Gateway Expressway

State Road 686A, State Road 690
Aerial map of Gateway Expressway
Route information
Maintained by Florida's Turnpike Enterprise
StatusUnder construction
History
  • Approved February 2014
  • Construction started August 21, 2017[1]
Major junctions
East end I-275 in St. Petersburg
West endLua error in Module:Jct at line 204: attempt to concatenate local 'link' (a nil value). in Pinellas Park
SR 686 at Bayside Bridge
Location
CountryUnited States
StateFlorida
CountiesPinellas
Highway system
SR 688SR 690 SR 692

The Gateway Expressway is a planned toll road in Pinellas County, Florida. The project consists of two branches: an elevated highway to be designated State Road 690 (SR 690) above 118th Avenue North between Interstate 275 (I-275) and U.S. Highway 19 (US 19) and a raised highway in the median of SR 686 from 118th Avenue North to the Bayside Bridge. Construction was approved in February 2014 and began in November 2017. The expressway is expected to be completed by late 2021.[1]

Route description

The Gateway Expressway consists of two connected segments:

  • A four-lane, elevated segment will run above 118th Avenue from US 19 to I-275. This section will be designated SR 690.
  • A raised, four lane expressway will be built in the median of SR 686 and carry the designation SR 686A.[1] This segment will run from the planned SR 690 segment north to the Bayside Bridge and connect to St. Petersburg–Clearwater International Airport.

Both segments will be tolled using electronic toll gantries for SunPass transponders or pay-by-plate billing.[2]

History

The intention of the Gateway Expressway project is to solve transportation problems in Pinellas County, where several expressway projects were cancelled in the 1970s and 1980s, leaving the county without any major limited-access thoroughfares except for I-275. Significant upgrades to US 19 in the 2000s improved traffic flow north–south in the county. However, only local roads travel east–west. The Gateway Expressway project had been identified for a long time as a priority project to improve traffic flow in Pinellas County.[3]

The project was announced by Governor Rick Scott in a press conference with local officials on February 17, 2014. It had been in the works for 15 years. Construction began in November 2017 and is expected to be complete in late 2021 at a cost of $545 million USD. The project was not expected to be funded for another 15–20 years.[4] Funding will be provided by the Federal Highway Administration ($153 million), Penny for Pinellas funds ($53 million), and the State of Florida (remainder of project costs).[3]

Major intersections

State Road 690

The entire route is in Pinellas County.

LocationmikmDestinationsNotes
St. Petersburg0.000.00 I-275Eastern terminus
28th Street NorthEastbound entry only. No toll to I-275
118th Avenue NorthWestbound exit only. No toll from I-275.
Toll gantry
Pinellas Park SR 686Connects with raised, express lanes only. Westbound exit and eastbound entry.
118th Avenue NorthWestbound exit and eastbound entry. Provides access from northbound US 19 and access to southbound US 19.
US 19Western terminus of SR 690 segment. Westbound exit (to northbound US 19 only) and eastbound eastbound entrance (from southbound US 19 only)
1.000 mi = 1.609 km; 1.000 km = 0.621 mi

State Road 686A express lanes

The entire route is in Pinellas County.

LocationmikmDestinationsNotes
Pinellas Park0.000.00 SR 690Southern terminus. Access only from westbound SR 690 and access to eastbound SR 690.
SR 688 (Ulmerton Road)No exit southbound. Toll gantry on northbound entrance.
St. Pete–Clearwater International AirportNo entry northbound
Largo SR 686 (Roosevelt Boulevard)Northern northbound terminus.
CR 611Module:Jct warning: "road" parameter is deprecatedNorthern southbound terminus. Southbound entry only.
1.000 mi = 1.609 km; 1.000 km = 0.621 mi

See also

References

  1. ^ a b c Florida Department of Transportation (January 23, 2018). "Gateway Expressway 433880-1-52-01". FDOT Current Projects. Retrieved January 30, 2018.
  2. ^ Schorsch, Peter (February 17, 2014). "Game-Changer: FDOT Plans Elevated Toll Road to Connect I-275 and US 19". Saint Peters Blog. Retrieved May 3, 2014.
  3. ^ a b O’Donnell, Christopher (February 17, 2014). "Accelerated Plan will link I-275, US 19 in Pinellas". Tampa Tribune. Retrieved May 3, 2014.
  4. ^ Staff (February 17, 2014). "Governor Scott Announces Advancement of Gateway Express Project in Pinellas County" (Press release). Office of the Governor of Florida. Retrieved May 3, 2014.