Line 3 (Mumbai Metro)
Line 3 | |
---|---|
Overview | |
Status | Planned |
Owner | Mumbai Metropolitan Region Development Authority (MMRDA) |
Locale | Mumbai, Maharashtra, India |
Termini | |
Stations | 27 |
Service | |
Type | Metro |
System | Mumbai Metro |
Depot(s) | Aarey Milk Colony |
Rolling stock | To be announced after tender awarding. |
History | |
Opened | 2020 |
Technical | |
Line length | 33.05 km (20.54 mi) |
Character | Fully Underground |
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge |
Line 3 of the Mumbai Metro, also referred to as the Colaba–Bandra-SEEPZ line, is a part of the metro system for the city of Mumbai, India that is currently in its tendering stage (as of January 2015).[2] When completed, the 33.5-km long line will be the first fully underground metro line in Mumbai, and in India.[3] The metro line will connect Cuffe Parade business district in the extreme south of the city to SEEPZ in the north-central[4] with 26 underground and one at-grade station.[5] The track width is standard gauge. The cost of this corridor is estimated at ₹23,136 crore (US$2.8 billion).[6][7] Line 3 is expected to reduce road congestion, besides reducing the load on the Western Line between Bandra and Churchgate.[8]
The project will be implemented by the Mumbai Metro Rail Corporation Limited (MMRCL). The line starts at Cuffe Parade, will run through Nariman Point, Churchgate, CST, Girgam, Worli, Mahim, Kalina University, Dadar, Bandra, Bandra-Kurla Complex, past the domestic and international terminals of Mumbai Airport, through Andheri MIDC and terminates at SEEPZ.[8][9]
History
A 20 km metro line from Colaba to Bandra was announced in January 2004, as part of a master plan unveiled by the Mumbai Metropolitan Region Development Authority (MMRDA). The plan encompassed a total of 146 kilometres (91 mi) of track, of which 32 kilometres (20 mi) was proposed to be underground. The MMRDA unveiled plans for an extended Colaba-Bandra-SEEPZ metro line in 2011. According to its earlier plans, a 20-km metro line from Colaba to Bandra was to be constructed, running underground for 10 kilometres (6.2 mi) from Colaba to Mahalaxmi, and then on an elevated track from Mahalaxmi to Bandra. The MMRDA decided to extend the line to the Chatrapati Shivaji International Airport. The 33.5-kilometre (20.8 mi) Colaba-Bandra-SEEPZ line was estimated to cost ₹21,000 crore (US$2.5 billion),[10] and will be the city's first fully underground metro line. It will have 27 stations[11] at Nariman Point, BKC, MIDC, SEEPZ, and elsewhere.[12] According the MMRDA, an underground metro will minimise land acquisition and disturbance to traffic during construction compared to an elevated metro.[13]
The Mumbai Metro Rail Corporation (MMRC), registered under provisions of Company Act, 1956, was constituted as a fully owned company of the MMRDA on 30 April 2008, as per state government directives.[14]
On 27 February 2012, the Central Government gave in-principle approval to the plan for Line 3. The project will be financed by the Japanese International Cooperation Agency (JICA), the state government, the central government, and other sources.[15] In April 2012, the MMRDA announced plans to grant the MMRC increased management autonomy, in an effort to enhance the project's operational efficiency.[16]
In early 2012, the MMRDA conducted talks with officials at Chhatrapati Shivaji International Airport (CSIA) to finance or construct the line's three stations at the airport and GVK SkyCity, a proposed nearby commercial development.[10][17] Mumbai International Airport Limited (MIAL) agreed to bear the cost of constructing the three stations, which is expected to total ₹777 crore. According to MIAL's CEO, R.K. Jain, MIAL is willing to contribute to the metro's construction because of the potential increase in passenger convenience.[18] MIAL estimated the cost of developing the metro lines in the airport as ₹518 crore.[17]
Source[9] | Amount (₹crores) | Share (%) |
---|---|---|
Equity by Centre | 2,403 | 10.4 |
Equity by MMRC and State | 2,403 | 10.4 |
Sub debt by Centre | 1,025 | 4.4 |
Sub debt by State | 1,615 | 7 |
Property development and impact fee | 1,000 | 4.3 |
Stakeholder contribution (MIAL) | 777 | 3.4 |
ASIDE funding / MMRDA grant | 679 | 2.9 |
JICA loan | 13,235 | 57.2 |
Total | 23,136 | 100 |
In August 2012, the Urban Development Ministry rejected the Planning Commission's proposal to implement Line 3 in a public-private partnership (PPP) mode, having found the mode unsatisfactory for the Delhi Airport Metro Express. The ministry instead proposed a funding pattern with a ratio of 20:80 between the Centre and the State. Of the State equity, 45% was proposed to be through a loan from the Japan International Cooperation Agency (JICA).[19] On 30 May 2013, following a meeting between the prime ministers of India and Japan in Tokyo, the Japanese state agreed to lend ¥71 billion (₹4,553 crore) in a soft loan at an interest rate of 1.44% for the construction of Line 3.[20][21] The Union Cabinet granted clearance to Line 3 on 27 June 2013.[22][23] The Cabinet also decide to convert Mumbai Metro Rail Corporation (MMRC), the existing state-level special purpose vehicle formed to implement metro projects, into a joint venture company of the state and central governments with equity participation.[24]
JICA will provide financial assistance in the form of a soft loan amounting to ₹13,235 crore (US$1.6 billion) for the ₹23,136 crore (US$2.8 billion) project.[3][25] JICA will fund 57.2% of the equity.[9] The other finance will come from the central and state equity of 10.4% each, sub-debt by the central government (4.4%), sub-debt by the state (7%), property development and impact fee (4.3%), stakeholder contribution from the Mumbai International Airport Ltd. (3.4%) and MMRDA grant/aside funding (2.9%).[26]
The MMRC's board consists of five members each from state and central governments.[8] The MMRDA presented their metro line plan to the Brihanmumbai Municipal Corporation on 13 February 2014.[27] Underground utilities will have to shifted to construct the line, as it is completely underground.[28]
Bidders for the work on tunnels and stations were to submit their bids by 30 October 2013.[29][30] On 31 January 2014, the bid document was modified and the annual turnover requirement was reduced to "average annual construction turnover of not less than USD 175 million defined as billing for civil infrastructure work completed or in progress over the last five years ending on March 2013". Sanjay Sethi, managing director of MMRC, stated, "The annual turnover requirement must have been set with the idea of attracting specific companies to the project. However, the Japan International Cooperation Agency (JICA) felt that consortia or joint ventures are a combination of management contractors and construction contractors. In all Metro projects, the annual turnover is the starting point for bidding based on which we should not restrict applications. The issue was also raised by several potential bidders."[4][31] The last date for the submission of pre-qualification bids was extended to 10 March 2014.[32] Fourteen pre-qualification bids were received for the design and construction of underground stations and tunnels for Line 3. The 14 bidders were: Afcon-KMB, CEC-ITD Cementation India-TPL, CTCEC-Pan India Infrastructures Pvt Ltd, Dogus-Soma Constructions, IL&FS-CR256 (China Railway), JKumar-CRTG, Larsen & Toubro-STEC, Mosmetrostory-Hindustan Construction Company, OHL-SK Engineering & Construction, Pratibha-GDYT Consortium, Sacyr-CMC-Essar, Salin Impreglio-Gammon, Strabag-AG-Patel Engineering and Unity Infrastructure-IVRCL-CTG.[33][34][35][36]
Line 3 was approved by the state cabinet on 26 February 2014.[37]
The foundation stone for the project was laid by Chief Minister Prithviraj Chavan in a bhoomi pujan ceremony at Andheri on 26 August 2014, in the presence of Union Urban Development minister Venkaiah Naidu.[38][39] The move was described by the media as a cosmetic gesture, as the developers of the project had not yet been decided and actual construction was expected to begin only by December 2014.[40][41] The date of the ceremony was a few days before the code of conduct for the 2014 State Assembly elections would come into force, which would prohibit the ruling Congress-NCP government from politicising the ceremony.[41][42] Some citizens protested against the State government at the ground breaking site. They protested the slow implementation and cost escalation of the Mumbai Metro project.[43]
Line 3 is being implemented through the engineering, procurement and construction (EPC) model.[35] The original deadline for the project was 2016, but it is currently expected to be completed in 2020.[20] The contract is likely to be awarded before December 2014, so that work can start thereafter.[38][39]
Stations
Line 3 | ||||
---|---|---|---|---|
# | Station Name[44] | Connections | ||
1 | Cuffe Parade | None | ||
2 | Vidhan Bhavan | None | ||
3 | Churchgate | Western Line | ||
4 | Hutatma Chowk | None | ||
5 | CST | Central Line | ||
6 | Kalbadevi | None | ||
7 | Girgaon | None | ||
8 | Grant Road | Western Line | ||
10 | Mumbai Central | Western Line | ||
11 | Mahalaxmi | Western Line | ||
12 | Science Museum | None | ||
13 | Acharya Atrey Chowk | None | ||
14 | Worli | None | ||
15 | Siddhivinayak | None | ||
16 | Dadar | Western Line Central Line | ||
17 | Shitladevi Temple | None | ||
18 | Dharavi | None | ||
19 | Bandra Kurla Complex | None | ||
20 | Vidyanagri | None | ||
21 | Santacruz | Western Line Harbour Line | ||
22 | CSIA Domestic | None | ||
23 | Sahar Road | None | ||
24 | CSIA International | None | ||
25 | Marol | Line 1 | ||
26 | MIDC | None | ||
27 | SEEPZ | None |
Infrastructure
The car yard, where metro coaches will be parked, is proposed to be built opposite SEEPZ on Aarey Colony land.[9] Passenger interchange facilities will be provided at Chhatrapati Shivaji Terminus (Central Line); Churchgate, Mumbai Central and Mahalaxmi (Western Line), Marol Naka (Metro Line 1), Bandra-Kurla Complex (Metro Line 2) and Mahalaxmi (Mumbai Monorail).[26]
Underground construction will be carried out at an average depth of 15 to 25 meters.[5][45] The tunnels will be created using a tunnel boring machine.[5] The MMRDA plans to build 5 stations on the line — Cuffe Parade, Bandra, Kalina, MIDC and SEEPZ — using the cut-and-cover method. In this method, the ground is dug, the entire station constructed, and finally the top is covered.[27] Some stations may be constructed using the New Austrian Tunnelling method, depending on circumstances.[5]
Power
MMRDA joint project director Dilip Kawathkar stated that AC power was chosen for Line 3 "after a proper study by a team of experts" which found that the AC model was "a better option". Experts believe that the decision to use AC will escalate the project cost by 15%, since more digging is required for the rail to work on AC.[46]
References
- ^ "Mumbai: Underground Metro work to start in January 2015". NDTV.com. 21 March 2014. Retrieved 27 March 2014.
- ^ http://www.dnaindia.com/mumbai/report-metro-3-tender-to-build-car-depot-at-aarey-colony-floated-2003624
- ^ a b "Cabinet clears Mumbai Metro's third line". Times of India. 29 June 2013. Retrieved 7 July 2013.
- ^ a b "Further delay in Colaba-Seepz metro as govt tweaks bid norms". Business Standard. 4 February 2014. Retrieved 27 March 2014.
{{cite web}}
: Italic or bold markup not allowed in:|publisher=
(help) - ^ a b c d Manthan K Mehta (25 March 2014). "Metro phase III tenders to be issued by July 2013". The Times of India. TNN. Retrieved 27 March 2014.
{{cite web}}
: Italic or bold markup not allowed in:|publisher=
(help) - ^ "Mumbai Metro Line 3 plan kicks off". Mumbai Mirror. 29 June 2013. Retrieved 7 July 2013.
- ^ "Cabinet approves Mumbai Metro Line 3: FM". Zee News. 28 June 2013. Retrieved 7 July 2013.
- ^ a b c "Metro company to be revamped for Colaba-SEEPZ route - Times Of India". timesofindia.indiatimes.com. Retrieved 25 January 2014.
- ^ a b c d "Metro-III gets Rs 4,553cr Japanese loan - Mumbai - DNA". Dnaindia.com. Retrieved 28 September 2013.
- ^ a b "Development body in talks with CSIA". The Indian Express. 14 January 2012. Retrieved 16 January 2012.
- ^ "Views on Colaba-Seepz underground metro sought". DNA India. 14 December 2011. Retrieved 30 December 2011.
- ^ "Public hearing to be held for Colaba-SEEPZ Metro line". Hindustan Times. 8 December 2011. Retrieved 9 December 2011.
- ^ "Underground Metro technically feasible: Study". The Indian Express. 6 March 2014. Retrieved 27 March 2014.
{{cite web}}
: Italic or bold markup not allowed in:|publisher=
(help) - ^ "Mumbai Metro Rail Corporation". MMRDA. MMRDA. Retrieved 4 March 2014.
Establishment of MMRC: As per State Govt. directives Mumbai Metro Rail Corporation (MMRC) has been constituted as fully owned company of MMRDA (registered under provisions of Company Act, 1956) as of 30th April, 2008. MMRC (at present) is responsible for the implementation of all the Metro Rail Corridors under Mumbai Metro Rail Project.
- ^ "Centre paves way for 3rd Metro line". Times of India. 28 February 2012. Retrieved 28 March 2012.
- ^ "Mumbai Metro likely to get autonomy status: MMRDA". DNA India. 27 April 2012. Retrieved 3 May 2012.
- ^ a b "Mumbai airport plans Rs 1,600-crore upgrade". Business Standard. 10 March 2014. Retrieved 27 March 2014.
{{cite web}}
: Italic or bold markup not allowed in:|publisher=
(help) - ^ "MIAL to build three stations near airport". The Indian Express. 5 March 2012. Retrieved 28 March 2012.
- ^ "Ministry rejects Plan for Mumbai Metro-3". Daily Pioneer. 17 August 2012. Retrieved 21 August 2012.
- ^ a b "Japan’s Rs 4K crore push for Mumbai Metro". Times of India. 30 May 2013. Retrieved 7 July 2013.
- ^ "Japan sanctions $ 700 million loan for Mumbai Metro". IBN Live. 29 May 2013. Retrieved 7 July 2013.
- ^ "Colaba-Bandra Seepz Metro gets Cabinet nod". The Indian Express. 28 June 2013. Retrieved 7 July 2013.
- ^ "If Metro-III meets its deadline, Mumbai will save Rs 1.60cr fuel daily by 2021". Times of India. 29 June 2013. Retrieved 7 July 2013.
- ^ "Business Line: Cabinet approves Mumbai Metro Line-3 project". The Hindu. 28 June 2013. Retrieved 7 July 2013.
- ^ "Mumbai Metro 3 plan gets boost after Japan signs Rs 4,553 cr loan". Hindustan Times. 18 September 2013. Retrieved 28 September 2013.
- ^ a b "Japan extends Rs 4553 crore loan for Mumbai Metro-3". Ibnlive.in.com. 17 September 2013. Retrieved 28 September 2013.
- ^ a b Ateeq Shaikh (23 February 2014). "1.74L sq mts of land to be used for Colaba-Bandra-SEEPZ metro". Daily News & Analysis (DNA). Retrieved 27 March 2014.
- ^ Ranjeet Jadhav (17 February 2014). "MMRDA starts homework to avoid delays in metro line 3". Mid-day.com. Retrieved 27 March 2014.
- ^ "Ball set rolling for underground Metro III; contract by March 2014 - Times Of India". Articles.timesofindia.indiatimes.com. 18 September 2013. Retrieved 28 September 2013.
- ^ "Bids invited for 32.5 km Mumbai Metro III project design and construction". Business Standard. 17 September 2013. Retrieved 28 September 2013.
- ^ "Eligibility norms eased to attract more bidders". The Indian Express. 6 February 2014. Retrieved 27 March 2014.
{{cite web}}
: Italic or bold markup not allowed in:|publisher=
(help) - ^ "Metro-III project ready to chug along". The Indian Express. 27 February 2014. Retrieved 27 March 2014.
{{cite web}}
: Italic or bold markup not allowed in:|publisher=
(help) - ^ "14 firms bid for city's 1st underground Metro line from Colaba to Seepz". The Indian Express. 11 March 2014. Retrieved 27 March 2014.
{{cite web}}
: Italic or bold markup not allowed in:|publisher=
(help) - ^ "14 firms in race for underground work on Metro-3". The Times of India. 11 March 2014. Retrieved 27 March 2014.
{{cite web}}
: Italic or bold markup not allowed in:|publisher=
(help) - ^ a b "14 consortia show interest in Mumbai Metro's underground line". Business Standard. 10 March 2014. Retrieved 27 March 2014.
{{cite web}}
: Italic or bold markup not allowed in:|publisher=
(help) - ^ "14 companies in fray for Colaba-SEEPZ Metro Line-3 underground stations & tunnels". Mid-day.com. 10 March 2014. Retrieved 27 March 2014.
- ^ "Cabinet nod to Rs 23k cr Metro-III project". The Times of India. 27 February 2014. Retrieved 27 March 2014.
{{cite web}}
: Italic or bold markup not allowed in:|publisher=
(help) - ^ a b http://gulfnews.com/news/world/india/mumbai-metro-3-foundation-stone-laid-1.1376929?utm_content=1.1376929&utm_medium=RSS&utm_source=Feeds&utm_campaign=Mumbai_Metro-3_foundation_stone_laid&localLinksEnabled=false&utm_term=News_RSS_feed
- ^ a b http://www.business-standard.com/article/economy-policy/construction-for-mumbai-metro-iii-may-start-in-december-114082601137_1.html
- ^ timesofindia.indiatimes.com/city/mumbai/No-booster-dose-for-Mumbais-moribund-Metro/articleshow/40311318.cms
- ^ a b http://timesofindia.indiatimes.com/city/pune/Pre-poll-rush-to-approve-delayed-metro/articleshow/40825808.cms
- ^ http://timesofindia.indiatimes.com/City/Mumbai/Metro-III-hopes-for-speedy-nods-after-puja-today/articleshow/40875769.cms
- ^ http://www.thehindubusinessline.com/industry-and-economy/logistics/mumbai-metro3-launched-today/article6353788.ece
- ^ "Metro Line 3 - Colaba-Bandra-SEEPZ (Fully Underground)". MMRDA. Retrieved 27 March 2014.
- ^ Our Bureau (21 March 2014). "Tender for Mumbai's Metro phase 3 to be floated in July". Business Line. Retrieved 27 March 2014.
{{cite web}}
: Italic or bold markup not allowed in:|publisher=
(help) - ^ http://www.mid-day.com/articles/mumbais-metro-3-will-be-one-of-the-few-in-the-world-to-run-on-ac/15298168