AguaClara is a project in Civil and Environmental Engineering at Cornell University that aims to improve drinking water quality through innovative research, knowledge transfer, open source engineering and design of sustainable, replicable water treatment systems.

History

La 34

La 34, or "La treinta y quatro," once a numbered plantation run by United Fruit, is the first site of an AguaClara plant [1]. Construction on the La 34 plant began in December of 2004 and was inaugurated in August of 2005. The plant serves a population of 2000 with a design flow of 285 Lpm (Liters per minute)

Ojojona

Construction on the Ojojona plant began in June 2006 and was completed in January 2007, serving a population of 2000 with a design flow of 375 Lpm.

Tamara

Construction on the Tamara plant began in January 2008 and was inaugurated on June 15, 2008, serving a population of 3500 with a design flow of 738 Lpm.

Marcala

Sponsors

Sponsors include:

Contribute to AguaClara

Future Goals

See Also