NeuConnect

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by 2a00:23c7:b70d:d501:5036:47bd:a53d:ed4b (talk) at 00:45, 27 November 2022 (→‎See also). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

NeuConnect Interconnector[1]
Location
CountryGermany, United Kingdom
General directioneast-west
FromGermany
Passes throughNorth Sea
ToEngland
Construction information
Expected2023
Technical information
Typesubmarine cable
Type of currentHVDC
Power rating1,400 MW
AC voltage400 kV
DC voltage500 kV

NeuConnect is a planned HVDC submarine power cable between England and Germany. [2] [1] [3]

Project Status

Contracts for cabling and converter stations were awarded in early in 2022. These contracts came into force in July 2022 when the project achieved financial close.[4]

In October 2022, the cable manufacturer Prysmian started production of the 725km cable.[5]

Early construction works are expected to start in 2022,[4] with major construction starting in 2023. As of October 2022, project was expected to start operations in 2028.[5]

Route

The cable will run between a new substation[6] on the Isle of Grain, in Kent in England to the new Fedderwarden substation in Wilhelmshaven in the Lower Saxony region of Germany.[1][3] Landfall will be next to Grain Coastal Park, in Kent, and at Hooksiel, near Wilhemshaven in Germany.[6]

At 725km in length, the interconnector will be one of the longest in the world.[4]

Specification

The HVDC link will consist of two main cables, each approximately 720 km (450 miles) long, together with a much thinner fibre optic cable for temperature and acoustic sensing for about 150 km (93 miles) from each landfall. The DC element will operate at 500 kV,[1] with a maximum capacity of 1,400 MW.[6]

Economics

The project is privately financed and will cost £2.4Bn (€2.8Bn). The project will deliver £1.7Bn in consumer benefits to UK consumers over 25 years, and could deliver a net reduction in carbon emissions of over 13MtCO2 in the same time.[4]

History

Neuconnect Britain Ltd. was established in 2018.[4]

NeuConnect received Interim Project Approval from Ofgem in January 2018.[7]

Public consultation events were held in July 2019.[7]

In December 2019, the planning application was submitted to Medway District Council.[7]

In December 2019, Invitations to Tender were launched for the procurement of two converter stations and 720 km of HVDC cabling.[7]

In December 2019, the Invitation to Tender (ITT) stage was launched to procure two converter stations and 720 km of HVDC cables.[8]

In January 2020, the Federal Network Agency in Germany (BNetzA) confirmed the NeuConnect interconnector project in its 2019-2030 grid development plan.[7]

In April 2020, Neuconnect completed site survey work on the Isle of Grain.[9]

A €1.2 billion cable contract was awarded in February 2022,[10] [11] and substations contract in April. [12] [11]

In July 2022, the project reached financial close, allowing early construction works to begin later in 2022. [4]

In October 2022, the cable manufacturer Prysmian started production of the 725km cable.[5]


See also

References

  1. ^ a b c d "NeuConnect Interconnector". 4Coffshore. Retrieved 25 January 2020.
  2. ^ "Project Overview". NeuConnect. Retrieved 25 January 2020.
  3. ^ a b "Project 309 - NeuConnect". TYNDP 2018 Europe's Network Development Plan to 2025, 2030 and 2040. entsoe. Retrieved 25 January 2020.
  4. ^ a b c d e f "FIRST EVER UK-GERMAN ENERGY LINK MOVES AHEAD AS £2.4BN/€2.8BN NEUCONNECT PROJECT REACHES FINANCIAL CLOSE" (Press release). NeuConnect News. 7 July 2022. Retrieved 9 September 2022.
  5. ^ a b c "CABLING PRODUCTION STARTS ON NEUCONNECT IN IMPORTANT MILESTONE FOR FIRST EVER UK-GERMAN ENERGY LINK". NeuConnect News Releases. NeuConnect. 4 October 2022. Retrieved 5 November 2022.
  6. ^ a b c Proposals for the NeuConnect Interconnector Public Information Leaflet (PDF). NeuConnect. Retrieved 26 January 2020.
  7. ^ a b c d e "Project News". NeuConnect. Retrieved 25 January 2020.
  8. ^ "NEUCONNECT'S MAJOR £1BN PROCUREMENT PROGRAMME MOVES TO NEXT STAGE, KEEPING VITAL NEW ENERGY LINK FIRMLY ON TRACK". Retrieved 26 April 2020.
  9. ^ "NEUCONNECT COMPLETES SITE SURVEY WORKS AS NEW ENERGY LINK CONTINUES TO MAKE GOOD PROGRESS". NeuConnect. Retrieved 26 April 2020.
  10. ^ "Prysmian Wins EUR 1.2 Billion Contract to Deliver UK-Germany Interconnector". Offshore Wind. 2 March 2022.
  11. ^ a b "NEUCONNECT AWARDS OVER £1.5BN OF MAJOR CONTRACTS AS FIRST EVER UK-GERMAN ENERGY LINK MOVES AN IMPORTANT STEP CLOSER". News. NeuConnect. 11 April 2022. Retrieved 22 April 2022. Contractors selected for cabling and converter station works on new interconnector that will connect two of Europe's largest energy markets for first time
  12. ^ "Siemens Energy receives order for power connection to Great Britain". www.windtech-international.com.