Jump to content

Derwent Reservoir (Derbyshire)

Coordinates: 53°24′45″N 1°44′35″W / 53.41250°N 1.74306°W / 53.41250; -1.74306
From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Jokulhlaup (talk | contribs) at 16:01, 23 April 2016 (External links: refine basin). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Derwent Reservoir
Derwent Reservoir - 11 July 2007
LocationDerbyshire
Coordinates53°24′45″N 1°44′35″W / 53.41250°N 1.74306°W / 53.41250; -1.74306
Lake typeReservoir
Primary inflowsRiver Derwent
Primary outflowsRiver Derwent
Basin countriesUnited Kingdom
Surface area70.8 ha (175 acres)
Max. depth34.7 m
Islands1

Derwent Reservoir is the middle of three reservoirs in the Upper Derwent Valley in the northeast of Derbyshire, England. It lies approximately 10 miles (16 km) from Glossop and 10 miles (16 km) from Sheffield. The River Derwent flows first through Howden Reservoir, then Derwent Reservoir and finally through Ladybower Reservoir. Between them they provide practically all of Derbyshire's water, as well as to a large part of South Yorkshire and as far afield as Nottingham and Leicester.

Derwent Reservoir is around 1.5 miles (2 km) in length, running broadly north–south, with Howden Dam at the northern end and Derwent Dam at the south. A small island lies near the Howden Dam. The Abbey Brook flows into the reservoir from the east.

At its peak the reservoir covers an area of 70.8 hectares (175 acres) and at its deepest point is 34.7 metres (114 ft) deep.

History

Derwent Dam in full flow - 11 July 2007

The Industrial Revolution and urbanisation of the 19th century created huge demand for water in the industrial cities of the East Midlands and South Yorkshire. The proximity of Sheffield and its neighbours to the Upper Derwent valley were thus factors in the decision to dam the valley to create the Howden and Derwent reservoirs.

The neo-Gothic solid masonry dam was begun in 1902, a year after the construction of Howden was begun, and proved a mammoth task. The huge stones that formed the walls of the dam were carried along a specially created railway from the quarries at Grindleford. Over 1,000 workers lived in a specially constructed self-contained town called Birchinlee[1] or "Tin Town". One of the metal huts was preserved and moved to the village of Hope, where it is now a hairdressing salon. The workers that died during the building of the dam were buried in Bamford Church.

The filling of the reservoir began in November 1914, and overflowed for the first time in January 1916, with the water almost immediately passing into supply. The dam can support a total of 9.64 million cubic metres of water.

Only two years after the dam's completion in 1916, it was decided that the flow from the reservoir was insufficient to support the surrounding population. As a result, between 1920 and 1931 the rivers Alport and Ashop were also diverted from the Ashop valley into the reservoir using tunnels and a Venturi Flume.

The diversion helped hold back water during the construction of the Ladybower Reservoir to the south, which was constructed between 1935 and 1945.

Bamford and Howden Railway

Dam Wall

Between 1901 and 1903 a standard gauge railway of over 7 miles (11 km) was built from the village of Bamford to the south of the reservoir to Howden, to carry the thousands of tons of stone required for the construction of the two dams. Near the southern end lay the newly opened quarry at Bole Hill near Grindleford.

Remains of the railway can still be seen alongside Derwent Reservoir as well as at the western end of the Ladybower dam where over 1.5 miles (2.4 km) of cutting and trackway remain, and are known locally as 'The Route'. Between the Howden and Derwent dams the present road was built over the top of the railway.

After supplying well over a million tons of stone the Bole Hill quarry was closed in September 1914, with the end of the railway following soon after. The section between the mainline railway at Hope and Yorkshire Bridge was relaid in 1935 to aid the construction of the Ladybower dam, but closed again in 1946.

Countryside

The base of the dam

The majority of the land around the reservoir is owned by Severn Trent Water, and of that around half is woodland. The woods consist predominantly of larch, pine, and spruce conifers, with the remaining third mainly sycamore, beech and oak.

The hills of the Peak District are given over to the pasture of sheep, leased to local farmers. The moorlands and gritstone edges are criss-crossed by footpaths open year-round other than during selected shooting periods.

Dambusters

During the Second World War the reservoir was used by pilots of the 617 Squadron for practising the low-level flights needed for Operation Chastise (commonly known as the "Dam Busters" raids), due to its similarity to the German dams. Today there is a commemorative plaque to 617 Squadron on the dam, and one of the towers on the dam houses the Derwent Valley Museum. The exhibition, owned and run by Vic Hallam, tells the tale of Squadron 617 and its training for Operation Chastise and also has a display on the history of the Derwent valley and the lost villages of Derwent and Ashopton.[2] Occasional flypasts of the Battle of Britain Memorial Flight at the reservoir are also staged to commemorate the events during the war. In September 2014, a unique and never to be repeated flypast took place with the two remaining airworthy Lancasters, one from the Battle Of Britain Memorial Flight, and one from Canada, flying three passes in formation.

References

  1. ^ Peak Secrets: Upper Derwent Valley 1400productions
  2. ^ "Derwent Dam Museum". Derwent Dam Museum. 2012. Archived from the original on 2 July 2012. Retrieved 1 May 2014.