Location of Sır Dam in Turkey
Official nameSır Baraji
CountryTurkey
LocationKahramanmaraş Province
Coordinates37°30′2.9″N 36°35′45.35″E / 37.500806°N 36.5959306°E / 37.500806; 36.5959306
StatusOperational
Construction began1987
Opening date1991
Dam and spillways
Type of damConcrete arch
Height116 m (381 ft)
Dam volume494,000 m3 (646,128 cu yd)
Reservoir
Total capacity1,120,000,000 m3 (907,999 acre⋅ft)
Surface area48 km2 (19 sq mi)
Power Station
TypeConventional
Turbines3 x 95 MW Francis-type
Installed capacity285 MW
Annual generation725 GWh

The Sır Dam is an arch dam on the Ceyhan River in Kahramanmaraş Province of southern Turkey. There is a hydroelectric power plant, established in 1991, at the dam, with a power output of 285 MW.[1]

Involuntary Resettlement

According to Terminski (2013), the construction of the dam resulted in involuntary resettlement of approximately 45,000 people.[2]

References

  1. ^ "Sir Dam". State Hydraulic Works. Retrieved 25 November 2011.
  2. ^ Bogumil Terminski, (2013). Development-Induced DIsplacement and Resettlement: Theoretical Frameworks and Current Challenges, Geneva, 2013.