Guxian Dam

Coordinates: 34°14′24″N 111°16′38″E / 34.24000°N 111.27722°E / 34.24000; 111.27722
From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Monkbot (talk | contribs) at 21:03, 21 September 2019 (top: Task 16: replaced (1×) / removed (0×) deprecated |dead-url= and |deadurl= with |url-status=;). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Guxian Dam
Guxian Dam is located in China
Guxian Dam
Location of Guxian Dam in China
CountryChina
LocationLuoning County
Coordinates34°14′24″N 111°16′38″E / 34.24000°N 111.27722°E / 34.24000; 111.27722
Construction began1978
Opening date1993
Dam and spillways
Type of damConcrete gravity
Height125 m (410 ft)
Length315 m (1,033 ft)
Elevation at crest553 m (1,814 ft)
Width (crest)9 m (30 ft)
Spillway type5 x tainter gate
Reservoir
Total capacity1,175,000,000 m3 (952,588 acre⋅ft)
Catchment area5,370 km2 (2,073 sq mi)
Power Station
Commission date1992
Turbines3 x 20 MW Francis-type
Installed capacity60 MW

The Guxian Dam is a concrete gravity dam on the Luo River, a tributary of the Yellow River, in Luoning County, Henan Province, China. The primary purpose of the dam is flood control but it also generates hydroelectricity and provides water for irrigation. The 125 m (410 ft) tall dam withholds a reservoir of 1,175,000,000 m3 (952,588 acre⋅ft) and provides 848,000,000 m3 (687,485 acre⋅ft) in flood storage. The dam's power station contains three 20 MW Francis turbine-generators for a total installed capacity of 60 MW. Construction on the dam began in 1958 but was suspended several times afterwards. It recommenced in 1978 and the reservoir began to fill in 1991. The dam's generators were commissioned in 1992 and the project complete in 1993. The dam's spillway is controlled by five tainter gates and has a maximum discharge capacity of 11,436 m3/s (403,859 cu ft/s). Flip buckets are used at the spillway base to dissipate water. On the right side of the spillway there are two intermediate orifice openings controlled by hydraulic press-operated radial gates. Two bottom outlets are set on the spillway's left side, also controlled by hydraulic press-operated radial gates. To the left of the bottom outlets is the power station.[1][2]

See also

References

  1. ^ "Guxian Dam and Reservoir Project". ChinaWater. Archived from the original on 1 October 2011. Retrieved 30 August 2011.
  2. ^ "China's highest Concrete Gravity Dams". Chinese National Committee on Large Dams. Retrieved 30 August 2011.