Upper Marsyangdi A Hydroelectric Station

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Nirmaljoshi (talk | contribs) at 03:27, 17 November 2020 (See also). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Upper Marsyandgi A Hydroelectric Station
Upper Marsyangdi A Hydroelectric Station is located in Nepal
Upper Marsyangdi A Hydroelectric Station
Location of Upper Marsyandgi A Hydroelectric Station in Nepal
Official nameUpper Marsyandgi A Hydroelectric Station
CountryNepal
Coordinates28°16′59″N 84°21′38″E / 28.283°N 84.36063°E / 28.283; 84.36063
PurposePower
StatusOperational
Construction began8 Jan 2013[1]
Owner(s)Joint venture of Power China Resources Ltd and Sino-Sagarmatha Power Company
Dam and spillways
Type of damGravity
ImpoundsMarshyangdi River
Upper Marsyandgi A Hydroelectric Station
Coordinates28°16′59″N 84°21′38″E / 28.283°N 84.36063°E / 28.283; 84.36063
Commission date2076-06-20 BS
TypeRun-of-the-river
Turbines2 x 25 MW Francis-type
Installed capacity50 MW

Upper Marsyandgi A Hydroelectric Station is a run-of-river hydro-electric plant located in Bhulbhule of Lamjung district of western Nepal.[2] The flow from Marshyangdi River is used to generate 50 MW electricity. The energy is evacuated by a 25 km long, 132 kv single circuit transmission line from Bhulbhule (powerhouse) to Middle Marsyangdi Hydropower Project.[2]

The project construction started in October 2012 and was expected to be completed in December 2015, but it was delayed due to the earthquake last year and the Indian blockade. First turbine was installed on 25 September 2016. The second turbine was added on 23 December 2016.[3] It is the first project to use a vortex type settling basin.[citation needed]

Funding

It is the first project in Nepal built with foreign direct investment from China.[4] The project was developed by Joint venture of Power China Resources Ltd and Sino-Sagarmatha Power Company Nepal.[5][6] Sino-Sagarmatha owns 10% share. Power China Resources Ltd, which holds 90% share, used 75% loan and 25% equity for the project. The project's payback period is 10 years.Nepal Electricity Authority buys the energy at 0.5999 USDollars per unit from this project.[2]

Environment concerns

  • Since the Marshyangi river is popular for rafting, the construction of the dam has dried up the downstream stretch that has disrupted the rafting and fishing in this area.[7]

See also

References

  1. ^ "Upper Marsyangdi A Hydropower Station, Nepal". Retrieved 2020-08-03.
  2. ^ a b c "Upper Marsyangdi to generate power from today". The Himalayan Times. 2016-09-25. Retrieved 2020-08-03.
  3. ^ "Upper Marsyangdi 'A' Operating in Full Capacity". Retrieved 2020-08-03.
  4. ^ "First half of Nepal's 50-MW Upper Marsyangdi hydroelectric project commissioned". Hydro Review. 2016-09-26. Retrieved 2020-08-03.
  5. ^ "China-invested hydropower plant starts operation in Nepal - China.org.cn". Retrieved 2020-08-03.
  6. ^ "Operating Projects :: Hydro (Above 1MW)".
  7. ^ "Caught in a series of dams and hydro projects, is Nepal's Marsyangdi river slowly drying up?". Firstpost. Retrieved 2020-08-03.