Jump to content

Bureya Dam

Coordinates: 50°16′09″N 130°18′48″E / 50.26917°N 130.31333°E / 50.26917; 130.31333
From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Monkbot (talk | contribs) at 06:52, 15 September 2019 (History: Task 16: replaced (1×) / removed (0×) deprecated |dead-url= and |deadurl= with |url-status=;). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Bureya Dam
Bureya Dam is located in Amur Oblast
Bureya Dam
Location of Bureya Dam in Amur Oblast
Bureya Dam is located in Russia
Bureya Dam
Bureya Dam (Russia)
Official nameБурейская ГЭС
CountryRussia
LocationFar East
Coordinates50°16′09″N 130°18′48″E / 50.26917°N 130.31333°E / 50.26917; 130.31333
StatusOperational
Construction began1976
Opening date2009
Owner(s)RusHydro
Dam and spillways
Type of damGravity dam
ImpoundsBureya River
Height140 m (459 ft)
Length736 m (2,415 ft)
Reservoir
Total capacity20.94 km3 (5.02 cu mi)[1]
Surface area750 km2 (290 sq mi)[1]
Power Station
Turbines6 × 335 MW
Installed capacity2,010 MW

The Bureya Dam (locally referred to as Bureyskaya, Russian: Бурейская ГЭС) is a hydroelectric dam on the Bureya River in the Russian Far East.

History

Bureya hydroelectric power station was built by Bureyagesstroy.[1] Construction started in 1976, but was halted until 1999. In 1999, RAO UES restarted the project. The dam was completed and the first unit was launched in 2003.[2] The construction of the whole complex was completed in 2009.[1]

Bureya Reservoir

The reservoir reached its specified level during the summer-autumn monsoon season of 2009. It was accompanied with first use of spillways during planned tests. Despite the fact that all primary construction works on power station was completed, it was officially commenced for exploitation by government commission in 2011. Therefore, officially, the complex is still under construction.

Spillways of Bureya HPP in work

Description

Bureya Dam is a gravity dam with height of 140 metres (460 ft) and crest length of 736 metres (2,415 ft).[3][4]

The power station has an installed capacity of 2010 MW, the full capacity. Power is generated by utilizing six turbines, each with a capacity of 335 MW. The facility is owned by RusHydro.

See also

References

  1. ^ a b c d "Bureisk HPP". Bureyagesstroy. Retrieved 2011-01-22.
  2. ^ "Dam Development in Russia". Amur-Heilong River Basin Information Center. Archived from the original on 2010-08-16. Retrieved 2011-01-22.
  3. ^ http://www.burges.rushydro.ru/hpp/general/
  4. ^ "Bureya Dam". International Database and Gallery of Structures. Retrieved 2011-01-22.