Ubolratana Dam
Upstream side of dam
Ubol Ratana Dam is located in Thailand
Ubol Ratana Dam
Location of Ubolratana Dam in Thailand
Official nameUbol Ratana Dam
LocationKhon Kaen Province, Thailand
Opening date1966
Owner(s)Electricity Generating Authority of Thailand (EGAT)
Dam and spillways
Type of damEarth core rock-fill dam
ImpoundsPhong River
Height32 m (105 ft)
Length885 m (2,904 ft)
Reservoir
CreatesUbol Ratana Reservoir
Total capacity2,263,000 m3 (79,900,000 cu ft)
Catchment area12,104 km2 (4,673 sq mi)
Power Station
Operator(s)Electricity Generating Authority of Thailand (EGAT)
Turbines3 x 8.4 MW Kaplan-type
Installed capacity25.2 MW
Annual generation57 GWh

The Ubol Ratana Dam (pronounced: Ubon Rat), formerly known as the "Phong Neeb Dam", is a multi-purpose dam in tambon Khok Sung, Ubolratana District, approximately 50 km (31 mi) north of Khon Kaen, Khon Kaen Province, Thailand. It was the first hydroelectric power project developed in the Thailand's northeastern area of Isan.[1] The dam impounds the Nam Phong, a tributary of the Mekong River. The dam was given its current name by royal permission in 1966, in honour of Thai princess Ubolratana Rajakanya.

Description

The dam is multi-purpose: electricity generation, irrigation, flood control, transportation, fisheries, and as tourist attraction.[2] It is an earth core rockfill dam, constructed in 1964. It's crest length is 885 m (2,904 ft), and 32 m (105 ft) high. Its catchment area is 12,104 km2 (4,673 sq mi). Its reservoir has a maximum storage capacity of 2,263,000 m3 (79,900,000 cu ft).[3]

The dam is managed by the Electricity Generating Authority of Thailand (EGAT).

Thirty thousand people were resettled to make way for the large reservoir accompanying the dam. This resettlement resulted in a sharp decrease in forested areas in the catchment areas and an increase in erosion.

In 1984, the dam was modified to reinforce dam safety and to ensure better flood protection.

Power plant

The power plant at the dam has three turbines, each with an installed capacity of 8,400 KW. The dam generates an average of 57 GWh a year. The operation of the turbines commenced on 4 February 1966, 14 March 1969, and 12 June 1968 respectively.[2]

History

In April 2016 the dam ran dry for the first time since its construction. With no usable storage it cannot provide irrigation water, cannot generate electricity, and its fish population is dying. Its usable storage stands at minus 3.95 percent (as of (2016-04-04).[4]

Ubol Ratana Dam is the first of the royal dams to run dry. The other royal dams are:[1]

  • Bhumibol Dam: opened in 1964 in the north on the Ping River. Capacity: 13,462,000,000 m3.
  • Sirindhorn Dam: opened in 1971 in the northeast on the Lam Dom Noi River. Capacity: 1,966,000,000 m3
  • Chulabhorn Dam: opened in 1972 in the northeast on the Phrong River. Capacity: 165,000,000 m3
  • Sirikit Dam: opened in 1974 in the north on the Nan River. Capacity: 9,510,000,000 m3
  • Srinagarind Dam: opened in 1980 in the west on the Khwae Yai River. Capacity: 17,745,000,000 m3
  • Vajiralongkorn Dam: opened in 1984 in the west on the Khwae Noi River. Capacity: 8,100,000 m3

Due to the on-going drought, the royal dams are heavily stressed. According to the Hydro and Agro Informatics Institute, as of 3 April 2016, sixteen Thai dams are at critically low levels of usable reservoir storage. Of the other royal dams, Bhumibol Dam is at four percent, Sirindhorn Dam is at 10 percent, Srinagarind Dam is at 11 percent, Sirikit Dam is at 12 percent, Chulabhorn Dam is at 13 percent, and Vajiralongkorn Dam is at 14 percent.[1]

See also

References

  1. ^ a b c Draper, John (2016-04-04). "A Royal Dam Runs Dry". Prachatai English. Retrieved 5 April 2016.
  2. ^ a b "Renovation of Small Hydropower Plants by Hydropower Construction Division in 2005". Electricity Generating Authority of Thailand. Archived from the original on 2010-01-14. Retrieved 2011-01-30.
  3. ^ "Ubol Ratana Dam". Electricity Generating Authority of Thailand (EGAT). Retrieved 5 April 2016.
  4. ^ "Report of EGAT reservoir storage conditions". Thaiwater.net. Hydro and Agro Informatics Institute (HAII). 2016-04-04. Retrieved 5 April 2016.