Aguçadoura test site
Aguçadoura Test Site | |
---|---|
Country | Portugal |
Location | Póvoa de Varzim |
Coordinates | 41°25′57″N 08°50′33″W / 41.43250°N 8.84250°W |
Wave power station | |
Water body | Atlantic Ocean |
Distance from shore | 5 km (3 mi) |
Power generation | |
Units operational | 1 × 300 kW |
Make and model | CorPower C4 |
Units decommissioned | 1 × 2 MW Archimedes Wave Swing; 3 × 750 kW Pelamis P1 |
The Aguçadoura test site is an offshore location in the north of Portugal where grid connected offshore renewable energy devices have been tested, for research and project demonstration.[1] It is about 5 km (3 miles) off the coast of Aguçadoura,[2] Póvoa de Varzim, about 35 km NNE of central Porto.
It was established in 2001, and as of 2024[update] four developers have tested devices there: the Archimedes Wave Swing, three Pelamis Wave Power P1 machines as the Aguçadoura Wave Farm, the Principle Power WindFloat, and CorPower Ocean's C4.[3]
Since 2021, it has been managed by WavEC and OceanACT.[4]
Archimedes Wave Swing
[edit]In May 2004, a 2 MW (peak power output) Archimedes Wave Swing (AWS) was installed at Aguçadoura, after unsuccessful attempts in 2001 and 2002.[5] The installation took three and a half days, and was eventually achieved by attaching the convertor to a pontoon and then submerging it and attaching to the seabed while the chamber remained floating.[6]
The AWS device on the submersible pontoon foundation was 48 m long, 28 m wide and 35 m high, and sat on the sea bed beneath the waves. It had a 9.5 m diameter moving captor with a stroke of 7 m that moved with the waves at a maximum speed of 2.2 m/s. It was connected to the Portuguese grid by a 6 km long cable.[5]
The testing was postponed until mid-September 2004, due to technical issues communicating with the device. At the end of October 2004 the testing license expired and the tests finished. The AWS intellectual property was later transferred to a Scottish company AWS Ocean Energy Ltd.[5]
Aguçadoura Wave Farm
[edit]Three Pelamis P1 wave energy converters were installed at Aguçadoura in September 2018, and connected to the Portuguese grid.[7] These each had a rated peak power of nominally 750 kW, giving a total of 2.25 MW installed capacity. There were plans to install a further 25 Pelamis WECs,[7] but this never happened.
The three machines were taken back to shore due to technical issues, but were never re-deployed due to the financial crisis. One of the project partners, Babcock & Brown pulled out after a major sale of assets to repay its debts.[2] Another of the partners, Energias de Portugal (EDP), were not discouraged by the failure and signed an agreement with US-based Principle Power to develop floating offshore wind turbines.[2]
Principle Power WindFloat
[edit]An initial agreement between Principle Power and EDP was made in 2009 to develop floating offshore wind turbines at the Aguçadoura site.[2] A consortium called WindPlus was set up to develop the project; it included Principle Power, EDP, and Vestas.[8]
In November 2011, the WindFloat 1 semi-submersible platform with a 2 MW Vestas wind turbine was installed around 5 km off the coast of Aguçaduora, following a 350 km tow from Setúbal.[9] The turbine was 54 m high, and with the foundation weighed 1200 t, and can be installed in water depths of over 50 m.[10] The structure was not permanently installed, but held in place by drag-embedment anchors similar to those used to moor floating oil platforms.[8]
After five years, the testing programme was completed, the device having survived 17 m high waves, wind speeds of up to 111 km/h , and generated 17 GWh of renewable electricity for the Portuguese grid. The design of the platform was approved by certification body Bureau Veritas in April 2016.[11]
The WindPlus consortium has since developed the 25 MW WindFloat Atlantic project, about 20 km off the coast of Viana do Castelo, some 30 km North of Aguçadoura. This has three WindFloat foundations each with a Vestas V164-8.4MW turbine, which began supplying power in January 2020.[12]
CorPower Ocean HiWave-5
[edit]In late 2020, CorPower Ocean secured a 10-year licence from the Portuguese Directorate-General for Natural Resources that would allow them to test an array of CorPower wave energy converters (WECs) at the Aguçadoura site within the HiWave-5 project.[13] A new subsea electricity cable was installed in Autumn 2022.[14] The first CorPower C4 WEC was installed in September 2023,[15] and started exporting to the Portuguese electricity grid in October 2023.[16] It is planned to install a further three C5 WECs as a demonstration of a CorPack wave cluster.[17]
References
[edit]- ^ "OES | Country info | Portugal". Ocean Energy Systems. Retrieved 3 March 2024.
- ^ a b c d Blum, Patrick (16 March 2009). "A Setback for Wave Power Technology". The New York Times.
- ^ Vieira, Mário; Macedo, Ana; Alvarenga, António; Lafoz, Marcos; Villalba, Isabel; Blanco, Marcos; Rojas, Rodrigo; Romero-Filgueira, Alejandro; García-Mendoza, Adriana; Santos-Herran, Miguel; Alves, Marco (1 January 2024). "What future for marine renewable energy in Portugal and Spain up to 2030? Forecasting plausible scenarios using general morphological analysis and clustering techniques". Energy Policy. 184: 113859. doi:10.1016/j.enpol.2023.113859. hdl:10362/159623. ISSN 0301-4215.
- ^ "Agucadoura Test Site". International WaTERS. Retrieved 3 March 2024.
- ^ a b c Prado, M.; Polinder, H. (1 January 2013), Mueller, Markus; Polinder, Henk (eds.), "9 - Case study of the Archimedes Wave Swing (AWS) direct drive wave energy pilot plant", Electrical Drives for Direct Drive Renewable Energy Systems, Woodhead Publishing Series in Energy, Woodhead Publishing, pp. 195–218, ISBN 978-1-84569-783-9, retrieved 3 March 2024
- ^ "Industry news". Power Engineer. 18 (3). IET: 4. 20 September 2004 – via IET Xplore.
- ^ a b Jha, Alok (25 September 2008). "Making waves: UK firm harnesses power of the sea ... in Portugal". London: The Guardian. Archived from the original on 26 September 2008. Retrieved 9 October 2008.
- ^ a b Macguire, Eoghan (28 June 2012). "Floating turbine buoys offshore wind potential". CNN World. Retrieved 7 April 2024.
- ^ Visser, Anne (30 November 2011). "EDP, Principle Power Deploy Full-scale 2MW WindFloat (Portugal)". Offshore Wind. Retrieved 6 April 2024.
- ^ Kennedy, Charles (21 June 2012). "Portugal Installs its First Floating Wind Turbine". CNBC. Retrieved 6 April 2024.
- ^ Weston, David (June 2016). "Principle Power completes 2MW WindFloat demo". Wind Power Monthly. Retrieved 6 April 2024.
- ^ "WindFloat Atlantic Project". Power Technology. Retrieved 7 April 2024.
- ^ Garanovic, Amir (16 November 2020). "CorPower secures 10-year marine license in Portugal". Offshore Energy. Retrieved 7 April 2024.
- ^ International, Power Engineering (7 October 2022). "CorPower Ocean and Maersk install subsea cable for HiWave-5". Power Engineering International. Retrieved 7 April 2024.
- ^ "CorPower C4 wave energy converter installed in Portugal". The Engineer. 5 September 2023. Retrieved 7 April 2024.
- ^ Garanovic, Amir (13 October 2023). "CorPower Ocean's wave energy device starts exporting power to Portugal's grid". Offshore Energy. Retrieved 7 April 2024.
- ^ "TotalEnergies joins CorPower Ocean's wave energy pilot project". Offshore magazine. 5 December 2023. Retrieved 7 April 2024.