Uppur Thermal Power Project

Coordinates: 9°35′05.4″N 78°54′31.0″E / 9.584833°N 78.908611°E / 9.584833; 78.908611
From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Dl2000 (talk | contribs) at 21:46, 11 July 2020 (→‎See also: rm nonexistent see-also article (WP:SEEALSO)). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Uppur Superctical Thermal Power Project
Map
Uppur Supercritical Thermal Power Project
CountryIndia
LocationRamanathapuram, Tamil Nadu
Coordinates9°35′05.4″N 78°54′31.0″E / 9.584833°N 78.908611°E / 9.584833; 78.908611
StatusUnder Construction
Construction beganMarch 2016
Construction costRs 12,655 crores
Operator(s)Tamil Nadu Generation and Distribution Corporation (TANGEDCO)
Thermal power station
Primary fuelCoal
Power generation
Nameplate capacity
  • 1,600 MW

Uppur Supercritical Thermal Power Project is located in Uppur and near Tiruvadanai, Ramanathapuram District in Tamil Nadu. The power plant is one of the coal based power plants of TANGEDCO. This project is being constructed by BHEL, L&T and Reliance Infrastructure.[1]

Construction

RIL,was awarded the Engineering, Procurement and Construction (EPC) contract in the BoP package and allied civil works, BHEL was awarded the Boiler, Turbine and Generator (BTG) contract and L&T was awarded the ‘seawater intake and outfall’ system contract.[2][3]

Materials for erection brought to the site and foundation process under progress. Foundation for two units of plant under Bharat Heavy Electricals Limited has already been completed.[4] ESP 1 & ESP 2 foundation completed and now erection activity is going on. The boiler foundation for unit 1 & 2 also completed with the efforts of BHEL Engineers. The Structural contractors have also been mobilized. The fabrication work is in full swing. Sh. R Anbarasu(GM-Projects VIII, BHEL) along with BHEL Engineer team are now making their efforts to speed-up the progress work.

Installed Capacity

Stage Unit Number Installed Capacity (MW) Date of Commissioning Status
Stage I 2x800 MW 1600 MW 2021-22 Under Constructions