This is an old revision of this page, as edited by Marcocapelle (talk | contribs) at 18:00, 27 October 2016 (removed Category:Business economics; added Category:Costs using HotCat). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Overnight cost is the cost of a construction project if no interest was incurred during construction, as if the project was completed "overnight."

The overnight cost is frequently used when describing power plants. The unit of measure typically used when citing the overnight cost of a power plant is $/kW. For example, the overnight cost of a nuclear plant might be $5,000/kW, so a 1000 MW plant would have an overnight cost $5 billion. (Interest on the $5 billion spent during construction would be extra.)