Line 1
 1 
A train at Liuyuan
Overview
StatusOperational
OwnerTianjin
LocaleTianjin, China
Termini
Stations22
Service
TypeRapid transit
SystemTianjin Metro
Services1
Operator(s)Tianjin Metro Corporation
History
Opened28 December 1984 (old system)
12 June 2006 (new system)
Closed2001 to 2006
Technical
Line length26.2 km (16.28 mi)
Number of tracks2
CharacterUnderground, At-grade, & Elevated
Track gauge1,435 mm (4 ft 8+12 in)
Route map

English
李楼
Lilou
双林
Shuanglin
财经大学
Caijingdaxue
(
Economics &
Finance College
)
华山里
Huashanli
( 11 )
复兴门
Fuxingmen
陈塘庄
Chentangzhuang
土城
Tucheng
( 8 )
南楼
Nanlou
下瓦房
Xiawafang
 5 
小白楼
Xiaobailou
营口道
Yingkoudao
(Yingkou Road)
 3 
鞍山道
Anshandao
(Anshan Road)
海光寺
Haiguangsi
(Haiguang Temple)
( 7 )
二纬路
Erweilu
(Erwei Road)
西南角
Xi'nanjiao
 2 
西北角
Xibeijiao
西站
Xizhan
洪湖里
Honghuli
勤俭道
Qinjiandao
(Qinjian Road)
本溪路
Benxilu
(Benxi Road)
佳园里
Jiayuanli
瑞景新苑
Ruijingxinyuan
刘园
Liuyuan

Line 1 of the Tianjin Metro (Chinese: 天津地铁一号线; pinyin: Tiānjīn Dìtiě Yī Hào Xiàn) runs 26.2 km from the north-west to the south-east of downtown Tianjin and serves 22 stations. It started operations on 12 June 2006. The line was rebuilt from the original Tianjin Metro line, which opened in 1976, but had to close down and undergo renovations in 2001 as part of the system's modernizing project. The line's color is red.

History

Construction began in 1970. The first section, spanning 3.6 km of track and 4 stations, which are named Xinhua Road, Template:TJM stations, Template:TJM stations and Template:TJM stations stations, was completed by February 1976. The second section, with an additional 1.6 km of track and the Template:TJM stations and Template:TJM stations stations, was completed by 1980. After construction resumed, the total length was 7.4 km, with 8 stations, and service on the line began on 28 December 1984.

To cut construction costs, the authority used an abandoned canal bed to build part of the system. Thus the underground section is only 2–3 meters beneath the street surface, and was the world's shallowest metro. Years later, train frequency reduced and trains were commonly delayed. The rolling stocks themselves where dilapidated, with most seat covers torn off, and lights becoming dim. To change to a more modern and cleaner system in East Asia, a massive reconstruction, modernization and expansion plan was laid out in 2000. In preparation, the system was closed on 1 September 2001, with renovation totally started on 21 November after being delayed due to the terrorist attacks of 11 September. After introducing new rolling stocks, adding half-height platform screen doors and extending the line to Template:TJM stations, the line was completed at the end of 2005 and was re-opened on 12 June 2006.

In 2008, Template:TJM stations Station was temporarily closed for three years for the reconstruction of the Tianjin West railway station. It reopened on 1 July 2011.

In 2016, Template:TJM stations Station was closed to make way for the line's southern extension, which is expected to enter operation in 2018. The signal system was also replaced by the new ATO system, and the running stock was also overhauled.

Details

  • Coaches per train - 6.
  • Frequency - 7–8 minutes in peak hours & 15 minutes at other times.
  • Operating hours - 5:30 to 22:30.


Infrastructure

Alignment and interchanges

The line is underground between Template:TJM stations and Template:TJM stations stations, and elevated for the other five stations. All elevated stations are entirely covered by mixture of transparent & opaque corrugated sheets. The line passes through six districts, namely Beichen, Hongqiao, Nankai, Heping, Hexi and Jinnan. The whole journey takes about twelve minutes. The line is currently not linked to other lines, but interchanges to future lines will be available when the new lines enter operation.

Concourse Level

all Line 1 station concourses are equipped with a customer service center, ticket vending machines, automatic fare gates, and Shenzhen Development Bank ATMs.

Platform level

For security and other reasons, All Line 1 stations have half-high security doors installed. TVs are installed that display travel tips, advertising, alerts, and waiting time for the next train.

Opening timeline

Segment Commencement Length Station(s) Name
Xinhualu — Haiguangsi 1 January 1976[a] 2.60 km (1.62 mi) 4 (1st section)
Haiguangsi — Xi'nanjiao 1 January 1980[a] 1.84 km (1.14 mi) 2 (2nd section)
Xi'nanjiao — Xizhan 28 December 1984 2.25 km (1.40 mi) 2 (3rd section)
Xinhualu 9 October 2001 Permanently ceased operation -1 Line 1 renovation project
Yingkoudao — Xizhan 9 October 2001 Temporary ceased operation -7
Shuanglin — Yingkoudao 12 June 2006 12.3 km (7.64 mi) 9
Yingkoudao — Xizhan Reentered operation 7
Xizhan — Liuyuan 8.2 km (5.10 mi) 6
Shuanglin 28 December 2016 Temporary ceased operation -1 Eastern extension
  1. ^ a b 10 August 1980 - Initial line began operation on a trial basis.

Stations (east to west)

Line 1 drawn to scale.
Station name Connections Distance
km
Location
English Chinese
Template:TJM stations (Temporary Closed) 双林 0.00 0.00 Jinnan
Template:TJM stations 财经大学 1.61 1.61 Hexi
Template:TJM stations 华山里 1.48 3.09
Template:TJM stations 复兴门 1.33 4.42
Template:TJM stations 陈塘庄 1.23 5.65
Template:TJM stations 土城 1.59 7.24
Template:TJM stations 南楼 1.10 8.34
Template:TJM stations 下瓦房  5  1.05 9.39
Template:TJM stations 小白楼 1.45 10.84 Heping
Xinhualu (Permanently Closed) 新华路 0.71 11.55
Template:TJM stations 营口道  3  0.80 12.35
Template:TJM stations 鞍山道 0.87 13.22
Template:TJM stations 海光寺 0.93 14.15 Nankai
Template:TJM stations 二纬路 1.06 15.21
Template:TJM stations 西南角  2  0.78 15.99
Template:TJM stations 西北角 1.02 17.01 Hongqiao
Template:TJM stations 西站  6  Tianjin West railway station TXP 1.23 18.24
Template:TJM stations 洪湖里 1.66 19.90
Template:TJM stations 勤俭道 1.15 21.05
Template:TJM stations 本溪路 1.45 22.50
Template:TJM stations 佳园里 1.24 23.74 Beichen
Template:TJM stations 瑞景新苑 1.06 24.80
Template:TJM stations 刘园 1.00 25.80
Eastern extension
Station name Connections Distance
km
Location
English Chinese
Template:TJM stations 双桥河 Jinnan
Template:TJM stations 咸水沽北
Template:TJM stations 东沽路
Template:TJM stations 国展路
Template:TJM stations 北洋村
Template:TJM stations 上郭庄
Template:TJM stations 高庄子
Template:TJM stations 洪泥河东
Template:TJM stations 梨双路北
Template:TJM stations 李楼

Rolling Stock

Type Time of manufacturing Series Sets Assembly Notes
Type B 2005 - 2006 DKZ9 (Replaced) 25 Tc+M+T+M+M+Tc Manufactured by CNR Changchun Railway Vehicles
Type B 2016 Unknown 25 Tc+M+T+M+M+Tc Manufactured by CRRC