The Crescent Development project
The Crescent Development Project | |
---|---|
General information | |
Status | Under construction |
Type | office, residential, hotel, shopping mall[1][2][3] |
Location | Baku, Azerbaijan |
Construction started | October 2009 |
Estimated completion | 2017 |
Opening | Still of work in progress... |
Owner | Gilan Construction |
Height | |
Roof | The Crescent City 210 m (690 ft),[4] The Crescent Place 170 m (560 ft)[5] Crescent Hotel 166 m (545 ft)[6] |
Technical details | |
Floor count | 43 (Crescent City)[4] 33+4 (Crescent Hotel)[7] |
Design and construction | |
Architect(s) | Heerim Architects & Planners Co. Ltd. |
Main contractor | Gilan Holding |
The Crescent Development Project or The Crescent Bay (formerly known as Caspian Plus) is an under construction skyscraper complex which is being built on the Caspian Sea coast in Baku.
The complex comprises an offshore hotel (Crescent Hotel), office tower (Crescent City), residential tower, and a retail and entertainment centre (Crescent Place).
The project is intended to be an architectural landmark of Azerbaijan.[8]
History
In February 2008, skyscrapernews.com, a well-known architectural review website, published an article about two projects designed by the Korean company, Heerim Architects, for construction in Baku. The projects, both with a lunar theme, were described as, "an attempt to reinvent the concept of the skyscraper beyond the traditional".[9] The article described two skyscraper complexes, proposed for construction on neighbouring peninsulas, on opposite shores of Baku Bay. The first, Full Moon Bay, was to be constructed on the western side of the bay. It included a 158-meter, 35-storey, discoid hotel called "Palace of the Winds 1 and 2".[9] The second complex, "Caspian Plus", had been proposed for construction on the eastern edge of Baku Bay near the seaport, acting as a counterpoint to "Full Moon Bay". Initially, the second project included a 32-storey crescent-shaped hotel (standing on its "horns" offshore), four high-rise residential buildings, and a 43-story business centre standing 203 metres tall (now called Crescent City Tower).[9] The fate of the related projects remained uncertain until October 2009 when foundation work in the location of the "Caspian Plus" complex was started.[citation needed]
The project has since been modified. A trio of high-rise residential buildings was removed to avoid visual overlapping of two other buildings (Port Baku Towers and Port Baku Residence). After modification, the project consisted of a hotel ("The Crescent Hotel"), an office tower ("The Crescent City"), and a high-rise residential building with a podium ("The Crescent Place"). The previous name of the project, "Caspian Plus", was changed to "The Crescent Development Project".[10]
The project Full Moon Bay was cancelled.
Project
The "Crescent Development Project" is situated with one part on the waterfront of Baku. An offshore part, which includes "The Crescent Hotel", will be located on an artificial island about 170 metres from shore. There will be an office tower ("The Crescent City"), and a residential high-rise building with a podium ("The Crescent Place"), on the coastline behind "The Crescent Hotel".
The Crescent Hotel
"The Crescent Hotel" is a curving arched building. It is designed to look like a crescent moon with its points on the surface of the Caspian Sea. The crescent shape of the building refers to one of the symbols of Azerbaijan, depicted on its national flag. The skyscraper’s arcuate configuration will not affect the interior of the hotel as the building will rely on two multi-storey column-like towers, which will create additional space and act as a support for the hotel.[9] These supporting towers are called Eastern and Western in accordance with their location. "The Crescent Hotel" is planned to have 33 floors plus 4 storey podium.[7][11] Upon completion, the hotel will comprise 230 guest rooms, 74 apartments and 16 villas. The total area is 177 969 m²,[7] parking is planned for 601 cars.[9] "The Crescent Hotel" will be connected to the shore and other buildings of the project via bridge. This hotel is planned to be a 'seven star' facility.[12]
The Crescent City
The office tower “The Crescent City”, is a 210-metre skyscraper with 43 overground levels.[4][9] It is being built behind "The Crescent Hotel" on the waterfront next to the seaport of Baku and the “JW Marriott Absheron”. According to the project design, the facade of the building is cylindrical and slightly flattened at the north-south direction. The bottom of the tower is narrow and widens as it approaches the top which includes a concave notch. The shape of "The Crescent City" is designed to resemble a torch.
The Crescent Place
"The Crescent Place" consists of 3 basement floors and 32 overground levels: a 5-storey podium, 2 floors of town houses and a 25-storey residential tower with 2 additional penthouse levels. The Crescent Place will be located onshore next to the tower of "The Crescent City". This residential building, standing 170 metres tall, will include 168 apartments.[13] The total area of the Crescent Place is 273 000 m² with space for approximately 100 retail outlets and an additional 40 food and beverage units.
Construction
According to a report published by the management company, almost all piling work for the project had been completed by November 2013. Nine per-cent of the entire project had been constructed. Ten per-cent of the coastal part of the Project had been completed.[14]
In July 2015, DSA Architects International was appointed to take over multidisciplinary lead consultancy design services on the Crescent Development Project, with construction works ongoing.
Site of The Crescent Hotel
The plot for "The Crescent Hotel" lies within an area in the Caspian Sea. In May 2012, sheet pile setting was started. These piles were installed in two rows around the perimeter of the future hotel's location.[citation needed] A double metal fence was then installed around the site which restricted any additional water entering the area.[citation needed] Once the fence was completed, water was pumped from the site and it was filled with sand to create the foundation of the building.[citation needed] As of early 2013, the soil creating the artificial island has been formed, and foundation work for the Western and Eastern towers is completed.[15] The piles constructed for "The Crescent Hotel", with a diameter 1500–2000 mm and a length 76.1 meters, are the biggest ever built in Azerbaijan. It was planned to build 464 piles by the end of 2013.[16][17] By the beginning of 2015, development of both the Eastern and Western Towers had begun on the artificial island.
Sites of The Crescent City and Crescent Place
Construction of the onshore foundation started in October 2009. For all parts of the coastline (sites of "The Crescent City" and "The Crescent Place"), 691 short piles with a diameter of 1.2 m and a depth of 26 meters have been installed .[18] For the tower “The Crescent city” 118 deep piles (diameter 1500 mm, depth of 52-61,5 meters) were constructed.[19][20]
By November 2013, 4 taps had been installed on the site of "The Crescent Place". First floors of the podium were appearing above the fence. The construction of the residential tower, "The Crescent Place", had been started.[citation needed] By the beginning of 2015, 35th floor of The Crescent Place Tower was being constructed.
By March 2014, the foundation of "Crescent City Tower" had been ready for concrete core pouring.[citation needed] As of beginning 2015, The Crescent City Tower was being constructed at 16-17 levels. In August 2015, the concrete core of the building reached up to the 30th level. By December 2015, the 43rd level of concrete core of the Crescent City was completed.
Completion
According to a spokesman of Ilk Construction, completion of the shell and core of "The Crescent Place" is scheduled for January 2015; the site of "The Crescent City" must be finished by May of the same year.[6] Completion of the entire project is planned in the second half of 2017.[12]
Gallery
-
Construction site (01.08.2012): It is seen the fenced area of the sea designated for "The Crescent Hotel"; piling works are being conducted for onshore part of the project
-
Construction site (17.08.2012): Offshore site is being filled with sand in order to create artificial island
-
Construction site (01.03.2013): An island has been created, beginning of piles testing on it; piling works for the onshore part is being completed
-
Construction site (30.04.2013): Beginning of the piles construction on island; onshore part is ready for construction the podium
-
Construction site (18.03.2014): Podium, rising of Crescent Place concrete core, parking
-
Completion of piling works for The Crescent Hotel on artificial island (18.03.2014)
-
February 2015: General view on the project, Crescent Place is topped out, Crescent City is built at 18-19 levels, the first floors of The Crescent Hotel' towers are being built on the island
-
February 2015: The Crescent City and The Crescent Hotel
-
March 2015: View on The Crescent Place and The Crescent Hotel
-
March 2015: Construction of The Crescent Hotel
References
- ^ Heerim.com: Crescent Place
- ^ Heerim.com: Crescent Hotel
- ^ Heerim.com: Crescent City
- ^ a b c d "Crescent Development Project". Archived from the original on 2015-01-08.
{{cite web}}
: Cite has empty unknown parameter:|автор=
(help) - ^ Ilk Construction - Crescent Place & Park, Earthworks and RC Package Project
- ^ a b "APA - Первые объекты возводимого в столице Азербайджана комплекса «Айпара» будут сданы в 2015 году". apa.az. Retrieved 16 January 2015.
- ^ a b c "Kempinski Crescent Hotel & Leisure". Archived from the original on 2015-12-05.
{{cite web}}
: Cite has empty unknown parameter:|автор=
(help) - ^ Crescent Hotel
- ^ a b c d e f "Full Moon Rising". skyscrapernews.com. Retrieved 16 January 2015.
- ^ Lotos.com
- ^ "Half moon hotel shows Baku's stellar architectural ambitions - CNN.com". CNN. 16 November 2011. Retrieved 16 January 2015.
- ^ a b "Page Not Found". aecom.com. Retrieved 16 January 2015.
{{cite web}}
: Cite uses generic title (help) - ^ "Project Update: Crescent Place". thorntontomasetti.com. Retrieved 16 January 2015.
- ^ AECOM. "Baku — signatures on the skyline". slideshare.net. Retrieved 16 January 2015.
- ^ New stage of works at “Crescent” area
- ^ Lotos.com.az
- ^ Lotos.com.az
- ^ Lotos.com.az: Completion work on short piles
- ^ Lotos.com.az
- ^ Malaysian company intends to participate in the project Crescent City in Baku
External links
- Heerim Architects & Planners
- GilanHolding.com
- www.dsa-arch.com
- ThorntonTomasetti.com
- Lotos.com
- ilkconstruction.com
- AZ Architecture & Engineering Developments (AZ A&E)
- Georgios Papadogeorgakis. "G/P: Parametric Structure of the Crescent Hotel". georgiosp.com. Archived from the original on 2015-01-08. Retrieved 2015-01-08.
- Archiloverz.org
- Inside Pictures of Crescent Moon Tower Dubai