Project network

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Biogeographist (talk | contribs) at 17:36, 16 May 2019 (→‎See also: capitalization; alphabetized; removed red links). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

A project network is a graph (weighted directed graph) depicting the sequence in which a project's terminal elements are to be completed by showing terminal elements and their dependencies. It is always drawn from left to right to reflect project chronology.[1][2]

The work breakdown structure or the product breakdown structure show the "part-whole" relations. In contrast, the project network shows the "before-after" relations.

The most popular form of project network is activity on node (AON) (as shown above), the other one is activity on arrow (AOA).

The condition for a valid project network is that it doesn't contain any circular references.

Project dependencies can also be depicted by a predecessor table. Although such a form is very inconvenient for human analysis, project management software often offers such a view for data entry.

An alternative way of showing and analyzing the sequence of project work is the design structure matrix or dependency structure matrix.