Yellow Line (Namma Metro)

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by 182.73.121.198 (talk) at 09:34, 27 June 2018. The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Yellow Line
Overview
OwnerBangalore Metro Rail Corporation Limited (BMRCL)
LocaleBangalore, Karnataka, India
Termini
  • R.V. Road
  • Bommasandra
Stations16
Websitebmrc.co.in
Service
TypeMetro
SystemNamma Metro
Depot(s)Hebbagodi
History
Planned openingMarch 2023 (2023-03)
Technical
Line length18.82 km (11.69 mi)
Number of tracks2
CharacterElevated
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC third rail

The Yellow Line of the Namma Metro is a proposed line that forms part of the metro rail system for the city of Bangalore, Karnataka, India. The 18.82 km line connects R.V. Road with Bommasandra. The Yellow Line is fully elevated and has 16 stations.[1] The R.V. Road station will serve as the interchange station with the Green Line and the Jayadeva Hospital station will serve as the interchange station with the proposed Red Line.[2]

Planning

The Yellow Line was included in Phase II of the Namma Metro project. Phase II also included another new line, the Red Line, as well as extensions of the Purple Line and Green Line.[1] Phase II spans a length of 72.095 km – 13.79 km underground, 0.48 km at grade and 57.825 km elevated, and adds 61 stations to the network, of which 12 are underground.[3] Unlike Phase I of the project, all stations in Phase II will have parking facilities.[4]

The State Government accorded approval vide Order No. UDD 127 BMR 2010 dated 4 January 2011 for preparation of the detailed project report (DPR) for Phase II by the DMRC.[1][5] The high power committee (HPC), in July 2011, gave in-principle clearance to proceed with Phase II.[6] The Karnataka government gave in-principle approval to Phase II of the Namma Metro project on 3 January 2012.[7][8] Phase II was cleared by the expenditure finance committee (EFC) in August 2013.[9] The Union Cabinet announced that it had approved plans for phase II on 30 January 2014.[10] The estimated total cost for Phase II is around 26,405 crore (US$3.2 billion).[11] The State Government will contribute 9,000 crore (US$1.1 billion).[12] The project cost of 26,405 is the 2011–12 price level, which it is set to escalate at 5 per cent every year with increasing cost of inputs. The Union government will share that part of cost escalation due to increase in central levies, while the Karnataka State and BMRCL have to bear any other escalation. According to the experts, the total project cost for Phase II is estimated to reach at least 30,000 crore (US$3.6 billion) at the start of construction itself.

Tenders for the construction of the R V Road – Bommasandra line were floated in 3 packages.[13] On 9 December 2016, the agency floated tenders for the construction of 6.418 km stretch from Bommasandra to Hosa Road station. The work involves the construction of five stations — Bommasandra, Hebbagodi, Huskur Road, Electronic City-II and Electronic City-I, and also includes construction of the depot entry line to Hebbagodi depot.[14] Tenders for the 6.38 km stretch from Hosa Road to HSR Layout were floated the next day.[15] Both packages were awarded to Thailand-based ITD Cementation India in May 2017,[16] a total contract of 1,750 crore (US$210 million).[17] Work is expected to begin by June 2017, and be completed within 27 months.

The final tender for the construction of the 6.34 km long elevated section and 5 stations - Central Silk Board, BTM Layout, Jayadeva Hospital, Ragigudda and RV Road - was awarded to a joint venture between Hindustan Construction Company Ltd (51%) and URC Construction Pvt Ltd. (49%) on 3 July 2017. The contract was worth 797.29 crore (US$96 million) and includes the construction of a road-cum-rail flyover, road widening and allied works.[18][19]

Section Length

(km)

Stations Contract cost Contractor(s) Expected completion
Bommasandra - Hosur Road 6.418 Bommasandra, Hebbagodi, Huskur Road, Electronic City-II, Electronic City-I 1,750 crore (US$210 million) ITD Cementation India September 2019
Hosa Road - HSR Layout 6.38 Hosa Road, Basapura Road, Chikkabegur, Munneshwara Nagar, Oxford College, HSR Layout
HSR Layout - RV Road 6.34 Central Silk Board, BTM Layout, Jayadeva Hospital, Ragigudda, RV Road 797.29 crore (US$96 million) Hindustan Construction Company (51%)
URC Construction (49%)
July 2020

Funding

Indian firms Biocon and Infosys announced that they would provide funding for the construction of the Hebbagodi and Electronics City metro stations respectively on the Yellow Line. BMRCL expects that each firm will contribute 100 crore (US$12 million) towards the project. Biocon CMD Kiran Mazumdar Shaw stated that the company wanted to fund the project because it would help decongest the city. Both Biocon and Infosys have offices located near the stations.[20]

Stations

The Yellow Line is fully elevated and will have 16 stations.

colspan="6" align="center" style="background:#Template:Namma Metro color;" | Yellow Line
# Station Name Opening Connections Contractor(s)
1 Rashtreeya Vidyalaya Road   Green Line Hindustan Construction Company (51%)
URC Construction (49%)
2 Ragigudda Hindustan Construction Company (51%)
URC Construction (49%)
3 Jayadeva  Red Line Hindustan Construction Company (51%)
URC Construction (49%)
4 BTM Layout Hindustan Construction Company (51%)
URC Construction (49%)
5 Silk Board junction  ORR Line Hindustan Construction Company (51%)
URC Construction (49%)
6 HSR Layout ITD Cementation India
7 Oxford College ITD Cementation India
8 Muneshwara nagara ITD Cementation India
9 Chickka Begur ITD Cementation India
10 Basapura ITD Cementation India
11 Hosa road ITD Cementation India
12 Electronic City-1 ITD Cementation India
13 Electronic City-2 ITD Cementation India
14 Huskur Road ITD Cementation India
15 Hebbagodi ITD Cementation India
16 Bommasandra ITD Cementation India

References

  1. ^ a b c bmrc.co.in/pdf/phase2/phase2forweb.pdf
  2. ^ "Know the location of new Red Line metro stations". The Hindu. Retrieved 22 July 2017.
  3. ^ "Metro gets poll push for Phase II". Deccan Chronicle. 2013-06-04. Retrieved 2013-09-28.
  4. ^ "Metro Phase II will be bigger, better, says BMRCL chief". Deccan Herald. Retrieved 13 January 2017.
  5. ^ "State Cabinet approves phase-II of metro". Business Standard. 4 January 2012. Retrieved 6 March 2012.
  6. ^ "Metro project: Cabinet approves two new lines for Phase 2". The Times of India. 4 January 2012.
  7. ^ Bangalore, 4 Jan, DHNS:. "Centre's nod for Phase-II of Metro may take 6 months". Deccan Herald. Retrieved 6 March 2012.{{cite web}}: CS1 maint: extra punctuation (link) CS1 maint: multiple names: authors list (link) CS1 maint: numeric names: authors list (link)
  8. ^ "Cabinet clears Namma Metro Phase 2 – Bangalore – DNA". Daily News and Analysis. 4 January 2012. Retrieved 6 March 2012.
  9. ^ Neha Sethi; Rahul Chandran (2013-09-05). "EFC clears `26,405 cr for Bangalore Metro phase II". Livemint. Retrieved 2013-09-28.
  10. ^ IRJ, 30 Jan; (30 January 2014). "Go-ahead for Bangalore metro phase 2".{{cite web}}: CS1 maint: extra punctuation (link) CS1 maint: multiple names: authors list (link) CS1 maint: numeric names: authors list (link)
  11. ^ "Cities / Bangalore : Frame policy for differential fare pricing, BMRCL told". The Hindu. Chennai, India. 22 February 2012. Retrieved 6 March 2012.
  12. ^ "Underground Bengaluru Metro Station service flagged off, Siddaramaiah seeks Centre's help for Namma Metro phase III | Latest News & Updates at Daily News & Analysis". dna. 29 April 2016. Retrieved 29 April 2016.
  13. ^ "Tender for Electronics City metro reach issued – Bangalore Mirror -". Bangalore Mirror. Retrieved 7 March 2017.
  14. ^ "Metro floats tenders for Electronics City route". The New Indian Express. Retrieved 11 December 2016.
  15. ^ Reporter, Staff. "Electronics City inches closer to being on metro map". The Hindu. Retrieved 11 December 2016.
  16. ^ "Thai company ITD will build stations on e-city line in Bengaluru". The Economic Times. Retrieved 11 May 2017.
  17. ^ Menezes, Naveen (6 July 2017). "Civic work to start in a year: Metro Phase II boasts of most expensive underground line". The Economic Times. Retrieved 22 July 2017.
  18. ^ "HCC JV bags Rs 797 crore order from Bangalore Metro". The Economic Times. 2017-07-03. Retrieved 2017-07-22.
  19. ^ Bureau, BW Online. "Hindustan Construction Receives Rs 798 Crore Bangalore Metro Contract". BW Businessworld. Retrieved 2017-07-22. {{cite news}}: |last= has generic name (help)
  20. ^ "Biocon, Infy to Adopt Two Metro Stations – ETtech". ETtech.com. Retrieved 18 May 2017.