Jump to content

Thames and Severn Canal

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Bender the Bot (talk | contribs) at 10:29, 7 November 2016 (Literary connections: clean up; http→https for Google Books using AWB). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Thames and Severn Canal
Specifications
Locks44
StatusSome restoration since 1972
History
Principal engineerJosiah Clowes
Date of act1783
Date closed1933
Thames and Severn Canal
Stroudwater Navigation
Stroudwater Junction
1
Wallbridge Lower Lock
Slad Brook (culverted)
 A46  Stroud Brewery Bridge
2
Wallbridge Upper Lock
Capel Mill diversion
 A419  (Dr Newtons Way) bridge
Golden Valley line Stroud viaduct
 A419  road built along canal bed
River Frome
3
Bowbridge Lock
4
Griffins Mill Lock
5
Ham Mill Lock
Stroud Brewery, navigable limit
6
Hope Mill Lock
Gough's Orchard feeder from R Frome
7
Gough's Orchard Lock
River Frome aqueduct
Brimscombe Port
8
Bourne Lock
Golden Valley Line bridge
9
Beales Lock
10
St Marys Lock
Railway bridge
11-12
Ile's/Ballinger's Lock (2)
13
Chalford Chapel Lock
River Frome
 A419  road bridge
14-16
Bell/Red Lion/Valley Lock (3)
17-18
Bakers Mill Locks (2)
19-21
Puck Mill Locks (3)
22-28
Daneway Locks (7)
Sapperton Tunnel
 A419  road over tunnel
Railway bridge
Thames Head pumping station
Source of the River Thames
 A433  road bridge
 A429  aqueduct
Cirencester Arm
29-32
Siddington Locks (4)
33-35
South Cerney Locks (3)
36
Boxwell Springs Lock
37-38
Wildmoorway Locks (2)
 B4696  Gateway Bridge
39
Cerney Wick Lock
North Wilts Canal
proposed diversion
40
Latton Lock
 A419  road bridge
41
Eisey Lock
42-43
Dudgrove Double Lock (2)
River Thames to Cricklade
44
Inglesham Lock
River Coln
River Thames, Lechlade

The Thames and Severn Canal is a canal in Gloucestershire in the south of England, which was completed in 1789. It was conceived as part of a canal route from Bristol to London. At its eastern end, it connects to the River Thames at Inglesham Lock near Lechlade, while at its western end, it connects to the Stroudwater Navigation at Wallbridge near Stroud, and thence to the River Severn. It has one short arm (branch), from Siddington to the town of Cirencester. It includes Sapperton Tunnel, which when built was the longest canal tunnel in Britain, and remains the fourth longest. There were always problems with water supply, as no reservoirs were built, while the summit section near the tunnel ran through porous limestone, and there were constant difficulties with leakage. Competition from the railways took much of the canal's traffic by the end of the 19th century, and most of the canal was abandoned in 1927, the remainder in 1941.

Since 1972, the Cotswold Canals Trust has been working to restore both the canal and the Stroudwater Navigation, so that it can again provide a navigable link between the Thames and the Severn. A number of the structures have been restored, and some sections are now in water. A major step forward occurred in 2003, when a bid was made to the Heritage Lottery Fund for £82 million to restore both canals. The bid and the project had to be split into smaller sections, but £11.9 million was awarded in 2006 for phase 1a, which with match funding will restore navigation from 'The Ocean' at Stonehouse to Wallbridge on the Stroudwater Navigation, and from Wallbridge to Brimscombe Port on the Thames and Severn Canal. Another step forwards occurred in 2010, when British Waterways gave Inglesham Lock to the Trust, and the Inland Waterways Association mounted a national campaign to fund its restoration and around 420 yards (380 m) of canal above it. The intention is to re-open the whole canal, but there are some major engineering obstacles to be overcome to achieve this.

History

Since the 1730s, when the first Act of Parliament to authorize a canal from the River Severn to Stroud had been passed, the Stroudwater Navigation had been seen as part of a larger plan to link London and Bristol by waterway. No work took place immediately, but the Stroudwater was eventually opened in 1779, and within two years the shareholders commissioned a survey for a canal from Dudbridge to Cricklade, which would complete the link. It is likely that John Priddy – previously the engineer for the Stroudwater scheme – carried out the survey, but others were soon involved including Sir Edward Littleton, who was part of the Staffordshire and Worcestershire Canal. Priddy suggested that there were better terminal points at Wallbridge and Lechlade. Robert Whitworth then surveyed two routes, the first as suggested by Priddy, and the second direct from the Severn to the Thames following the valley of the River Coln. The first route was chosen, based on excellent water supplies at Cirencester, although the estimates of the amount of water available proved to be wildly optimistic.[1]

The estimated cost of the project was £127,916, most of which was promised within three weeks. The bill to authorise the canal passed through Parliament relatively easily, and became an Act on 17 April 1783. The company could raise an initial £130,000, with an additional £60,000 if required. The canal was to be suitable for boats 12 feet (3.7 m) wide, and so could accommodate Thames barges, but not Severn Trows.[2] Josiah Clowes was appointed head engineer, surveyor and carpenter to the canal in 1783 to assist Whitworth. Clowes became resident engineer and was paid £300 per year. Clowes' work on the canal gave him a reputation which made him highly sought after in the last five years of his life. He left the construction of the canal shortly before completion to work on Dudley Tunnel.[3]

There was great debate about the gauge of the tunnel required at Sapperton. Commissioners from the River Thames thought that it would have to be built for narrow boats, since the cost of a larger tunnel would be prohibitive. It was also going to be longer than any tunnel yet built. However, a decision was made that it would be built as a broad tunnel, 15 feet (4.6 m) wide and high, and so the company advertised for tunnellers. The tunnel was expected to take four years to complete when work began at the start of 1784, but it was not completed until April 1789. The canal opened in stages as it was completed. The first 4 miles (6.4 km) from Wallbridge to Chalford opened in January 1785, and by mid-1786, the navigable section had reached the western portal of the tunnel, 7.5 miles (12.1 km) and 28 locks from Wallbridge. A wharf was built at Daneway Bridge, equipped with a warehouse and coalyard.[4]

Looking east from Upper Wallbridge Lock

The tunnel was constructed from many workfaces, with 25 shafts sunk along its course to provide access. After completion there were problems, and the tunnel was shut for two and a half months during 1790 for further work to be carried out. The summit level and a branch to Cirencester were completed in 1787, and became operational as soon as the tunnel opened. The final section to the junction with the Thames at Inglesham, which descends through 16 locks, was finished in November 1789.[4] The canal was completed at a cost of £250,000.[5] With the Stroudwater Navigation, which had been completed in 1779, it completed a link between the River Severn in the west and the River Thames in the east.

As built, the main line was just under 28.7 miles (46.2 km) long and had 44 locks. The branch to Cirencester added a further 1.5 miles (2.4 km). The first 2.5 miles (4.0 km) from Wallbridge to Brimscombe, where there was a transhipment basin, was built with locks 69 by 16 feet (21.0 by 4.9 m), enabling Severn trows to use it. Beyond that, the locks were 90 by 12.7 feet (27.4 by 3.9 m) and the boats used were Thames barges. The canal's summit, which is 362 feet (110 m) above sea level and 8.1 miles (13.0 km) long, includes the 3,817-yard (3,490 m) Sapperton Tunnel, at the time, the longest in England. Its length has only been exceeded by two other canal tunnels, at Standedge in the Pennines and at Strood in Kent.[6][7]

Operation

Until the summit level was completed, little thought seems to have been given to water supply. It was assumed that the River Frome, to the west of the tunnel, the River Churn which flowed through Cirencester, and the River Coln, together with springs at Boxwell and a well near the source of the River Thames at Thames Head, would be sufficient. The original horse pump at Thames Head was replaced by a windmill, but Clowes discovered that he could not stop the summit pound from leaking. The flow on the River Churn was 1.7 million gallons (7.7 Megalitres (Ml)) per day, whereas the calculated flow at the start of the project had been more than ten times this value. The summit level was losing around 1.1 million gallons per day (5 Mld), largely because the underlying rock was porous limestone, and it was estimated that around half of the daily requirement could actually be supplied. The wells at Thames Head were extended and a Boulton & Watt steam engine was installed in 1792 to pump the water into the canal. An extra, shallow lock was built at Boxwell, which allowed the level of the canal to be dropped beyond it, and more water to be taken from Boxwell springs. The new arrangements were adequate, although some of the reason was the failure of traffic to develop to the levels anticipated.[7][8]

Leakage was affected by springs breaking through the clay lining of the canal bed. In summer when the springs receded, water was lost through these holes at a rate greater than the available supply. In one of the attempts to rectify this problem, the size of the locks was reduced which resulted in their unusual double headed appearance. In a further attempt to prevent water loss, at King's Reach, the section immediately east of Sapperton Tunnel, the canal was lined with concrete rather than puddle clay.

Neither of the river navigations to which the canal connected were satisfactory. In the west, the situation was remedied in 1820, with the construction of the Gloucester and Sharpness Canal seven years later. On the Thames, there had been a proposal for a canal from Lechlade to Abingdon in 1784, and for a cut from Inglesham to Buscot in 1788, but neither had been built. Some improvements were made to the river after 1786, but the Canal company encouraged the building of bypasses. The Wilts and Berks Canal was one, providing a link to the river at Abingdon, but although it was proposed in 1793, it was not opened until 1810, and the North Wilts Canal, which provided a connecting link from Latton to Swindon was not completed until 1819. Ultimately, most of the Bristol to London trade used the Kennet and Avon Canal after it opened in 1810, as it provided a much shorter route than the Thames and Severn Canal.[9]

Decline

Railway competition began in 1836, when the Cheltenham and Great Western Railway proposed a line between Swindon and Cheltenham, via Gloucester. The canal company opposed the scheme, and received compensation of £7,500 from the railway company over the next four and a half years.. The line opened to Kemble in 1841, and the tolls on the carriage of materials for the railway's construction improved the financial position of the canal for a short time. The railway company was then taken over by the Great Western Railway, who built a new tunnel at Sapperton, and opened the railway to Gloucester in 1845. Canal tolls were cut, in an attempt to retain traffic, but toll revenue fell from £11,000 to £2,874 between 1841 and 1855. The Thames Commissioners were also in financial difficulties, and the Thames was nearly unnavigable from Oxford to Lechlade after 1855. In 1866, plans to convert the canal to a railway were rejected by Parliament, but the Thames Commissioners were replaced by the Thames Conservancy, and most of the river was soon returned to a navigable state.[10]

The condition of the canal continued to decline. Complaints were made about its state in 1874 and 1885, which resulted in surveys being undertaken, but little was done to remedy the situation. In 1893, the Thames and Severn company announced that the canal between Chalford and Inglesham would close two days later. Negotiations with a number of interested parties took place, and having given an assurance that it would not be converted into a railway to the Great Western Railway, an Act of Parliament was obtained in 1895, which formed a Trust with powers to raise £15,000. The Trust included representatives from the Sharpness New Docks & Gloucester & Birmingham Company, the Stroudwater Canal, the Staffs & Worcs Canal, the Severn Commissioners, Berkshire, Gloucestershire and Wiltshire County Councils and Stroud and Cirencester District Councils. At the same time as the Trust refurbished the canal, the upper Thames was upgraded by the Thames Conservancy. Although the canal was re-opened in March 1899, lack of water on the summit level soon closed it again, after which Gloucestershire County Council suggested that they take it over. They did so on 2 July 1901. In 1925 they began negotiations with interested parties which ultimately led to the abandonment of the canal from Chalford to Inglesham in 1927. The Stroudwater Navigation managed to keep the remaining section open until 1933, when it was abandoned,[11] and their own canal closed in 1941.[12]

Restoration

The canal towpath at South Cerney near Cirencester. Large trees have grown up in the 70 years since the canal was abandoned.

Following the publication of Ronald Russell's influential book entitled Lost Canals of England and Wales in 1972, a number of canal restoration schemes sprang up. Among the organisations established that year was the Stroudwater Canal Society, which soon became the Stroudwater, Thames and Severn Canal Trust,[13] and from 1975, the Cotswold Canals Trust.[14] Volunteers for the Trust have since been working to restore both the Stroudwater Navigation and the Thames and Severn Canal. Extensive lobbying in 1979 resulted in Gloucestershire County Council deciding to rebuild a damaged bridge at Daneway, rather than replace it with a much cheaper low-level causeway, which would have severed the route. Two years later, County Council support was required when the project benefited from 20 workers and a £17,000 budget for materials under the Job Creation Scheme set up by the Manpower Services Commission, as the Council had to manage the scheme.[15]

In 1991, the Trust commissioned the engineering consultancy Sir William Halcrow and Partners to conduct a feasibility study for restoration of the eastern end of the canal. Funding was provided by the National Rivers Authority, local authorities, and other interested parties. The report demonstrated that there was a good case for the provision of a navigable culvert beneath the proposed Latton Bypass. Despite initially saying that a culvert would not be built,[16] negotiation continued, and – helped by grants of £250,000 from Gloucestershire County Council and £125,000 from North Wilts Council – the Department of the Environment decided in 1997 that a culvert would be provided under the road.[17]

Funding

In order to provide a suitable structure to drive the restoration forwards, the Cotswold Canals Partnership was established in 2001, drawing together people representing the Proprietors of the Stroudwater Navigation, the Cotswold Canals Trust, councils at district and county level, and a number of other interested parties.[18] In 2002, the waterway was identified as being of high priority in the Association of Inland Navigation Authorities report entitled Vision for Strategic Enhancement of Britain's Inland Navigation Network, and was one of several new projects highlighted at British Waterways' Unlocked and Unlimited conference held in March. The estimated cost of the project was £82 million.[19] Having raised £100,000, the Trust lodged the money with the Waterways Trust, in the hope that it could be used as match funding for any grants that might be received. Andy Stumpf became the full-time Regeneration Programme Manager, working on a major bid application to the Heritage Lottery Fund (HLF) to finance the restoration, and the canal was visited by Charles, Prince of Wales, in his capacity as Patron of the Waterways Trust.[20] A Heritage Survey, which cost £60,000 and was funded by the Inland Waterways Association, was carried out, as was a Community Development Plan and a Visitor Management Strategy, costing another £30,000, all of which were pre-requisites for the main HLF bid.[21]

By the time the bid was ready for submission, the HLF were under pressure for the funds they had, and asked British Waterways, who were managing the application, to split the bid and the project into smaller phases. At the end of 2003, a provisional grant of £11.3 million was awarded by the HLF, to enable the restoration of the Stroudwater Navigation between Stonehouse and Wallbridge, and the Thames and Severn Canal between Wallbridge and Brimscombe Port. An additional £2.9 million was received from the European Inter-Regional budget for this first phase.[22] By the time the grant was awarded in January 2006, it had risen to £11.9 million, and a further £6 million of match funding was received from the South West of England Regional Development Agency.[18] Alongside these major developments, the Trust has rebuilt a number of locks and bridges and some small sections of the rest of the route are now in water.

With the restoration underway, British Waterways pulled out of the partnership in 2008 because of financial difficulties. The role of project leader was taken over by Stroud District Council, and a new body, the Stroud Valleys Canal Company,[23] was created in March 2009 to act as a holding company for the assets of the waterway, with a responsibility to manage and maintain it once it is reopened. They now own most of the canal bed between Wallbridge and Brimscombe.[24] The cost of the restoration exceeded estimates, and as a result, the Heritage Lottery Fund agreed to supply an additional £800,000 in December 2012, to allow full restoration between Stonehouse and Bowbridge, and the upgrading of the towpath onwards to Brimscombe Port. Work on the canal beyond Bowbridge will now be handled by volunteers.[25]

Progress

The Restoration Programme is divided into several key phases. Phase 1a covers 6 miles of the most difficult section to restore, centred on Stroud, comprising the lengths of the Stroudwater Navigation between Stonehouse and Wallbridge, and the Thames and Severn Canal between Wallbridge and Brimscombe Port. Phase 1b connects the completed Phase 1a section, westwards, to the rest of the inland waterways network, at Saul Junction on the Gloucester and Sharpness Canal. Phase 2 covers work at the eastern end of the canal, between Gateway Bridge in the Cotswold Water Park (Cerney Wick), and Inglesham Lock, the junction with the Thames.[26] It will form a link between the upper Thames, the North Wilts Canal and the Wilts and Berks Canal. Phase 3 completes the project, connecting Brimscombe Port in the west with Gateway Bridge in the east, via Sapperton Tunnel.[27]

Phase 1a

Gates being fitted to Bowbridge Lock as part of phase 1a

Phase 1a of the Restoration Programme covers the length of canal from The Ocean pub at Stonehouse, on the Stroudwater Navigation, to Brimscombe Port, east of Stroud, on the Thames and Severn Canal – a length of about 6 miles. The work includes restoration of 10 locks, reconstruction of 10 bridges, and re-instatement of about 2100m of in-filled canal; plus the major reconstruction of Brimscombe Port.[28]

Funding was in place for all of the scheduled work, but increasing costs have curtailed the programme. A revised plan – with increased support from volunteer labour – aims to have restoration completed to Bowbridge by the end of 2015, with all major work eastwards put on hold.[28]

Phase 1a also included the provision of a multi-user trail between Stonehouse and Saul, but this is likely to be held over to Phase 1b.[28]

The final section of the canal before it joins the Stroudwater Navigation presents particular problems for restoration, as the channel had been used as part of a flood relief scheme by the Environment Agency. Water from the Slad Brook, which is culverted beneath Stroud, joins the canal a short distance above Lower Wallbridge Lock. The Painswick Stream and Ruscombe Brook join the channel below the junction and flow through the Dudbridge locks, after which the water is discharged into the River Frome below the A419 Dudbridge Road bridge. As a consequence of its flood relief function, the channel here is classified as a "main river".[29] Designs for reinstatement of the canal have had to accommodate large flows on this section, and include underground bywash culverts, capable of carrying the full flood flow of the streams.[30]

At Capels Mill, the bed of the canal was used as the route for the Stroud Bypass in the 1980s, and so a diversion had to be built at this point. It passes through an area which was used as a landfill site in the 1960s and 1970s. Some 355 yards (325 m) of new channel was constructed, some of it edged with sheet piling. After passing through a railway viaduct, the bank is supported by a series of contiguous concrete piles, which were drilled to a depth of between 30 feet (9 m) and 49 feet (15 m) and provide a retaining wall which is 35 feet (11 m) tall at its highest point. As the project neared completion, open days to allow the public to walk along the bottom of the new canal section were held on 10 and 11 May 2013, and were attended by over 1,800 people. Where domestic rubbish had to be removed, it was relocated on the site, covered with 2 feet (600 mm) of crushed recycled concrete and a layer of Bentomat geotextile, which was topped by subsoil and topsoil obtained from elsewhere on the site. Tubular vents allow any methane produced by the disturbed rubbish to escape safely. The new section was filled with water and officially completed on 2 June 2013.[31]

Phase 1b

The second phase of the Restoration Programme covers the length of the Stroudwater Navigation between the Ocean Railway Bridge, Stonehouse, and Saul Junction on the Gloucester and Sharpness Canal, a distance of about 4 miles (6.4 km). The simpler work includes construction of 2 new locks, restoration of a further 6 locks, construction of several minor road bridges, and re-instatement of about 1 mile (1.6 km) of in-filled canal.[32]

This section poses some significant engineering problems. A new railway bridge is required at Stonehouse, where the canal has been culverted underneath the Bristol-Birmingham line.[32] Since the canal was abandoned, the River Frome and the Oldbury Brook have both been diverted to use part of the canal bed.[32] Most significantly, the original route has been divided by both the construction of the M5 motorway and development of the A38 trunk road. Plans to overcome these obstacles have been produced, but await the necessary funding.[33]

The trust will conserve this section of the route until the funding is available.

A bid for Heritage Lottery funding to restore phase 1b was submitted in late 2015.[34]

Phase 2

Restoration Programme Phase 2 covers work at the eastern end of the canal, between Gateway Bridge in the Cotswold Water Park (Cerney Wick), and the junction with the Thames at Inglesham Lock, a distance of about 10 miles (16 km). The section does not pose the major engineering challenges faced elsewhere, but land ownership is an issue, and there are several miles of infilled canal around Kempsford.[26]

Funding is only in place for minor projects, but several locks have been substantially restored, lengths of towpath reconstructed, and dredging completed.[26]

In 2002 British Waterways bought the lock at Inglesham and the adjacent round house, to safeguard the route of the canal. After they pulled out of the restoration scheme, they sold the house, which was bought by a member of the Cotswold Canals Trust, and transferred the ownership of the lock to the Trust.[35] In June 2010 the Inland Waterways Association (IWA) mounted a national campaign for £125,000 to enable Inglesham Lock and around 420 yards (380 m) of the pound above it to be restored.[36]

Phase 3

The completion of the project is outlined in Phase 3, to connect Brimscombe Port in the west with Gateway Bridge in the east, a distance of about 16 miles (26 km).[27] Restoring this central section poses several major engineering difficulties: firstly to overcome the water supply that was always inadequate, and secondly because the 2.2-mile-long Sapperton Tunnel is blocked by two rock falls. In addition, there are two missing railway bridges, an aqueduct, and 31 locks to rebuild. As of May 2015, there is no significant funding in place for any restoration projects on this section of the canal.[27]

Structures

Chalford Roundhouse at the site of Chalford Wharf

A number of the buildings associated with the canal have survived and appear on the listed building register, including five circular cottages, built with three floors. The lower floor was intended to be used as a store and has access to the outside. A set of outside steps leads up to the first floor, which is around 16 feet 10 inches (5.13 m) in diameter. It was designed as a living area and was equipped with a cooking range. A staircase, built between the inner and outer wall, leads up to a circular bedroom on the second floor.[37] The round houses are situated at Lechlade, by the entrance lock from the Thames;[38] at Marston Meysey;[39] at Cerney Wick near Latton, next to lock 39;[40] at Coates, close to the eastern portal of the tunnel;[41] and at Chalford, next to lock 13.[42] Some had a pointed slate roof, while others had a lead cone, which collected rain water for drinking. They were built in the 1790s for use by lock-keepers and lengthmen, but were not particularly popular due to the limited amount of space and problems with finding suitable furniture for a circular room.[37]

Literary connections

In 1953, C. S. Forester published Hornblower and the Atropos, a historical novel set during the Napoleonic Wars, in which Horatio Hornblower, a captain in the Royal Navy, travels along the canal to London. He assists with legging the boat through the Sapperton tunnel and then steering it after the postillion in charge of the horses is injured.[43][44]

Points of interest

See also

Bibliography

  • Hadfield, Charles (1969). The Canals of South and South East England. David and Charles. ISBN 0-7153-4693-8. {{cite book}}: Invalid |ref=harv (help)
  • Forester, C. S. (2006). Hornblower and the Atropos. Penguin. ISBN 978-0-14-102504-9. {{cite book}}: Invalid |ref=harv (help)
  • Jackson, W Turrentine; Chaloner, W H (1962). The Development of Transport in Modern England. Routledge. ISBN 0-7146-1326-6. {{cite book}}: Invalid |ref=harv (help)
  • McKnight, Hugh (1981). The Shell Book of Inland Waterways. David & Charles. ISBN 0-7153-8239-X. {{cite book}}: Invalid |ref=harv (help)
  • Skempton, A. W. (2002). A Biographical Dictionary of Civil Engineers in Great Britain and Ireland. Thomas Telford. ISBN 0-7277-2939-X. {{cite book}}: Invalid |ref=harv (help)
  • Squires, Roger (2008). Britain's restored canals. Landmark Publishing. ISBN 978-1-84306-331-5. {{cite book}}: Invalid |ref=harv (help)

References

  1. ^ Hadfield 1969, pp. 315–316.
  2. ^ Hadfield 1969, p. 316.
  3. ^ Skempton 2002.
  4. ^ a b Hadfield 1969, pp. 316–319
  5. ^ Jackson & Chaloner 1962.
  6. ^ Hadfield 1969, p. 319.
  7. ^ a b Cumberlidge 2009, pp. 309–310
  8. ^ Hadfield 1969, pp. 323–324.
  9. ^ Hadfield 1969, pp. 322–324.
  10. ^ Hadfield 1969, pp. 333–335.
  11. ^ Hadfield 1969, pp. 335–340.
  12. ^ Hadfield 1969, p. 314.
  13. ^ Squires 2008, p. 78.
  14. ^ Cumberlidge 2009, p. 285.
  15. ^ Squires 2008, pp. 104, 110.
  16. ^ Squires 2008, pp. 128, 130.
  17. ^ Squires 2008, p. 140.
  18. ^ a b "Cotswold Canals Partnership". Cotswold Canals Partnership. Archived from the original on 6 May 2012.
  19. ^ Squires 2008, p. 154.
  20. ^ Squires 2008, p. 156.
  21. ^ Squires 2008, p. 158.
  22. ^ Squires 2008, p. 164.
  23. ^ "Heritage". Stroudwater Canal Proprietors.
  24. ^ "Stroud Valleys Canal Company". Cotswold Canals Partnership. Archived from the original on 26 May 2012.
  25. ^ "Project Update" (PDF). Stround District Council. December 2012. Retrieved 11 June 2013.
  26. ^ a b c "Cotswold Canals – Phase 2 Restoration". Cotswold Canals in Pictures. Retrieved 4 May 2015.
  27. ^ a b c "Cotswold Canals – Phase 3 Restoration". Cotswold Canals in Pictures. Retrieved 4 May 2015.
  28. ^ a b c "Cotswold Canals – Phase 1a Restoration". Cotswold Canals in Pictures. Retrieved 4 May 2015.
  29. ^ "Ebley to Wallbridge". Proprietors of the Stroudwater Navigation.
  30. ^ "Plan 11a Dudbridge Locks" (PDF). Cotswold Canals Partnership.
  31. ^ "Capels Mill - Conclusion". Cotswold Canals Trust. Retrieved 9 June 2013.
  32. ^ a b c "Cotswold Canals – Phase 1b Restoration". Cotswold Canals in Pictures. Retrieved 4 May 2015.
  33. ^ "Occupation Bridge to Westfield Lock" (PDF). Cotswold Canals Partnership.
  34. ^ "Progress Roundup". Navvies (274). Waterway Recovery Group: 42. January 2016.
  35. ^ "British Waterways transfers ownership" (PDF). Cotswold Canals Trust.
  36. ^ "Inglesham Lock – IWA National Restoration Appeal". ('We want to extend the Thames!'). Inland Waterways Association. Retrieved 1 July 2010.
  37. ^ a b McKnight 1981, p. 88
  38. ^ Historic England. "Details from listed building database ({{{num}}})". National Heritage List for England.
  39. ^ Historic England. "Details from listed building database ({{{num}}})". National Heritage List for England.
  40. ^ Historic England. "Details from listed building database ({{{num}}})". National Heritage List for England.
  41. ^ "Map" (PDF). Cotswold Canals.
  42. ^ Historic England. "Details from listed building database ({{{num}}})". National Heritage List for England.
  43. ^ McKnight 1981, p. 145.
  44. ^ Excerpt from "Hornblower and the Atropos"