Hubco Coal Power Project, also known as CPHGC Coal Power Project, is a coal power plant project located in Hub, Balochistan Pakistan.[1]

History

[edit]

It was established by the China Power Hub Generation Company (CPHGC) under the China-Pakistan Economic Corridor (CPEC).[2]

It has an installed capacity of 1320 MW and commenced full operations on Aug 17, 2019.[2]

References

[edit]
  1. ^ Hussain, Dilawar (October 12, 2015). "Hubco's power project on track — company's CEO". DAWN.COM.
  2. ^ a b Kiani, Khaleeq (August 19, 2019). "1,320MW coal-fired Hub power plant commissioned". DAWN.COM.