Oloibiri Oilfield
This article has an unclear citation style. (May 2010) |
Oloibiri Oilfield | |
---|---|
Country | Nigeria |
Region | Niger Delta |
Location | Bayelsa State |
Block | OML29 |
Offshore/onshore | Onshore |
Operator | SPDC |
Partner | BP (till 1979) |
Field history | |
Discovery | 15 January 1956 |
Start of development | 1956 |
Start of production | 1958 |
Peak year | 1964 |
Abandonment | 1978 |
Production | |
Current production of oil | 5,100 barrels per day (~2.5×10 5 t/a) |
Year of current production of oil | 1958 |
Estimated oil in place | 20.06 million barrels (~2.737×10 6 t) |
Producing formations | Agbada Formation |
Oloibiri Oilfield is an onshore oilfield located in Oloibiri in Ogbia LGA of Bayelsa State, Nigeria, about 45 miles (72 km) east of Port Harcourt in the Niger Delta. Oloibiri field is about 13.75 square kilometres (5.31 sq mi) and lies in a swamp within OML 29. Oloibiri Oilfield is named after Oloibiri, a small, remote creek community, where it is located. In Nigeria, Oilfield is usually named after the host community where it is located or local landmark. Oilfield is also given names taken from indigenous language.
The field is currently operated by Shell Petroleum Development Company of Nigeria Limited (SPDC).The field was originally operated by Shell Darcy. On 30 April 1956, Shell Darcy changed its name to Shell-BP Petroleum Development Company of Nigeria Limited to reflect BP interest. In 1979, it changed its name gain to Shell Petroleum Development Company of Nigeria Limited (SPDC) following the nationalisation of BP interest by the Government.
Exploration history
Oloibiri Oilfield was discovered on Sunday 15 January 1956 by Shell Darcy. It is Nigeria first commercial oil discovery. The discovery ended 50 years of unsuccessful oil exploration in the country by various companies and launched Nigeria into the limelight of Petro-State.
Following the discovery of oil in commercial quantity in Oloibiri, Shell stepped up exploration in the Niger Delta and By 1958 Shell/D'Arcy has discovered oil in twelve areas in the Niger Delta of which Oloibiri, Afam and Bomu were the most promising.
The discovery well Oloibiri −1 was spudded on 3 August 1955 and drilled vertical to a total depth of 12008 feet (3660m). The well was tested and it flowed at the rate of about 5,000 barrels (790 m3) of oil per day and it was deemed to be a commercial discovery. Some gas was also discovered with the oil. The oil discovery was made in the Tertiary Agbada.
.
Appraisal
Between 26 June 1956 and 28 October 1958, 11 appraisal wells were drilled vertical to appraisal the extension of the reservoir to different sections of the field. The first appraisal well was Oloibiri-2, it was spudded on 26 June 1956 and drilled vertically to a total depth of 2932m and it encountered oil in the Agbada Formation. Six of these appraisal wells were a success and encountered oil pay.
An appraisal well Oloibiri-17 was spudded on 9 June 1967 after 9 years of production and drilled deviated to a measured depth of 12520 feet (3816 mD) but the result was not encouraging. Oloibiri-17 was plugged and abandoned. The field production was on depletion from its peak production and the well was drilled to appraisal another section of the field so as to increase production.
Another appraisal well Oloibiri-18 was spudded on 21 April 1979 and drilled to a vertical depth of 9616 feet (2931 m) but the result was also discouraging. The field was almost depleted at that time. The main objective of the Oloibiri-18 was to appraise a new section and improve the drainage of the reservoir but the well was dry with shows and so it was plugged and abandoned.
Development
Following the successful completion of the appraisal of the field, four development wells were drilled in 1958 (between 17 June 1958 and 27 November 1958) for the development of the field. The four development wells and the six successful appraisal wells were completed as oil production wells.
The discovery well, Oloibiri-1 was completed on 5 June 1956 as a commercial oil production well. Thus, Oloibiri-1 made history as the first truly commercial oil well in Nigeria. This brings the number of completed production wells on field to eleven.
Production
The field started oil production between late 1957 and early 1958 and the first oil production from the field came at the rate of 4,928 barrels per day (783.5 m3/d). The field produced at an average rate of 5,100 barrels (810 m3) of oil per day for the first year. The production increased thereafter as more wells were completed and put onto production and reached its peak in 1964. The field was drained from eleven production wells. The oil produced from the field is sour and heavy and has an API of 20.6. The gas produced with the oil was flared off as a result of lack of gas processing and utilisation facility in the country then, so the gas was not considered necessary.
Royal Dutch Shell laid the first crude oil pipeline in the country from the Oloibiri field to Port Harcourt on Bonny River to access export facilities. Nigeria exported its first crude oil in February 1958 from the Oloibiri oil field, initially at the rate of 5,100 barrels per day (810 m3/d). The oil was being pumped from the field via the country's first pipeline, laid by Shell.
The Oloibiri oilfield produced over 20 million barrels (3,200,000 m3) of oil during its 20 years life cycle. Oil production finally stopped in 1978 and the field was abandoned the same year. The Oloibiri oilfield was abandoned without any improved recovery to drain some of the 21.26 million barrels (3,380,000 m3) of hydrocarbon still left on the field.
References