12 reopened underground section; Sheinbaum stressed that "malicious events" involved NG]. Infobae (in Spanish). 15 January 2023. Retrieved 15 January 2023.
  150. ^ "Reabren Línea 12 del Metro tramo Culhuacán a Periférico Oriente" [Metro Line 12 from Culhuacán to Periférico Oriente section reopened]. unomásuno (in Spanish). 15 July 2023. Retrieved 16 July 2023.
  151. ^ Rivera, José Antonio (22 June 2021). "Grupo Carso pierde 7,887 millones de pesos en la BMV desde la conferencia sobre Línea 12" [Grupo Carso loses 7,887 billion pesos in the BMV since the conference on Line 12]. El Economista (in Spanish). Archived from the original on 27 June 2021. Retrieved 27 June 2021.
  152. ^ Puga, Tláloc (30 June 2021). "Tras anunciar que rehabilitará tramo de la L12, Carso pierde 2 mil 734 mdp en dos días" [After announcing L12 section rehabilitation, Carso loses 2,734 billion pesos in two days]. El Universal (in Spanish). Archived from the original on 1 July 2021. Retrieved 5 July 2021.
  153. ^ "Se va Florencia Serranía: deja la dirección del Metro y Guillermo Calderón la sustituye" [Florencia Serranía leaves: She leaves the Metro directorship and Guillermo Calderón replaces her]. El Financiero (in Spanish). Mexico City. 28 June 2021. Archived from the original on 28 June 2021. Retrieved 30 June 2021.
  154. ^ García Soto, Salvador (9 September 2021). "DNV denuncia violación a sus investigaciones" [DNV denounces violation of its investigations]. El Universal (in Spanish). Archived from the original on 10 September 2021. Retrieved 10 September 2021.
  155. ^ "FGJCDMX investiga a 11 soldadores y 2 directivos por accidente de Línea 12 del Metro" [FGJCDMX investigates 11 welders and 2 directors for Metro Line 12 accident]. Proceso (in Spanish). 11 August 2021. Archived from the original on 17 August 2021. Retrieved 10 September 2021.
  156. ^ Fuentes, David (18 October 2021). "Por L12, buscan imputar homicidio culposo, daños y lesiones a Horcasitas y otros 9: abogado" [For L12, they seek to charge Horcasitas and 9 others with negligent homicide, damages and injuries: defense]. El Universal (in Spanish). Mexico City. Archived from the original on 18 October 2021. Retrieved 18 October 2021.
  157. ^ Trejo, Yeseline (18 October 2021). "Fiscalía CDMX presenta 10 denuncias por colapso de Línea 12" [Mexico City Attorney's Office files 10 complaints for Line 12 collapse]. Diario AS (in Spanish). Mexico City. Archived from the original on 18 October 2021. Retrieved 18 October 2021.
  158. ^ "¿Quién es Enrique Horcasitas, director del proyecto Metro del 2006 al 2012?" [Who is Enrique Horcasitas, Metro project director from 2006 to 2012?]. SDP Noticias (in Spanish). Mexico City. 18 October 2021. Archived from the original on 18 October 2021. Retrieved 18 October 2021.
  159. ^ Hernández, Nelly (19 October 2021). "En la traducción de peritaje de L12 eliminaron el tema de mantenimiento: Abogado" [In the translation of L12's expert opinion, the maintenance issue was eliminated: Lawyer]. Radio Fórmula (in Spanish). Archived from the original on 20 October 2021. Retrieved 19 October 2021.
  160. ^ "Imputan a diez exfuncionarios por caída de metro de México" [Ten ex-officials charged in Mexico City metro crash]. Chicago Tribune. Mexico City. Associated Press. 6 December 2021. Archived from the original on 17 December 2021. Retrieved 17 December 2021.
  161. ^ "Carso destinará 800 millones de pesos a reparar la Línea 12" [Carso will destine 800 million pesos to repair Line 12]. Expansión (in Spanish). 26 October 2021. Archived from the original on 27 October 2021. Retrieved 3 November 2021.
  162. ^ "Revelan que Carso subcontrató a empresa para fijar los pernos en la Línea 12 del Metro" [It is revealed that Carso subcontracted a company to install the studs on Metro Line 12.]. Aristegui Noticias (in Spanish). 3 November 2021. Archived from the original on 3 November 2021. Retrieved 3 November 2021.
  163. ^ a b Camhaji, Elías (31 January 2022). "Carlos Slim's company pays out thousands of dollars to Mexico City metro tragedy victims to prevent further lawsuits". El País. Translated by Kitson, Melissa. Archived from the original on 4 February 2022.
  164. ^ Vela, David Saúl (2 May 2022). "Colapso en Línea 12 del Metro: Difieren audiencia de imputación a Enrique a Horcasitas" [Metro Line 12 Collapse: Enrique Horcasitas' arraignment hearing deferred]. El Financiero (in Spanish). Archived from the original on 3 May 2022. Retrieved 5 May 2022.
  165. ^ "Línea 12 del Metro: Cicsa de Slim paga miles de pesos en acuerdos reparatorios a víctimas del colapso" [Metro Line 12: Slim's CICSA pays thousands of pesos in settlements to collapse victims]. El Economista (in Spanish). 1 February 2022. Archived from the original on 3 February 2022. Retrieved 2 February 2022.
  166. ^ Pantoja, Sara (31 January 2022). "Empresa de Slim dará hasta 6 mdp a familias de fallecidos en Línea 12; no podrán demandar" [Slim's company will give up to $6 million pesos to families of Line 12 fatalities; they cannot sue]. Proceso (in Spanish). Mexico City. Archived from the original on 1 February 2022. Retrieved 2 February 2022.
  167. ^ Pantoja, Sara (2 February 2022). "Fiscal llama a todas las víctimas de la Línea 12 a firmar el acuerdo con Slim" [Attorney general calls all victims of Line 12 to sign agreement with Slim]. Proceso (in Spanish). Mexico City. Archived from the original on 3 February 2022. Retrieved 2 February 2022.

Further reading

External videos
video icon The collapse