This is an old revision of this page, as edited by GreenC bot (talk | contribs) at 20:19, 23 August 2023 (Removed 1 archive link; reformat 3 citations per Category:CS1 errors: archive-url. Wayback Medic 2.5). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

William R. Bennett Bridge
The bridge seen from Kelowna City Park
Coordinates49°52′47″N 119°30′43″W / 49.879648°N 119.511852°W / 49.879648; -119.511852
Carries5 lanes of Highway 97, pedestrians and bicycles
CrossesOkanagan Lake
LocaleKelowna, British Columbia, Canada
Official nameWilliam R. Bennett Bridge
Maintained byProtrans WRB Bridge (SNC-Lavalin)
Characteristics
DesignPontoon bridge
Longest span44 metres (144 ft)
Clearance below18 metres (59 ft)
History
OpenedMay 25, 2008
Statistics
Daily traffic50,000 vehicles
Location
Map

The William R. Bennett Bridge is a pontoon bridge in the Okanagan Valley of British Columbia, Canada. Completed on May 25, 2008, the bridge replaced the older Okanagan Lake Bridge built in 1958 to link Downtown Kelowna to West Kelowna across Okanagan Lake as part of Highway 97.

On April 21, 2005, Premier Gordon Campbell officially renamed the bridge, then the Okanagan Lake Bridge, the William R. Bennett Bridge in honour of former premier Bill Bennett, a native of Kelowna.

Construction budget

The first press release from the British Columbia Ministry of Transportation to include budget information was in 2003. At that time, the project was estimated to cost CA$100 million for the bridge and another $20 million for the two interchange upgrades on the west side of the lake.[1]

By June 29, 2005, the cost of the bridge had increased from the previous estimate of $100 million to $144 million "due to dramatic increases in the cost of construction materials and labour", which included significant increases in the cost of concrete, steel, and fuel. Over the next 30 years, the province of British Columbia expected to pay SNC-Lavalin a total of $179 million "to design, build, finance, operate, maintain and rehabilitate the bridge".[2]

Construction schedule

  • April 2005: Arthon Construction begins bridge end preloads from rock on Westside Road
  • May 2005: Arthon completes east side preload
  • June 2005: SNC-Lavalin is chosen to design, build, finance and operate the new bridge
  • July 2005: Construction begins on a dry dock near Bear Creek Provincial Park, where the bridge pontoons will be built
  • Q3 2005: Arthon completes preloads on west side of Lake Okanagan
  • Q3 2005: Graving dock ready
  • Q3 2006: Roadwork on both approaches begins
  • Q4 2006: First four pontoons in place
  • Q1 2007: Bridge deck construction begins
  • Q4 2007: All pontoons in place
  • Q4 2007: Roadwork on both approaches is completed
  • Q1 2008: Bridge deck construction is completed
  • Q2 2008: Test and commission
  • Q2 2008: Bridge officially opens
    • Official opening scheduled for May 25, 2008
  • Q2 2009: Decommission of the old bridge
  • Q2 2009: Shoreline restoration

Bridge facts

  • Extending 1,060 metres (3,478 ft) long in total, the bridge includes a 690-metre (2,264 ft) string of long poles holding pontoons supporting an elevated deck[3]
  • At the deepest point near the middle of the bridge, the lake is approximately 60 metres (197 ft) deep
  • There are a total of 9 concrete pontoons
  • The pontoons are 25 metres (82 ft) wide and 60 to 90 metres (197 to 295 ft) long
  • The navigation span on the west side of the bridge is 44 metres (144 ft) long and provides 18 metres (59 ft) of clearance between the bridge and the lake[1]
  • Three lanes are for westbound traffic
  • Two lanes are for eastbound traffic
  • An additional 1.3 metres (4 ft 3 in) wide pedestrian and cyclist pathway exists on the south (eastbound) side of the bridge
  • The west side of the bridge has a pedestrian, cyclist, and vehicle underpass at Campbell Road and another interchange at Westside Road
  • The Kelowna side of the bridge retains the existing pedestrian and cyclist underpass between City Park and Lake Avenue
  • The new bridge was designed to handle up to 80,000 vehicles daily; the old Okanagan Lake Bridge was designed to handle 38,000 vehicles daily but, in 2005, handled approximately 50,000 vehicles daily[4][5]
  • The bridge is maintained by Protrans WRB Bridge, which is a subsidiary of SNC-Lavalin[6]

See also

References

  1. ^ Province of British Columbia (28 Oct 2003). "New Bridge Fulfils Premier's Commitment to Kelowna" (PDF). Government of British Columbia. Archived from the original (PDF) on 18 July 2011. Retrieved 11 December 2022.
  2. ^ Province of British Columbia (29 June 2005). "SNC-Lavalin Chosen To Deliver William R. Bennett Bridge" (PDF). Government of British Columbia. Archived from the original (PDF) on 11 June 2011. Retrieved 11 December 2022.
  3. ^ Ministry of Transportation and Infrastrucutre. "Profile of the Elevated Portion of the William R. Bennett Bridge" (PDF). th.gov.bc.ca. Ministry of Transportation and Infrastructure. Archived from the original (PDF) on 2011-06-11. Retrieved 11 December 2022.
  4. ^ McHugh, Anne-Rachelle (8 February 2006). "Public hates billboards -- report". Westside Weekly.
  5. ^ Canadian Consulting Engineer Staff. "William R. Bennett Bridge". canadianconsultingengineer.com. Canadian Consulting Engineer. Retrieved 11 December 2022.
  6. ^ Protrans WRB. "Protrans WRB Bridge". Protrans WRB Bridge. Retrieved 11 December 2022.