Southampton District Energy Scheme

Coordinates: 50°54′17″N 1°24′35″W / 50.9048°N 1.4096°W / 50.9048; -1.4096
From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by SDriskell (talk | contribs) at 15:03, 18 March 2016 (Added infobox.). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Southampton District Energy Scheme
Map
CountryUnited Kingdom
LocationSouthampton
Coordinates50°54′17″N 1°24′35″W / 50.9048°N 1.4096°W / 50.9048; -1.4096
StatusOperational
Commission date1986
Owner(s)Southampton City Council
Geothermal power station
Min. source temp.76 °C
Max. well depth1,800 m (5,900 ft)
External links
CommonsRelated media on Commons

The Southampton District Energy Scheme is a district heating and cooling system in Southampton, United Kingdom. The system is owned by Southampton City Council and operated by Cofely.

History

In the 1980s the Department of Energy undertook a research and development programme to examine the potential of geothermal aquifers in the UK. However, after some initial success drilling a well in the Wessex Basin in 1981, it was deemed too small to be commercially viable. The project was abandoned by the Department of Energy, but Southampton City Council took the decision to create the UK's first geothermal power scheme. This was undertaken as part of a plan to become a ‘self sustaining city’ in energy generation, promoted by then-leader of the city council Alan Whitehead.[1]

Pumping started in 1986 from the Wessex Basin aquifer at a depth of 1,800 metres and a temperature of 76 °C.[1][2] The system initially supplied only the Southampton Civic Centre, but was gradually expanded to serve over 1,000 residential properties,[1] as well as the WestQuay shopping centre, the Royal South Hants Hospital, Solent University and the Carnival offices; and is part of an enlarged city centre district heating system that includes other combined heating, cooling and power sources.

By 2007 the system had 11 km of pipes, and was producing 40GWh of heat, 22GWh of electricity and 8GWh of cooling per year.[1]