Hsieh-ho Power Plant
Hsieh-ho Power Plant 協和發電廠 | |
---|---|
Country | Taiwan |
Location | Zhongshan, Keelung |
Coordinates | 25°09′26″N 121°44′22″E / 25.157328°N 121.739325°E |
Status | Operational |
Commission date | January 1977 (Unit 1)[1] December 1977 (Unit 2) March 1980 (Unit 3)[2] 1985 (Unit 4)[3] |
Owner | Taipower |
Operator | Taipower |
Thermal power station | |
Primary fuel | Oil |
Power generation | |
Units operational | 4 X 500 MW |
Nameplate capacity | 2,000 MW |
External links | |
Commons | Related media on Commons |
The Hsieh-ho Power Plant (Chinese: 協和發電廠; pinyin: Xiéhé Fādiànchǎng) is an oil-fired power plant in Zhongshan District, Keelung, Taiwan.[4][5] The power plant is the only fully oil-fired power plant in Taiwan.
Generation units
The power plant consists of four 500-MW generation units. The third 500-MW unit was finished on 19 December 1979 after a record-breaking construction period of 26 months. It went into operation in March 1980. The fourth 500-MW unit was completed in 1985 after 29 months construction period.[2][3]
Components
The steam generator is rated at 1,701 tonne/hour, 176 kg/cm3 and 542 °C at superheater outlet and reheat to 542 °C.
The steam turbine is a tandem-compound with four flow exhaust, 3,600 rpm single reheat with throttle steam conditions of 166 kg/cm2, 538 °C with reheat to 538 °C.
The stacks are 200 meters high slip-form reinforced concrete stack.
Transportation
Hsieh-ho Power Plant is accessible North from TRA Keelung Station.
See also
References
- ^ http://web3.moeaboe.gov.tw/ECW/english/content/ContentLink.aspx?menu_id=1540
- ^ a b http://taiwaninfo.nat.gov.tw/ct.asp?xItem=138601&CtNode=103&htx_TRCategory=&mp=4
- ^ a b http://www.gibsin.com.tw/old/Case-HsiehHoFPP.pdf
- ^ "Gibsin Engineer, Ltd : Fossil Power Plant - Project Name : Hsieh-Ho Fossil Power Plant Unit" (PDF). Gibsin.com. Retrieved 2013-10-04.
- ^ "Hsieh-Ho Oil Power Station Taiwan - GEO". Globalenergyobservatory.org. 2010-02-15. Retrieved 2013-10-04.