Williams v Roffey Bros & Nicholls (Contractors) Ltd

From Wikipedia, the free encyclopedia
Jump to: navigation, search
Williams v Roffey Bros Ltd
Court Court of Appeal
Full case name Williams v. Roffey Bros & Nicholls (Contractors) Ltd
Citation(s) [1989] EWCA Civ 5, [1991] 1 QB 1, [1990] 2 WLR 1153
Transcript(s) Full text of judgment
Judge(s) sitting Glidewell, Russell and Purchas, L. JJ.

Williams v Roffey Bros & Nicholls (Contractors) Ltd [1989] EWCA Civ 5 is a leading English contract law case, which decided that in varying a contract, the court will be quick to find consideration, if "factual benefits" are given from one to another party.

Contents

[edit] Facts

Roffey Bros was contracted by Shepherds Bush Housing Association Ltd to refurbish 27 flats at Twynholm Mansions, Lillie Road, London SW6. They subcontracted carpentry to Mr Lester Williams for £20,000 payable in instalments. Some work was done and £16,200 was paid. Then Williams ran into financial difficulty because the price was too low. Roffey Bros was going to be liable under a penalty clause for late completion, so they had a meeting on 9 April 1986 and promised an extra £275 per flat for on time completion. Williams did eight flats and stopped because he had only got £1,500. New carpenters were brought in. Williams claimed.

Mr Rupert Jackson QC held Williams should get the eight times £275 with a few deductions for defects and some of the £2,200 owing from the original sum. He said that they had agreed that the original price was too low, and that raising it to a reasonable level was in both sides’ interests.

[edit] Judgment

Glidewell LJ held Williams had provided good consideration even though he was merely performing a pre-existing duty. Williams got £3,500 (not full expectation damages). He said that the idea of promissory estoppel was not properly argued and ‘not yet been fully developed’.[1] The concept of economic duress provided an answer to Stilk’s old problem. The test for understanding whether a contract could legitimately be varied was set out as follows.

  • if A has a contract with B for work
  • before it is done, A has reason to believe B may not be able to complete
  • A promises B more to finish on time
  • A ‘obtains in practice a benefit, or obviates a disbenefit’ from giving the promise
  • there is no economic duress or fraud...

The practical benefit of timely completion, even though a pre-existing duty is performed, constitutes good consideration. On Stilk v Myrick, Glidewell LJ said,

It is not in my view surprising that a principle enunciated in relation to the rigours of seafaring life during the Napoleonic wars should be subjected during the succeeding 180 years to a process of refinement and limitation in its application to the present day.


Russell LJ said ‘the courts nowadays should be more ready to find [consideration’s] existence so as to reflect the intention of the parties to the contract where the bargaining powers are not unequal’. He noted that Roffey Bros’ employee, Mr Cottrell had felt the original price to be less than reasonable, and there was a further need to replace the ‘haphazard method of payment by a more formalised scheme’ of money per flat. "True it was that the plaintiff did not undertake to do any work additional to that which he had originally undertaken to do but the terms upon which he was to carry out the work were varied and, in my judgment, that variation was supported by consideration which a pragmatic approach to the true relationship between the parties readily demonstrates.’

Purchas LJ concurred with Glidewell LJ.

[edit] Significance

The doctrine introduced by this decision has been widely criticised. [2]

[edit] See also

  • Watkins & Son Inc. v. Carrig, 21 A.2d 591 (N.H., 1941), Watkins & Son agreed to excavate a cellar for Carrig. Half way through, solid rock was encountered. Carrig promised more money orally, about nine times the amount and the new agreement was enforced.
  • Restatement Contract 2d, s.89, "A promise modifying a duty under a contract not fully performed on either side is binding (a) if the modification is fair and equitable in view of circumstances not anticipated by the parties when the contract was made"
  • Uniform Commercial Code, s.2-209

[edit] Notes

  1. ^ per Lloyd J, Syros Shipping Co. SA v. Elaghill Trading Co. [1980] 2 Lloyds Rep. 390, 392
  2. ^ A Blair, “Minding your own business – Williams v Rovvey re-visited: consideration re-considered” (1996) Journal of Business Law 254

[edit] External links

Personal tools
Namespaces

Variants
Actions
Navigation
Interaction
Toolbox
Print/export