Overall equipment effectiveness: Difference between revisions

From Wikipedia, the free encyclopedia
Content deleted Content added
Chris 73 (talk | contribs)
→‎Overall equipment effectiveness: better example for calculation, much easier
Chris 73 (talk | contribs)
Line 31: Line 31:
OEE breaks the performance of a manufacturing unit into three separate but measurable components: Availability, Performance, and Quality. Each component points to an aspect of the process that can be targeted for improvement. OEE may be applied to any individual Work Center, or rolled up to Department or Plant levels. This tool also allows for drilling down for very specific analysis, such as a particular Part Number, Shift, or any of several other parameters.
OEE breaks the performance of a manufacturing unit into three separate but measurable components: Availability, Performance, and Quality. Each component points to an aspect of the process that can be targeted for improvement. OEE may be applied to any individual Work Center, or rolled up to Department or Plant levels. This tool also allows for drilling down for very specific analysis, such as a particular Part Number, Shift, or any of several other parameters.
It is unlikely that any manufacturing process can run at 100% OEE. Many manufacturers benchmark their industry to set a challenging target; 85% is not uncommon.
It is unlikely that any manufacturing process can run at 100% OEE. Many manufacturers benchmark their industry to set a challenging target; 85% is not uncommon.
OEE is calculated with the formula (Availability)*(Performance)*(Quality)
*OEE is calculated with the formula (Availability)*(Performance)*(Quality)
Using the examples given below:
*Using the examples given below:
(Availability= 86.6%)*(Performance=93%)*(Quality=91.3%)= (OEE=73.6%)
*(Availability= 86.6%)*(Performance=93%)*(Quality=91.3%)= (OEE=73.6%)
Alternatively, and often easier, OEE is calculated by dividing the minimum time needed to produce the parts under optimal conditions by the actual time needed to produce the parts. For example:
Alternatively, and often easier, OEE is calculated by dividing the minimum time needed to produce the parts under optimal conditions by the actual time needed to produce the parts. For example:
Total Time: 8 hour shift or 28.800 seconds, producing 14.400 parts, or one part every 2 seconds.
*Total Time: 8 hour shift or 28.800 seconds, producing 14.400 parts, or one part every 2 seconds.
Fastest possible cycle time is 1,5 seconds, hence only 21.600 seconds would have been needed to produce the 14.400 parts. The remaining 7.200 seconds or 2 hours were lost.
*Fastest possible cycle time is 1,5 seconds, hence only 21.600 seconds would have been needed to produce the 14.400 parts. The remaining 7.200 seconds or 2 hours were lost.
The OEE is now the 21.600 seconds divided by 28.800 seconds, equal to 1,5 seconds per part divided by 2 seconds, or 75%.
*The OEE is now the 21.600 seconds divided by 28.800 seconds, equal to 1,5 seconds per part divided by 2 seconds, or 75%.


=== Total effective equipment performance ===
=== Total effective equipment performance ===

Revision as of 21:29, 5 January 2014

Overall equipment effectiveness (OEE) is a hierarchy of metrics developed by Seiichi Nakajima[who?] in the 1960s to evaluate how effectively a manufacturing operation is utilized. It is based on the Harrington Emerson way of thinking regarding labor efficiency.[citation needed] The results are stated in a generic form which allows comparison between manufacturing units in differing industries. It is not however an absolute measure and is best used to identify scope for process performance improvement, and how to get the improvement. If for example the cycle time is reduced, the OEE will increase i.e more product is produced for less resource. Another example is if one enterprise serves a high volume, low variety market, and another enterprise serves a low volume, high variety market. More changeovers (set-ups) will lower the OEE in comparison, but if the product is sold at a premium, there could be more margin with a lower OEE.

OEE measurement is also commonly used as a key performance indicator (KPI) in conjunction with lean manufacturing efforts to provide an indicator of success. OEE can be illustrated by a brief discussion of the six metrics that comprise the system. The hierarchy consists of two top-level measures and four underlying measures.

The top-level metrics

Overall equipment effectiveness (OEE) and total effective equipment performance (TEEP) are two closely related measurements that report the overall utilization of facilities, time and material for manufacturing operations. These top view metrics directly indicate the gap between actual and ideal performance.

  • Overall equipment effectiveness quantifies how well a manufacturing unit performs relative to its designed capacity, during the periods when it is scheduled to run.
  • Total effective equipment performance (TEEP) measures OEE against calendar hours, i.e.: 24 hours per day, 365 days per year.

The underlying metrics

In addition to the above measures, there are four underlying metrics that provide understanding as to why and where the OEE and TEEP gaps exist.

The measurements are described below:

  • Loading: The portion of the TEEP Metric that represents the percentage of total calendar time that is actually scheduled for operation.
  • Availability: The portion of the OEE Metric that represents the percentage of scheduled time that the operation is available to operate. Often referred to as Uptime.
  • Performance: The portion of the OEE Metric that represents the speed at which the Work Center runs as a percentage of its designed speed.
  • Quality: The portion of the OEE Metric that represents the Good Units produced as a percentage of the Total Units Started. Commonly referred to as First Pass Yield FPY.

Calculations for OEE and TEEP

What follows is a detailed presentation of each of the six OEE / TEEP Metrics and examples of how to perform calculations. The calculations are not particularly complicated, but care must be taken as to standards that are used as the basis. Additionally, these calculations are valid at the work center or part number level but become more complicated if rolling up to aggregate levels.[1]

Overall equipment effectiveness

OEE breaks the performance of a manufacturing unit into three separate but measurable components: Availability, Performance, and Quality. Each component points to an aspect of the process that can be targeted for improvement. OEE may be applied to any individual Work Center, or rolled up to Department or Plant levels. This tool also allows for drilling down for very specific analysis, such as a particular Part Number, Shift, or any of several other parameters. It is unlikely that any manufacturing process can run at 100% OEE. Many manufacturers benchmark their industry to set a challenging target; 85% is not uncommon.

  • OEE is calculated with the formula (Availability)*(Performance)*(Quality)
  • Using the examples given below:
  • (Availability= 86.6%)*(Performance=93%)*(Quality=91.3%)= (OEE=73.6%)

Alternatively, and often easier, OEE is calculated by dividing the minimum time needed to produce the parts under optimal conditions by the actual time needed to produce the parts. For example:

  • Total Time: 8 hour shift or 28.800 seconds, producing 14.400 parts, or one part every 2 seconds.
  • Fastest possible cycle time is 1,5 seconds, hence only 21.600 seconds would have been needed to produce the 14.400 parts. The remaining 7.200 seconds or 2 hours were lost.
  • The OEE is now the 21.600 seconds divided by 28.800 seconds, equal to 1,5 seconds per part divided by 2 seconds, or 75%.

Total effective equipment performance

Where OEE measures effectiveness based on scheduled hours, TEEP measures effectiveness against calendar hours, i.e.: 24 hours per day, 365 days per year.

TEEP, therefore, reports the 'bottom line' utilization of assets.

Loading

The Loading portion of the TEEP Metric represents the percentage of time that an operation is scheduled to operate compared to the total Calendar Time that is available. The Loading Metric is a pure measurement of Schedule Effectiveness and is designed to exclude the effects how well that operation may perform.

Calculation: Loading = Scheduled Time / Calendar Time

Example:

A given Work Center is scheduled to run 5 Days per Week, 24 Hours per Day.

For a given week, the Total Calendar Time is 7 Days at 24 Hours.

Loading = (5 days x 24 hours) / (7 days x 24 hours) = 71.4%

Availability

The Availability portion of the OEE Metric represents the percentage of scheduled time that the operation is available to operate. The Availability Metric is a pure measurement of Uptime that is designed to exclude the effects of Quality, Performance, and Scheduled Downtime Events. The losses due to wasted availability are called availability losses.


Example: A given Work Center is scheduled to run for an 8-hour (480 minute) shift with a 30-minute scheduled break.

Operating Time = 450 Min Sched – 60 Min Unsched Downtime = 390 Minutes

Calculation: Availability = uptime/ available time

Availability 390 minutes / 450 minutes = 86.6%

Performance

The Performance portion of the OEE Metric represents the speed at which the Work Center runs as a percentage of its designed speed. The Performance Metric is a pure measurement of speed that is designed to exclude the effects of Quality and Availability. The losses due to wasted performance are also often called speed losses. In practice it is often difficult to determine speed losses, and a common approach is to merely assign the remaining unknown losses as speed looses.

Calculation: Performance = (Parts Produced * Ideal Cycle Time) / Operating time [2]

Example:

A given Work Center is scheduled to run for an 8-hour (480 minute) shift with a 30-minute scheduled break.

Operating Time = 450 Min Sched – 60 Min Unsched Downtime = 390 Minutes

The Standard Rate for the part being produced is 40 Units/Hour or 1.5 Minutes/Unit

The Work Center produces 242 Total Units during the shift. Note: The basis is Total Units, not Good Units. The Performance metric does not penalize for Quality.

Time to Produce Parts = 242 Units * 1.5 Minutes/Unit = 363 Minutes

Performance = 363 Minutes / 390 Minutes = 93.0%

Quality

The Quality portion of the OEE Metric represents the Good Units produced as a percentage of the Total Units Started. The Quality Metric is a pure measurement of Process Yield that is designed to exclude the effects of Availability and Performance. The losses due to defects and rework are called quality losses.

Calculation: Quality = (Units produced - defective units) / (Units produced)

Example:

242 Units are produced. 21 are defective.

(242 units produced - 21 defective units) = 221 units

221 good units / 242 total units produced = 91.32%

OEE as a heuristic

OEE is useful as a heuristic, but can break down in several circumstances. For example, it may be far more costly to run a facility at certain times. Performance and quality may not be independent of each other or of availability and loading. Experience may develop over time. Since the performance of shop floor managers is at least sometimes compared to the OEE, these numbers are often not reliable, and there are numerous ways to fudge these numbers [3].

OEE has properties of a geometric mean. As such it punishes variability among its subcomponents. For example 20% * 80% = 16%, whereas 50% * 50% = 25%. When there are asymmetric costs associated with one or more of the components, then the model may become less appropriate.

Consider a system where the cost of error is exceptionally high. In such a condition, higher quality may be far more important in a proper evaluation of effectiveness than performance or availability. OEE also to some extent assumes a closed system and a potentially static one. If one can bring in additional resources (or lease out unused resources to other projects or business units) then it may be more appropriate for example to use an expected net present value analysis.

Variability in flow also can introduce important costs and risks that may merit further modeling. Sensitivity analysis and measures of change may be helpful.

Automated OEE Systems

Although OEE can be manually calculated based on collected production data, the standardization of plant floor networks and OPC technology has led many industrial vendors to introduce automated OEE systems, ranging in complexity from a single sensor to complex integrated MES, ERP or CMMS systems. Notable industrial OEE vendors include:

Product Name Vendor
FactoryTalk VantagePoint EMI Rockwell Automation
Proficy Plant Applications GE Intelligent Platforms[4]
Ignition MES Module Inductive Automation[5]
Wonderware MES Performance Invensys Wonderware

Recently there have developments in integrating autocoding systems [6] with OEE software, whereby OEE values can be displayed on operator screens.

Further reading

  • Dwyer, John (2008). "OEE – The Great Energy Saving" (PDF). The Manufacturer: 52–55. {{cite journal}}: Unknown parameter |month= ignored (help)
  • France, Alan (2010), IDHAMMAR WHITEPAPER – Implementing OEE Systems: Delivering on the Promise of OEE, Idhammar Systems Ltd
  • France, Alan (2010), IDHAMMAR WHITEPAPER – The Business Case for OEE Systems: The operational and financial return on investment, Idhammar Systems Ltd
  • Hansen, Robert C (2005). Overall Equipment Effectiveness (OEE). Industrial Press. ISBN (978-0-8311-)3237-8. {{cite book}}: Check |isbn= value: invalid character (help)
  • Koch, Arno (2007). OEE for the Production Team. Makigami. ISBN 978-90-78210-08-5 (English), 978-90-78210-07-8 (Dutch), 9-783940-775-04-7 (German). {{cite book}}: Check |isbn= value: invalid character (help)
  • Productivity Press Development Team (1999), OEE for Operators: Overall Equipment Effectiveness, Productivity Press, ISBN 978-1-56327-221-9

See also

References

  1. ^ "OEE Overview - with Calculation Methods" (PDF). Retrieved 23 September 2013.
  2. ^ "OEE Primer: Calculating OEE". Retrieved 9 July 2013.
  3. ^ "Top Three Methods on how to Fudge Your OEE". Retrieved 05 Jan 2014. {{cite web}}: Check date values in: |accessdate= (help)
  4. ^ "Manufacturing Software MES - Proficy". GE Intelligent Platforms. Retrieved 14 March 2013.
  5. ^ "Ignition OEE & Downtime Tracking". Inductive Automation. Retrieved 19 October 2011.
  6. ^ Alan France on the benefits of integrating Autocoding and OEE Engineering Maintenance 25th July 2013