Incremental launch

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Noleander (talk | contribs) at 03:41, 27 July 2020 (Notable examples: Better link). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Incremental launch bridge construction
Incrementally-launched bridge construction Itz Valley Bridge near Coburg

Incremental launch is a method in civil engineering of building a complete bridge deck from one abutment of the bridge only, manufacturing the superstructure of the bridge by sections to the other side. In current applications, the method is highly mechanised and uses pre-stressed concrete.[1]: 1 

History

The first bridge to have been incrementally launched appears to have been the Waldshut–Koblenz Rhine Bridge, a wrought iron lattice truss railway bridge, completed in 1859. The second incrementally launched bridge was the Rhine Bridge, a railway bridge that spanned the Upper Rhine between Kehl, Germany and Strasbourg, France, completed in 1861 and subsequently destroyed and rebuilt on several occasions.

The first incrementally launched concrete bridge was the 96-metre (315 ft) span box girder bridge over the Caroní River, completed in 1964. The second incrementally launched concrete bridge was over the Inn River, Kufstein in Austria, completed in 1965. The structural engineers for both bridges were Professor Dr Fritz Leonhardt and his partner, Willi Baur.[1]: 1 

The usual method of building concrete bridges is the segmental method, one span at a time.[2]

Method

The bridges are mostly of the box girder design and work with straight or constant curve shapes, with a constant radius. 15-to-30-metre (49 to 98 ft) box girder sections of the bridge deck are fabricated at one end of the bridge in factory conditions. Each section is manufactured in around one week.[citation needed]

The first section of the launch, the launching nose, is not made of concrete, but is a stiffened steel plate girder and is around 60% of the length of a bridge span, and reduces the cantilever moment.[3] The sections of bridge deck slide over sliding bearings, which are concrete blocks covered with stainless steel and reinforced elastomeric pads.

Notable examples

References

  1. ^ a b "The incremental launching method in prestressed concrete bridge construction" (PDF). Berne, Switzerland: VSL International Limited. April 1977. Retrieved 20 April 2020.
  2. ^ Liu, Xian Peng; Qin, Zong Ping; Leung, L. W.; Yue, Lingling (2007). "Construction of the Precast Segmental Approach Structures for Sutong Bridge" (PDF). ICE Conference 2007. Beijing, China: YWL. Retrieved 20 April 2020.
  3. ^ "The Charming History of the Incremental Launching Method". BridgeTech. The Bridge Engineering eManuals Project. 2020. Retrieved 20 April 2020.