Flamanville Nuclear Power Plant

From Wikipedia, the free encyclopedia
Jump to: navigation, search
Flamanville Nuclear Power Plant
Flamanville-Diélette (Manche, Fr) vue sur la centrale nucléaire.jpg
Flamanville Nuclear Power Plant is located in France
Flamanville Nuclear Power Plant
Location of Flamanville Nuclear Power Plant
Official name Centrale Nucléaire de Flamanville
Country France
Location Flamanville, Manche
Coordinates 49°32′11″N 1°52′54″W / 49.53639°N 1.88167°W / 49.53639; -1.88167Coordinates: 49°32′11″N 1°52′54″W / 49.53639°N 1.88167°W / 49.53639; -1.88167
Status Operational
Construction began 1979
Commission date December 4, 1985 (December 4, 1985)
2016 (Flamanville 3 scheduled)
Operator(s) EDF
Nuclear power station
Reactor type PWR
EPR
Reactor supplier Framatome
Areva
Power generation
Units operational 2 x 1,382 MW
Make and model Alstom
Units under const. 1 x 1,650 MW
Nameplate capacity 2,764 MW
Annual generation 17,917
Website
Areva site

The Flamanville Nuclear Power Plant is located at Flamanville, Manche, France on the Cotentin Peninsula.

It houses two pressurized water reactors (PWRs) that produce 1.3 GWe each and came into service in 1986 and 1987, respectively. It produced 18.9 TWh in 2005, which amounted to 4% of the electricity production in France. In 2006 this figure was about 3.3%.

1978 picture showing the blasting that was done to demolish the cliffs and old, under-sea iron ore mines, before the reactors were built.

In 2006, before the start of construction of unit 3, there were 671 workers regularly working at the two operational reactors.

The safety of the Flamanville plant has been questioned due to the danger of flooding of the kind experienced during the 1999 Blayais Nuclear Power Plant flood.[1]

Unit 3[edit]

Construction on a new reactor, Flamanville 3, began on 4 December 2007.[2] The new unit is an Areva European Pressurized Reactor type and is planned to have a nameplate capacity of 1,650 MWe.

EDF has previously said France's first EPR would cost €3.3 billion[2] and start commercial operations in 2012, after construction lasting 54 months.[3]

On 3 December 2012 EDF announced that the estimated costs have escalated to €8.5 billion ($11 billion), and the completion of construction is delayed to 2016.[4] The next day the Italian power company Enel announced it was relinquishing its 12.5% stake in the project, and 5 future EPRs, so would be reimbursed its project stake of €613 million plus interest.[5][6]

In November 2014 EDF announced that completion of construction was delayed to 2017 due to delays in component delivery by Areva.[7]

Flamanville Nuclear Power Plant at night
Flamanville Nuclear Power Plant at night

References[edit]

  1. ^ The great lesson France has to learn from Fukushima Deciphering Fukushima, published 2011-03-08, accessed 2012-05-08
  2. ^ a b "Construction of Flamanville EPR begins". World Nuclear News. 2007-12-04. Retrieved 2011-03-19. 
  3. ^ "Flamanville 3 concrete poured". Nuclear Engineering International. 6 December 2007. Retrieved 1 August 2011. 
  4. ^ "Le coût de l'EPR de Flamanville encore revu à la hausse". Le Monde. 3 December 2012. Retrieved 4 December 2012. 
  5. ^ "Enel Drops Participation in Flamanville EPR as Project Costs Soar by $2.6B". POWER. 6 December 2012. Retrieved 14 August 2013. 
  6. ^ "Enel and Edf Terminate their cooperation on EPR in France". Enel. 4 December 2012. Retrieved 14 August 2013. 
  7. ^ Michael Stothard (18 November 2014). "EDF in fresh delay for flagship nuclear plant". Financial Times. Retrieved 21 November 2014.