Jump to content

Arafura-class offshore patrol vessel

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by SNITZ01 (talk | contribs) at 02:26, 13 December 2023 (Construction). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

KDB Darulaman at the Royal Australian Navy International Fleet Review 2013. The Arafura-class is based on the Lürssen-designed Darussalam-class, operated by the Royal Brunei Navy.
Class overview
NameArafura class
Builders
Operators Royal Australian Navy
Preceded byArmidale-class patrol boat
Cost
  • A$3.6 billion (2018) for 12 vessels
  • A$300 million (2018) per unit
BuiltNovember 2018 – present
Planned14 (12 OPV, 2 MCMV)
Building6
General characteristics
TypeOffshore patrol vessel
Displacement1,640 tonnes[1]
Length80 metres [1]
Beam13 metres [1]
Draught4 metres [1]
Propulsion2 x 4,440kW diesel engines[1]
Speed22 knots (41 km/h; 25 mph) (maximum)[1]
Range4,000 nmi (7,400 km)[1]
Endurance21 days[1]
Complement40[1]
Sensors and
processing systems
SAAB Situational Awareness System (SAS) with Saab EOS500 electro-optical fire control director,[2][3] Terma SCANTER 6002 radar,[4][5] Safran Vigy Engage electro-optical surveillance and fire control multisensor system[6][7]
Armament
  • 1 x 40mm Oto Marlin 40 autocannon [8] (cancelled)
  • 1 × Rafael Typhoon stabilised gun mount fitted with a 25 mm M242 Bushmaster autocannon (interim)
  • 2 x .50 calibre machine guns[1]
  • 2 x 8.5 metre sea boats[1]
  • 1 x 10 metre sea boat[1]
Aircraft carriedUnmanned aerial vehicle;[1] light UAV capability to be integrated under Project Sea 129[9]
Aviation facilitiesUtility deck[1]

The Arafura class is a class of offshore patrol vessels being built for the Royal Australian Navy (RAN). Initially proposed in the 2009 Defence White Paper and marked as procurement project SEA 1180, it was originally planned that 20 Offshore Combatant Vessels (OCV) would replace 26 vessels across four separate ship classes: the Armidale-class patrol boats, the Huon-class minehunters, the Leeuwin-class survey vessels, and the Paluma-class survey motor launches. Although having a common design (which could be up to 2,000 tonnes in displacement), the ships would use a modular mission payload system to fulfill specific roles; primarily border patrol, mine warfare, and hydrographic survey. The 2013 Defence White Paper committed to the OCV project as a long-term goal, but opted in the short term for an accelerated procurement of an existing design to replace the Armidales, and life-extension refits for the other types. This resulted in the Offshore Patrol Vessel (OPV) project and the number of vessels reduced to 12. However, this was further increased to 14 when 2 further Mine Counter Measures variants were proposed under SEA 1905.

Then-Prime Minister Malcolm Turnbull announced on 18 April 2016 that ship designers Damen, Fassmer and Lürssen had been shortlisted for the project.[10] On 24 November 2017, the government announced that Lürssen had been selected.[11]

Offshore combatant proposal

Planning and design

First made public in Defending Australia in the Asia Pacific Century: Force 2030, the 2009 Department of Defence white paper, the planned vessels stem from Government instructions for the RAN to rationalise patrol, mine warfare, and hydrographic survey assets into a single class of warship.[12] It was originally planned 20 OCVs would replace 26 vessels across four separate ship classes: the Armidale-class patrol boats, the Huon-class minehunters, the Leeuwin-class survey vessels, and the Paluma-class survey motor launches

Instead of being capable of performing all roles simultaneously, the ships will have a modular mission payload system like the Standard Flex system used by the Danish Navy, or the system used by the United States Navy's littoral combat ships: mission-specific equipment will be fitted to containerised modules, which can be exchanged for different modules when the ship needs to change roles.[12][13][14] The use of containerised modules means that equipment can be upgraded without taking the ships out of service for refit, and if necessary can be fitted to requisitioned civilian vessels.[15] The cost in developing and implementing the modular system is predicted to be offset by the savings in the areas of maintenance (having to purchase and maintain stocks to repair four different designs), personnel (having to retrain sailors when they transfer to a new ship), and administration.[12][15]

The Paluma-class survey motor launch HMAS Benalla (left) and the Huon-class minehunter HMAS Gascoyne: two of the four ship classes were to be replaced by the Offshore Combatant Vessel

It was anticipated that the new ships could have displaced anywhere up to 2,000 tonnes, although defence magazine editor Kym Bergmann predicts that this 'worst case' would require 50,000 tons of steel or aluminium to be fabricated (compared to 36,000 tons for the Attack-class submarine program), and unless multiple shipbuilders are involved, the 12- to 18-month construction time per vessel will see the last ship enter service during the late 2020s.[12][16]

Instead of building all 20 vessels to the same design, the idea of hull variants optimised for different roles is also being explored:[15] the module system will allow a ship designed for one role to be rapidly reconfigured to serve in another role, with a small but acceptable loss in capability compared to a 'native' OPV. The OPVs could be designed to carry a helicopter or an unmanned aerial vehicle to improve each ship's surveillance range, but this avenue is dependent on further study and cost-benefit analysis.[12][17]

The OPV was originally planned to replace 26 vessels across four warship classes: the Armidale-class patrol boats, the Huon-class minehunters, the Leeuwin-class survey vessels, and the Paluma-class survey motor launches.[12][18] The new ships were to be used for offshore and littoral patrol, border protection, anti-terrorism and anti-piracy operations, mine warfare, and hydrographic survey.[12] It was plausible that the OPVs will operate in support of the Canberra-class landing helicopter dock ships; amphibious operations would benefit from the survey and mine warfare capabilities of the ships.[17]

Another major change, reportedly being examined by the DSR (Australia's Defence Strategic Review), is the possibility of either up-arming or divesting the service's new Arafura-class OPVs, before NUSHIP Arafura has even conducted sea trials. The concern is that the OPVs are not able to contribute to any high-end scenarios, as they lack so much as a large calibre gun. One possibility, being examined, is outfitting the vessels with between four and six Kongsberg Naval Strike Missiles, which the RAN is already procuring. Another approach, which has gained some traction, is the possibility of divesting the fleet to other government agencies (such as the Australian Border Force) and international partners (such as Papua New Guinea), and instead procuring a fleet of missile-armed corvettes.

International co-operation

The Royal Navy has begun plans for a similar vessel under the Future Surface Combatant program, designated the Future Mine Countermeasures/Hydrographic/Patrol Vessel (FMHPV).[19] At the start of 2010, it was announced that the governments of Australia and the United Kingdom were exploring the potential for idea-sharing and co-operation on the design of the OPV and FMHPV, as well as planned replacements for the Anzac-class, Type 22, and Type 23 frigates.[19] Although the nations will share their analyses, a common design or shared construction program is unlikely, as the two nations have different needs and replacement schedules.[15][19] The RAN is also observing the development of the United States Navy Littoral Combat Ships, to take advantage of lessons learned during the program.[15]

Austal suggested a scaled-down variant of the Independence-class littoral combat ship (USS Coronado pictured) for the Australian OCV project

Proposed designs

While designing the Independence-class trimarans for the Littoral Combat Ship program, Australian-owned shipbuilder Austal also prepared a scaled-down version that could serve as the basis for the Australian OPV.[16] The Austal Multi Role Vessel (MRV 80) would have an overall length of 80 metres, a top speed of 26 knots, carry an NH-90 or similar helicopter, and have 500 square metres for mission equipment or cargo.[20]

In 2012, American shipbuilder Huntington Ingalls Industries proposed a variant of the Legend-class National Security Cutter, a ship built for the United States Coast Guard.[21]

Offshore Patrol Vessel program

Although the 2013 White Paper committed to the OCV as a long-term plan, it announced that an interim patrol boat class based on an existing design would be acquired as a short-term replacement for the Armidales, while the Palumas and Huons would undergo life-extension upgrades.[22] The 20 vessels originally planned to be built was reduced was later reduced to 12 following the change in their planned role.[12] The project received the procurement designation SEA 1180.[19]

Prime Minister Malcolm Turnbull announced on 18 April 2016 that ship designers Damen, Fassmer and Lürssen had been shortlisted for the project.[10] On 24 November 2017, the government announced that Lürssen had been selected.[11]

In October 2017, the Australian government announced that the vessels would use an Australian-designed SAAB tactical combat management system.[23]

Under SEA 1905 a further two ships are to be built by Civmec for the mine countermeasures role. A third vessel may be procured under SEA 2400 to fulfill the survey role although this is unlikely.[24] This was expanded in the 2020 Defence Strategic Update and 2020 Force Structure Plan released on 30 June 2020 for up to 8 vessels optimised for mine countermeasures and hydrographic survey roles potentially based on the Arafura design, possibly bringing the total number of vessels back up to the original 20.[25][26]

Design

The Arafura-class is based on the Lürssen-designed Darussalam-class, operated by the Royal Brunei Navy.[1] Each vessel has a gross displacement of 1,640 tonnes, and measures 80 metres long, with a beam of 13 metres and a draft of 4 metres.[1] Propulsion power is from two MTU 16V diesel engines rated at 4440kW each, which drive variable pitch propellers and give a top speed of 22 knots, and shipboard electrical power is generated by MAN diesel engines.[1] The ship's range is about 4,000 nautical miles (7,400 km), with an endurance of 21 days.[1] The standard crew complement is 40 sailors, though up to 20 more can be berthed if required.[1] The ships will be deployed with empty space available to install container-mounted systems such as aircraft support and sensors; if fully utilized, the gross displacement could increase to 1,800 tonnes.[1]

Shipboard armament was originally intended to be a single 40 mm gun and two 12.7 mm guns.[1] The 40 mm gun was cancelled in 2021 due to a combination of technical problems and a re-assessment of the threats the ships would face. The ships will instead be armed with a Typhoon Weapon Station on an interim basis until a replacement weapon is identified and then acquired.[27] In May 2023 it was reported that the RAN was considering purchasing a containerised variant of the C-Dome surface-to-air missile system to improve the Arafura-class's armament.[28]

Each vessel carries two 8.5 metre rigid inflatable boats and a single 10 metre boat, which are intended as the primary means of deploying offensive force in the ships' border patrol role.[1] A single unmanned aerial vehicle is carried and deployed from an open utility deck.[1] Two separate electro-optic targeting systems and three radars are installed and managed by the Saab 9LV system.[1] In order to allow the ships to operate in conjunction with allied international forces, each ship is equipped with a unique electronic identifier transponder that allows for communication via the Link 16 network.[1]

Construction

The class of ships will be based on Lürssen's OPV80, similar to the Darussalam-class offshore patrol vessel of the Royal Brunei Navy.[29][30] The first two vessels will be built by ASC Shipbuilding in Adelaide, South Australia before production is transferred to the shipyard of Forgacs Marine & Defence, a subsidiary of Civmec, in Henderson, Western Australia.[11][31]

Construction of the first ship began on 15 November 2018. On that day, it was also announced that the vessel would be named HMAS Arafura, and the class the Arafura-class patrol vessels.[32]

On 9 April 2020 the second ship in the class, HMAS Eyre, was laid down at ASC's shipyard. The names of the following four ships were also announced at this time: HMA Ships Pilbara, Gippsland, Illawarra and Carpentaria.[33]

The first three ships amongst the then new names, HMAS Pilbara, HMAS Gippsland and HMAS Illawarra were laid down at the shipyard of Civmec in Henderson on 11 September 2020,[34] 30 July 2021[35] and 27 September 2022,[36] respectively.

In October 2022 it was reported that Arafura did not meet civilian safety standards and the Albanese government was concerned that the ships were too lightly armed to meet the Navy's needs. The government was considering reducing the number of ships to be built, with those completed possibly being transferred to the Australian Border Force.[37] The delays to completing the Arafura-class ships led the project to be added to the Defence 'projects of concern' list in April 2023.[38] As of November 2023, Arafura had been launched but not commenced sea trials, and her commissioning date had been delayed until 2024 potentially due to the ship not meeting safety standards.[39][40]

Criticism

With the cancellation of the main gun and the lack of any other major weaponry, the class has been criticised for being unable to operate in medium to high-end warfighting and resulting in calls to either up-arm the class or transfer the ships to the Australian Border Force Marine Unit in favour of a fleet of corvettes.[41][42][43] The class has also faced criticism for schedule delays and being over budget.[43][42]

Ships

Dates in Italics indicate estimates

Name Pennant number Builder Laid down Launched Commissioned Status Named for
Offshore Patrol Vessels (12)
Arafura OPV 203 ASC Shipbuilding,
Osborne
10 May 2019 16 December 2021 2024[39] Fitting out Arafura Sea
Eyre OPV 204 9 April 2020 22 November 2023[44] Fitting Out Eyre Peninsula, South Australia
Pilbara OPV 205 Forgacs Marine & Defence,
Henderson
11 September 2020 Under construction Pilbara, Western Australia
Gippsland OPV 206 30 July 2021 Under construction Gippsland, Victoria
Illawarra OPV 207 27 September 2022 Under construction Illawarra, New South Wales
Carpentaria OPV 208 Under construction; steel cut August 2022[45] Gulf of Carpentaria
TBA Ordered
TBA Ordered
TBA Ordered
TBA Ordered
TBA Ordered
TBA Ordered
Mine Countermeasures Vessels (2)
TBA Planned
TBA Planned
Source:[33][46][47]

Citations

  1. ^ a b c d e f g h i j k l m n o p q r s t u v w x y "Arafura ahead of schedule". Australian Defence Magazine. 11 April 2019. Retrieved 11 July 2020.
  2. ^ "SAAB Receives Order for Australian OPV Situational Awareness System". Saab Press Release. 20 April 2018.
  3. ^ "Saab sensor system for OPVs". Australian Defence Magazine. 23 April 2018.
  4. ^ "SCANTER 6002 radar selected for SEA 1180 OPVs". Defence Connect. 7 August 2018.
  5. ^ "Australian SEA1180 OPVs to feature Terma's air and surface surveillance radars". Naval Today. 31 July 2018.
  6. ^ Scott, Richard. "Vigy Engage selected for Project SEA 1180 OPVs". Jane's Navy International.
  7. ^ "Safran Vigy Engage Selected for Australia's SEA 1180 OPVS". Monash Publishing Group. 5 September 2018.
  8. ^ "Navy Outlook 2020". Faircount Media Group. Retrieved 6 March 2021.
  9. ^ "Shortlist announced for Sea 129 Phase 5 - Australian Defence Magazine".
  10. ^ a b Anderson, Stephanie (18 April 2016). "Malcolm Turnbull says 12 offshore patrol vessels to be built in Adelaide". ABC News. Retrieved 18 April 2016.
  11. ^ a b c "Hundreds of Australian Jobs Created in Offshore Patrol Vessel Project". Christopher Pyne. Federal Member for Sturt, Minister for Defence Industry. 24 November 2017. Retrieved 24 November 2017.
  12. ^ a b c d e f g h Department of Defence, Defending Australia in the Asia Pacific Century, pp. 72–3
  13. ^ Thornton, The Rationale for the RAN Offshore Combatant Vessel, pp. 6, 8
  14. ^ Boettger, The Offshore Combatant Vessel, p. 31
  15. ^ a b c d e Australian Offshore Combatant Vessels, p. 1
  16. ^ a b Bergmann, Buzz around all-in-one combatant vessels
  17. ^ a b Australian Offshore Combatant Vessels, p. 2
  18. ^ Thornton, The Rationale for the RAN Offshore Combatant Vessel, p. 6
  19. ^ a b c d Scott, UK, Australia begin talks on future ship projects
  20. ^ "Multi Role Vessel MRV80" (PDF). Austal. 2010. Archived from the original (PDF) on 5 March 2012. Retrieved 18 January 2013.
  21. ^ HII Targets RAN SEA1180 Project, in The Navy
  22. ^ Department of Defence (3 May 2013). Defence White Paper 2013. Commonwealth of Australia. p. 84. ISBN 978-0-9874958-0-8.
  23. ^ "Joint Media Release – Prime Minister, Minister for Defence and Minister for Defence Industry – New Approach to Naval Combat Systems". Department of Defence. 3 October 2017. Retrieved 3 October 2017.
  24. ^ "Draft: Strategic infrastructure and land use plan" (PDF). Western Australian Government. 18 June 2020. Archived (PDF) from the original on 2 July 2020.
  25. ^ "Factsheet: Naval Shipbuilding" (PDF). Department of Defence. Retrieved 6 March 2021.
  26. ^ McLaughlin, Andrew (30 June 2020). "Govt outlines expansion of Australian Defence Firepower". ADBR. Retrieved 6 March 2021.
  27. ^ Tillett, Andrew (14 December 2021). "Defence quietly cancels another navy contract – after denying problems". Australian Financial Review. Retrieved 17 December 2021.
  28. ^ Felton, Ben (5 May 2023). "Australia Considering Modular C-Dome For Arafura OPVs". Naval News. Retrieved 6 August 2023.
  29. ^ "ASC Shipbuilding welcomes OPV bid partners Lürssen and Forgacs to Techport for the first time". www.asc.com.au. Retrieved 3 April 2018.
  30. ^ '"Aussie Navy Renewal", Ships Monthly, March 2018, page 14
  31. ^ Bell, Frances (24 November 2017). "Navy Offshore Patrol Vessels to be built in WA and SA by German company Luerssen". ABC News. Retrieved 24 November 2017.
  32. ^ Zerbe, Ryan (15 November 2018). "Construction begins on Arafura Class patrol vessels". Navy Daily. Royal Australian Navy. Retrieved 15 November 2018.
  33. ^ a b "Major milestone for Navy's multibillion-dollar OPV program". Defence Connect. 9 April 2020. Retrieved 9 April 2020.
  34. ^ "Keel Laid for Australia's third Arafura-class OPV". Naval News. 11 September 2020. Retrieved 11 September 2020.
  35. ^ "2020–21 Major Projects Report" (PDF). Australian National Audit Office. 13 December 2021. p. 173. Retrieved 23 March 2022.
  36. ^ "Keel laid for fifth Arafura OPV". Defence Connect. 27 September 2022. Retrieved 27 September 2022.
  37. ^ Greene, Andrew (9 October 2022). "'97 years late': Expensive problems on major defence projects concern federal government". ABC News. Retrieved 15 April 2023.
  38. ^ "Defence updates 'projects of concern' list". www.defenceconnect.com.au. 27 October 2022. Retrieved 15 April 2023.
  39. ^ a b "Australia Lists Arafura-class OPV as 'Project of Concern'". Naval News. 21 October 2023. Retrieved 29 October 2023.
  40. ^ Felton, Ben (23 November 2023). "Luerssen Australia Launches Second Arafura Class OPV". Naval News. Retrieved 13 December 2023.
  41. ^ Felton, Benjamin (20 December 2022). "What does Australia's Strategic Review hold for the RAN?". Naval News. Retrieved 9 January 2023.
  42. ^ a b Bergmann, Kym. "Arafura class OPVs late, over budget and underequipped". The Australian. News Corp. Retrieved 9 January 2023.
  43. ^ a b Greene, Andrew (9 October 2022). "'97 years late': Expensive problems on major defence projects concern federal government". ABC News. ABC. Retrieved 9 January 2023.
  44. ^ Defence Media (22 November 2023). "Second Arafura class offshore patrol vessel launches in South Australia".
  45. ^ "Luerssen starts construction of the sixth Arafura class OPV Carpentaria".
  46. ^ "Arafura Class OPV". Royal Australian Navy. Retrieved 13 November 2021.
  47. ^ "RAN's second Arafura class patrol vessel to be delayed by six months". Baird Maritime. 28 July 2021. Retrieved 13 November 2021.

References