Next Generation Bi-Level Passenger Car
Silver two-story railcar
Rendering of the Next Generation Bi-Level Passenger Rail Car
ManufacturerNippon Sharyo
DesignerSumitomo Corporation
AssemblyRochelle, Illinois, United States
Family nameSuperliner
Number built4 partial shells
SuccessorSiemens Venture
Specifications
Car body constructionStainless steel
Track gauge4 ft 8+12 in (1,435 mm) standard gauge
Notes/references
[1][2]

The Next Generation Bi-Level Passenger Rail Car was a failed design of bilevel intercity railroad passenger cars that was to be built by Sumitomo, with construction subcontracted to Nippon Sharyo. The contract was awarded in 2012 with delivery scheduled between 2015 and 2018. After delays in production, a prototype car failed buff strength testing in August 2015, leading to the cancellation of the contract with Nippon Sharyo. Siemens replaced Nippon Sharyo as the construction subcontractor in late 2017 and under the new contract, Siemens Venture railcars will be delivered between 2020 and 2023 instead of the bilevel design.

The bilevel cars were designed by the Next Generation Corridor Equipment Pool Committee (NGCE) under the provisions of the Passenger Rail Investment and Improvement Act of 2008. The cars were intended to replace single-level Amfleet and Horizon cars in the Midwest and supplement the bilevel Surfliner railcar and California Car railcars in California.

History

[edit]

The Next Generation Bi-Level Passenger Rail Car was to be the third generation of a design that began with the California Car, which entered service in 1996. The California Car was derived from the design of Amtrak's successful Superliner long-distance coach, which entered service in 1979, but modified to account for use on corridor services with more frequent stops. The California Car is designed with two wide lower-level door openings per side, rather than the single narrow door of the Superliner; interior stairways are straight single flights, rather than spirals; seating for trips of at most six hours; and with total accessibility as an original criterion, rather than as an adaptation. An improved version of the California Car, the Surfliner, entered service in 2000.[3]: 582 

Caltrans and Amtrak began drafting the specification for a third generation of the design in 2006. This specification, dubbed "Corridor Car for the 21st Century" or C21, became the basis for the design work undertaken by the Next Generation Corridor Equipment Pool Committee (NGCE) under the provisions of the Passenger Rail Investment and Improvement Act of 2008 beginning in 2009.[3]: 583 

The specification encompassed three car types: a standard coach, a combination cab-baggage car, and a cafe-lounge car.[1]: 32  All three types would measure 16 feet 2 inches (4.93 m) high, 85 feet (26 m) long, and 10 feet 6 inches (3.20 m) wide. The cars were designed for low-level boarding only; the distance from the rail to the bottom step is 18 inches (460 mm).[1]: 35  The coach would seat a maximum of 89 passengers, most of them on the upper level. Seating would be 2×2, with some table seating provided. Stairs at both ends of the car provided access between levels. There would be restrooms on both levels, and a bicycle rack on the lower level.[1]: 43  The cab-baggage design would have capacity for 15 fewer passengers, with much of the lower level seating given over to checked baggage storage.[1]: 44  The cafe-lounge would have a single staircase at one end, with the galley located centrally on the upper level.[1]: 45  The car would have some passenger seating, but most space would be used for lounge seating.[1]: 34 

Caltrans, on behalf of the state coalition (California, Michigan, Missouri and Illinois), issued a request for proposal (RFP) for building cars to the new bilevel specification in April 2012. Five companies submitted final proposals: Alstom, Construcciones y Auxiliar de Ferrocarriles (CAF), Kawasaki, Siemens, and Sumitomo.[3]: 588  Caltrans awarded the contract to Sumitomo in November 2012. Sumitomo, in turn, selected Nippon Sharyo as the carbuilder for the order. The contract was for 130 cars, valued at $352 million. Eighty-eight of the cars were for the Midwestern states and 42 for California. Delivery of the new cars was scheduled for 2015–2018.[4] The 88 Midwestern cars were funded by a $220 million American Recovery and Reinvestment Act of 2009 (ARRA) grant which, by law, had to be spent by September 30, 2017.[5]: 54 [6]: 23 [7]

This ambitious schedule proved untenable. By May 2015, Caltrans acknowledged that the project was fourteen months behind schedule and replaced much of its project management team. The project slipped further that August when the new car shell failed a buff strength compression test. This failure forced a complete redesign of the car, delaying the project by at least two years. This would place delivery beyond the expiration of the ARRA funds.[6]: 17 

In November 2017, Caltrans and Sumitomo announced that Siemens would replace Nippon Sharyo as a subcontractor. Under a new contract, valued at $371 million, Siemens would deliver 137 Siemens Venture single-level cars instead of bilevel cars.[8] Cars deliveries started in mid-2020 and entered service in February 2022.[9]

See also

[edit]

References

[edit]
  1. ^ a b c d e f g Amtrak (September 20, 2012). "Specification for PRIIA Bi-Level Passenger Rail Car" (PDF). Archived from the original (PDF) on September 27, 2013. Retrieved September 2, 2017.
  2. ^ Johnston, Bob (September 4, 2015). "Nippon Sharyo prototype fails test, workers laid off". Trains. Retrieved March 20, 2022.
  3. ^ a b c Hunter, Stanton C.; Highfill, Robert C. (2013). Implementation of the Nation's First Standardized Intercity Rail Car Specification (PDF). AREMA 2013 Annual Conference. American Railway Engineering and Maintenance-of-Way Association. pp. 579–599.
  4. ^ Leaf, Brian (September 27, 2012). "Rochelle's Nippon Sharyo train car plant lands $352 mil contract". Rockford Register Star.
  5. ^ Johnston, Bob (October 2017). "Time is up". Trains. 77 (10): 48–55. ISSN 0041-0934.
  6. ^ a b Fleming, Susan A. (May 26, 2016). RAIL GRANT OVERSIGHT: Greater Adherence to Leading Practices Needed to Improve Grants Management (PDF) (Report). United States Government Accountability Office. GAO-16-544.
  7. ^ Hall, C.B. (2016). "Those Corridor Cars: Better Late than Never". Passenger Train Journal. 40 (3): 15–16. ISSN 0160-6913.
  8. ^ "Caltrans Amends Multimillion Dollar, Multi-State Railcar Contract" (Press release). Caltrans. November 8, 2017.
  9. ^ Johnson, Bob (February 2, 2022). "First Look at Siemens Venture Coaches". Trains Magazine.
[edit]