Dasmariñas–Las Piñas Transmission Line

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Ervin111899 (talk | contribs) at 15:25, 4 August 2020. The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Dasmariñas–Las Piñas Transmission Line
Some of its steel poles along Aguinaldo Highway in Dasmariñas, Cavite.
Some of its steel poles along Aguinaldo Highway in Dasmariñas, Cavite.
Location
CountryPhilippines
ProvinceCavite
Metro Manila
FromDasmariñas Substation
ToLas Piñas Substation
Ownership information
OwnerNational Power Corporation (2001–2003)
National Transmission Corporation (2003–present)
OperatorNational Power Corporation (2001–2003)
National Transmission Corporation (2003–2009)
National Grid Corporation of the Philippines (2009–present)[a]
Construction information
CommissionedNovember 30, 2001; 22 years ago (November 30, 2001)
Technical information
Type of currentHVAC
No. of transmission towers210 (209 steel poles and 1 lattice tower)
AC voltage230 kV
No. of poles209
No. of circuits2

The Dasmariñas–Las Piñas Transmission Line (abbreviated as 8LI1DAS-LPI and 8LI2DAS-LPI) is a 230,000 volt, double-circuit transmission line in Metro Manila and Calabarzon, Philippines that connects Dasmariñas and Las Piñas substations of National Grid Corporation of the Philippines (NGCP).

Route description

Steel poles 202–209 (with 202, 204, 205, and 208 are suspension towers and have flag design while 203, 206, 207, and 209 are anchor towers) along Manila-Cavite Expressway (CAVITEX) in Las Piñas, Metro Manila and Bacoor, Cavite.

The Dasmariñas–Las Piñas Transmission Line went into service in November 30, 2001[1]. Originally commissioned by the government-owned National Power Corporation (NAPOCOR), it is now operated and maintained by privately-owned National Grid Corporation of the Philippines (NGCP). It passes through the cities of Dasmariñas, Imus, and Bacoor in Cavite, and Las Piñas in Metro Manila.

The transmission line starts at Dasmariñas substation, turns left into Ramon Tirona Avenue, and run parallel with Aguinaldo Highway until Bacoor. Upon approaching Bacoor Junction, it will parallel with Aguinaldo Boulevard until Bacoor Exit of Manila-Cavite Expressway (CAVITEX). It then utilize the eastern side of CAVITEX until its terminus at Las Piñas substation.

Statistics

The transmission line consists of 209 steel poles (1–209) and 1 lattice tower (208A).

Expansion and improvements

In order to protect the steel poles from corrosion, several poles are being painted with aluminum paint.

In 2016, NGCP constructed lattice tower 208A that connects to 3rd 300 MVA transformer at Las Piñas Substation on a location where a water tower was once located.

Controversy

Notes

  1. ^ As stated on danger plate sign placed on tower 208A.

References

  1. ^ "Project Completion Report on the Power Transmission project (Loan 1288-PHI) to the Philippines (December 2002)" (PDF). www.adb.org. Retrieved August 3, 2020.