The '''Chiltern Tunnel''' is a [[High-speed rail|high-speed]] [[Tunnel|railway tunnel]] currently under construction in [[Buckinghamshire]] and [[Hertfordshire]], England, and will upon completion carry the [[High Speed 2]] (HS2) railway line under the [[Chiltern Hills]]. The twin-bore tunnels, which are {{convert|16.04|km|mi|abbr=in}} long,<ref name=":0">{{Cite web|title=Bouygues Travaux Publics - Project - HS2, High-Speed Rail Line|url=https://www.bouygues-tp.com/en/projects/hs2-high-speed-rail-line|access-date=2021-08-12|website=www.bouygues-tp.com}}</ref> will be the longest on the HS2 line.<ref name=":3">{{Cite web|title=Chiltern Tunnel|url=https://www.hs2.org.uk/building-hs2/tunnels/tunnel-drives/chiltern-tunnel/|access-date=2022-02-04|website=High Speed 2|language=en-GB}}</ref> Each tunnel will also have additional {{convert|220|m|abbr=on}} entry and {{convert|135|m|abbr=on}} exit perforated concrete portals to reduce sudden changes in air pressure and subsequent noise.<ref>{{Cite web |title=HS2 reveals noise-cancelling Chiltern Tunnel north portal design |url=https://mediacentre.hs2.org.uk/news/hs2-reveals-noise-cancelling-chiltern-tunnel-north-portal-design |access-date=2023-06-03 |website=HS2 News and Information |language=english}}</ref>
The '''Chiltern Tunnel''' is a [[High-speed rail|high-speed]] [[Tunnel|railway tunnel]] currently under construction in [[Buckinghamshire]] and [[Hertfordshire]], England, and will upon completion carry the [[High Speed 2]] (HS2) railway line under the [[Chiltern Hills]]. The twin-bore tunnels, which are {{convert|16.04|km|mi|abbr=in}} long,<ref name=":0">{{Cite web|title=Bouygues Travaux Publics - Project - HS2, High-Speed Rail Line|url=https://www.bouygues-tp.com/en/projects/hs2-high-speed-rail-line|access-date=2021-08-12|website=www.bouygues-tp.com}}</ref> will be the longest on the HS2 line.<ref name=":3">{{Cite web|title=Chiltern Tunnel|url=https://www.hs2.org.uk/building-hs2/tunnels/tunnel-drives/chiltern-tunnel/|access-date=2022-02-04|website=High Speed 2|language=en-GB}}</ref> Each tunnel will also have additional {{convert|220|m|abbr=on}} entry and {{convert|135|m|abbr=on}} exit perforated concrete portals to reduce sudden changes in air pressure and subsequent noise.<ref>{{Cite web |title=HS2 reveals noise-cancelling Chiltern Tunnel north portal design |url=https://mediacentre.hs2.org.uk/news/hs2-reveals-noise-cancelling-chiltern-tunnel-north-portal-design |access-date=2023-06-03 |website=HS2 News and Information |language=english}}</ref>


A contract for the tunnel's construction was awarded in 2017; preparatory work commenced during the following year. In May 2021, it was announced that excavation had commenced. The boring process, which is to be largely performed by a pair of [[tunnel boring machine]]s (TBMs), is advancing at an average speed of {{convert|15|m|abbr=on}} per day; it is anticipated that it will be complete in March 2024.<ref>{{Cite web|title=HS2 Corporate Plan 2021–2024|url=https://assets.hs2.org.uk/wp-content/uploads/2021/07/HS2_CorporatePlan_2021-2024-Accessibility_FINAL.pdf|url-status=live|archive-url=https://web.archive.org/web/20211221135213/https://assets.hs2.org.uk/wp-content/uploads/2021/07/HS2_CorporatePlan_2021-2024-Accessibility_FINAL.pdf |archive-date=21 December 2021 }}</ref><ref>{{Cite web |title=Sir Jonathan Thompson appointed to the HS2 Ltd Board |url=https://www.gov.uk/government/news/sir-jonathan-thompson-appointed-to-the-hs2-ltd-board |access-date=21 April 2021 |website=GOV.UK |language=en}}</ref><ref name="tunnellingstart">{{cite web |date=13 May 2021 |title=HS2 high-speed rail project begins underground tunnel |url=https://www.bbc.co.uk/news/av/uk-57093884 |url-status=live |access-date=13 May 2021 |website=BBC News|archive-url=https://web.archive.org/web/20210512232434/https://www.bbc.co.uk/news/av/uk-57093884 |archive-date=12 May 2021 }}</ref><ref name=":2">{{Cite web |last=Hakimian |first=Rob |date=15 July 2022 |title=HS2 timeline of major events to 2025 revealed |url=https://www.newcivilengineer.com/latest/hs2-timeline-of-major-events-to-2025-revealed-15-07-2022/ |access-date=16 July 2022 |website=New Civil Engineer}}</ref> {{As of|2023|5|29}}, the first TBM had excavated a total distance of {{convert|11.773|km|mi|abbr=in}}{{snd}}73% of the tunnel bore length.<ref name = progmap />
A contract for the tunnel's construction was awarded in 2017; preparatory work commenced during the following year. In May 2021, it was announced that excavation had commenced. The boring process, which is to be largely performed by a pair of [[tunnel boring machine]]s (TBMs), is advancing at an average speed of {{convert|15|m|abbr=on}} per day; it is anticipated that it will be complete in March 2024.<ref>{{Cite web|title=HS2 Corporate Plan 2021–2024|url=https://assets.hs2.org.uk/wp-content/uploads/2021/07/HS2_CorporatePlan_2021-2024-Accessibility_FINAL.pdf|url-status=live|archive-url=https://web.archive.org/web/20211221135213/https://assets.hs2.org.uk/wp-content/uploads/2021/07/HS2_CorporatePlan_2021-2024-Accessibility_FINAL.pdf |archive-date=21 December 2021 }}</ref><ref>{{Cite web |title=Sir Jonathan Thompson appointed to the HS2 Ltd Board |url=https://www.gov.uk/government/news/sir-jonathan-thompson-appointed-to-the-hs2-ltd-board |access-date=21 April 2021 |website=GOV.UK |language=en}}</ref><ref name="tunnellingstart">{{cite web |date=13 May 2021 |title=HS2 high-speed rail project begins underground tunnel |url=https://www.bbc.co.uk/news/av/uk-57093884 |url-status=live |access-date=13 May 2021 |website=BBC News|archive-url=https://web.archive.org/web/20210512232434/https://www.bbc.co.uk/news/av/uk-57093884 |archive-date=12 May 2021 }}</ref><ref name=":2">{{Cite web |last=Hakimian |first=Rob |date=15 July 2022 |title=HS2 timeline of major events to 2025 revealed |url=https://www.newcivilengineer.com/latest/hs2-timeline-of-major-events-to-2025-revealed-15-07-2022/ |access-date=16 July 2022 |website=New Civil Engineer}}</ref> {{As of|2023|7}}, the first TBM had excavated a total distance of {{convert|11.773|km|mi|abbr=in}}{{snd}}73% of the tunnel bore length.<ref name = progmap />


==History==
==History==

Revision as of 21:33, 9 July 2023

Chiltern Tunnel
Overview
LocationUnited Kingdom (Buckinghamshire, Hertfordshire)
Coordinates51°42′34″N 0°41′35″W / 51.7095°N 0.6931°W / 51.7095; -0.6931 (north portal)
OS grid reference
StatusUnder construction
SystemHigh Speed 2
CrossesChiltern Hills
StartWest Hyde
EndSouth Heath
Operation
Work begun13 May 2021
TrafficRail
Technical
Length16.04 km (9.97 miles)
No. of tracks2
Track gauge1,435 mm (4 ft 8+12 in)
Electrified25 kV 50 Hz AC
Operating speed320 km/h (200 mph)
Width9.1 metres (30 ft)

The Chiltern Tunnel is a high-speed railway tunnel currently under construction in Buckinghamshire and Hertfordshire, England, and will upon completion carry the High Speed 2 (HS2) railway line under the Chiltern Hills. The twin-bore tunnels, which are 16.04 km (9.97 miles) long,[1] will be the longest on the HS2 line.[2] Each tunnel will also have additional 220 m (720 ft) entry and 135 m (443 ft) exit perforated concrete portals to reduce sudden changes in air pressure and subsequent noise.[3]

A contract for the tunnel's construction was awarded in 2017; preparatory work commenced during the following year. In May 2021, it was announced that excavation had commenced. The boring process, which is to be largely performed by a pair of tunnel boring machines (TBMs), is advancing at an average speed of 15 m (49 ft) per day; it is anticipated that it will be complete in March 2024.[4][5][6][7] As of July 2023, the first TBM had excavated a total distance of 11.773 km (7.315 miles) – 73% of the tunnel bore length.[8]

History

The construction of the High Speed 2 (HS2) railway is to involve numerous major civil engineering works along its intended route.[9] Construction periodical New Civil Engineer has described the Chiltern Hills as "HS2’s biggest and potentially most challenging site". It has been anticipated that, of the 102 km (63 miles) of tunnels that are to be bored to accommodate the line, around 16 km (9.9 miles) will be bored for the Chiltern tunnel alone.[9]

The design of the Chiltern tunnel has been subject to changes during the planning stages of the project. During August 2015, it was announced that the tunnels would be extended 2.6 km (1.6 miles) north; this revision has allowed for the replacement of a separate planned cut-and-cover tunnel, as well as avoiding the destruction of around 12 hectares (30 acres) of woodland such as Farthings Wood.[10][11] During 2017, Contract C1 (Central 1), which covers the 21.6km section of the line that the Chiltern tunnels comes within, was awarded to the Align JV joint venture, comprising Bouygues Travaux Publics, Sir Robert McAlpine and VolkerFitzpatrick.[12] The two tunnel boring machines were supplied by Herrenknecht[2] and were delivered to the site in December 2020.[13]

Design

The basic configuration of the Chiltern tunnel will consist of a pair of parallel bores, which are to be excavated by a pair of tunnel boring machines (TBMs).[9] Each TBM weighs around 2,000 tonnes, has a length of 170 m (560 ft), and has been specially customised to suit the local geology, which primarily consists of chalk and flint. Staff are conveyed between the surface and the TBM using people carriers, which will have up to a one-hour transit time towards the later years of the boring. While both TBMs are intended to be operational simultaneously throughout the majority of the work, due to sensitivities surrounding the M25 motorway, only one TBM will be active at a time while within close proximity to this key trunk route.[9]

The southern entrance to the tunnels is aligned with the nearby Colne Valley Viaduct and is near the M25. The pair of tunnels will be 16.04 km (9.97 miles) long, with the northern portal near South Heath. At their deepest point, they will be 90 m (300 ft) below ground level; the internal diameter of each bore will be 9.1 m (30 ft).[14] The completed tunnel will have a total of forty cross passages linking the two separate bores[15] and five shafts which will be used for both ventilation and emergency access purposes; these are located (in order from South to North) at Chalfont St Peter,[16] Chalfont St Giles,[17][18] Amersham,[19] Little Missenden[20] and Chesham Road[21] - the latter of which is just an intervention shaft for emergencies. These vents are all to be fitted with headhouses, produced through engagement with both the Chilterns AONB Review Group and Buckinghamshire Council. The surface elements of the St Giles shaft have been intentionally disguised as agricultural buildings.[22] The initial design of the Amersham vent shaft was modified after being criticised due to its design being reportedly out of keeping with the location.[23][24] After several iterations the design is at its final approval stage.[25]

Construction

In July 2020, work was completed on a 17 m (56 feet) high headwall at the southern end, at 51°36′42″N 0°31′27″W / 51.6117°N 0.5242°W / 51.6117; -0.5242 (HS2 Chiltern Tunnel Portal Southern Headwall), close to the M25 motorway. To accommodate workers during the construction phase, a temporary facility containing accommodation and various amenities has been constructed on site; this site will also be used to support the construction of the nearby Colne Valley Viaduct as well.[9][12]

During September 2020, final preparations for the arrival of the first of the two TBMs were made,[26][27] and both arrived on site in December that year.[13] During March 2021, the first section of fibre-reinforced concrete tunnel lining was cast; this is produced onsite at a purpose-built facility near to the southern portal, which is capable of manufacturing up to 49 sections at a time.[28] A total of 56,000 precisely-engineered sections will be required to complete each tunnel.[9]

Excavation commenced on 13 May 2021, with completion estimated around March 2024.[6][29][7] During the following month, it was reported that the first TBM, which was being operated around the clock, had been advancing at a typical speed of 15 m (49 ft) per day. Each TBM is operated by a crew of 17 working in 12-hour shifts, while surface logistics and support for the boring work is provided by over 100 people on the surface.[9] During June 2021, the second TBM commenced boring as well.[30]

The first stage of the drive (from the south portal to the Chalfont St Peter ventilation shaft) was completed in March 2022,[31] and the first of the cross passages between the main running tunnels were completed in August that year.[32] The Chalfont St Giles ventilation shaft was reached in October 2022.[33]

The chalk that has been excavated during the boring of the tunnels is to be used to create a nature reserve covering 127 hectares (310 acres) in the vicinity of the southern portals; for this purpose, measures for the temporary storage and treatment of up to 3,000,000 cubic metres (110,000,000 cu ft) of chalk slurry were provisioned onsite prior to excavation commencing.[12][34][35][36] Approval for this scheme was issued in May 2021.[37]

Progress

As of 4 July 2023, TBM Florence, the first machine to be launched in May 2021, had progressed a distance of 11.773 km (7.315 miles) from the south portal – 73% of the bore length.[8] TBM Cecilia, the second machine to be launched in June 2021, had completed 11.577 km (7.194 miles) – 72% of the bore length.[8] Both TBMs are currently on the west side of the Buckinghamshire town of Amersham, having passed under the Shardeloes country house estate, close to Little Missenden.[8]

References

  1. ^ "Bouygues Travaux Publics - Project - HS2, High-Speed Rail Line". www.bouygues-tp.com. Retrieved 12 August 2021.
  2. ^ a b "Chiltern Tunnel". High Speed 2. Retrieved 4 February 2022.
  3. ^ "HS2 reveals noise-cancelling Chiltern Tunnel north portal design". HS2 News and Information. Retrieved 3 June 2023.
  4. ^ "HS2 Corporate Plan 2021–2024" (PDF). Archived (PDF) from the original on 21 December 2021.
  5. ^ "Sir Jonathan Thompson appointed to the HS2 Ltd Board". GOV.UK. Retrieved 21 April 2021.
  6. ^ a b "HS2 high-speed rail project begins underground tunnel". BBC News. 13 May 2021. Archived from the original on 12 May 2021. Retrieved 13 May 2021.
  7. ^ a b Hakimian, Rob (15 July 2022). "HS2 timeline of major events to 2025 revealed". New Civil Engineer. Retrieved 16 July 2022.
  8. ^ a b c d "HS2: In your area map". HS2 Ltd. Retrieved 9 July 2023.
  9. ^ a b c d e f g Horgan, Rob (14 June 2021). "The reality of working on HS2's biggest construction site". newcivilengineer.com.
  10. ^ "HS2 confirms Chilterns tunnel extension". Infrastructure Intelligence. Retrieved 19 March 2021.
  11. ^ A., Evans (28 May 2015). "High Speed Rail in the Chilterns Part 2: Chiltern Long Tunnel Proposal" (PDF). gov.uk.
  12. ^ a b c "Colne Valley Viaduct – HS2's largest bridge". railengineer.co.uk. 7 June 2021.
  13. ^ a b "Work on longest tunnels set to begin". Modern Railways. 17 March 2021. Retrieved 16 July 2022.
  14. ^ "The HS2 Tunnel Boring Machines (TBMs)". High Speed 2. Retrieved 20 March 2021.
  15. ^ "Design of Chiltern Tunnel and ventilation shaft interfaces". High Speed 2. 17 September 2020. Retrieved 17 August 2022.
  16. ^ "Chalfont St Peter ventilation shaft and headhouse". High Speed 2. 6 October 2021. Retrieved 5 July 2022.
  17. ^ "Chalfont St Giles ventilation shaft and headhouse". High Speed 2. 15 September 2021. Retrieved 5 July 2022.
  18. ^ "HS2's Chiltern tunnel headhouse vent shaft gains planning approval". Global Railway Review. Retrieved 19 March 2021.
  19. ^ "HS2: Images show new design for ventilation shaft for tunnel". BBC News. 6 July 2022. Retrieved 6 July 2022.
  20. ^ Evans, A (28 May 2015). "High Speed Rail in the Chilterns Part 1: General Long Tunnel Requirements" (PDF). HS2 Ltd. Retrieved 5 July 2022.
  21. ^ "Chesham Road intervention shaft". High Speed 2. 24 March 2022. Retrieved 5 July 2022.
  22. ^ Bamford, Thomas (5 February 2021). "HS2 reveals Chilterns 'barn design' vent shaft for Chalfont St Giles". bucksherald.co.uk.
  23. ^ "HS2 reveals designs for tunnel vent shaft - in the middle of busy junction".
  24. ^ "Council warns Amersham HS2 vent shaft plans are 'totally unacceptable'". 22 May 2021.
  25. ^ "HS2 reveals updated designs for Amersham vent shaft headhouse".
  26. ^ "Progress at Chiltern tunnel site as HS2 prepares for arrival of first tunnelling machines". Archived from the original on 16 September 2020. Retrieved 30 July 2020.
  27. ^ "Giant machines for HS2's Chilterns tunnels unveiled". BBC News. 11 August 2020.
  28. ^ "HS2 Casts First of 112,000 Chiltern Tunnel Wall Segments". Railway-News. 19 March 2021. Retrieved 19 March 2021.
  29. ^ "Work begins to create a tunnel through the Chilterns for new HS2 rail line". itv.com. 13 May 2021.
  30. ^ Kajastie, Nia (1 July 2021). "Second HS2 tunnelling machine starts digging under the Chilterns". geplus.co.uk.
  31. ^ "HS2 tunnelling machines reach Chalfont St Peter ventilation shaft". High Speed 2. 14 March 2022. Retrieved 17 August 2022.
  32. ^ "HS2 completes first tunnel cross passages". RailUK. 22 August 2022. Retrieved 22 August 2022.
  33. ^ "HS2 Chiltern tunnel - 'Florence' and 'Cecilia' reach 4 mile point at Chalfont St Giles". RailUK. 10 October 2022. Retrieved 11 October 2022.
  34. ^ "HS2 to 'rewild' 127 hectares around its 10-mile Chilterns tunnel". The Guardian. 3 March 2021. Retrieved 19 March 2021.
  35. ^ Horgan, Rob (27 April 2021). "How HS2 plans to reuse chalk slurry from Chilterns tunnel to 'rewild' the Colne Valley". newcivilengineer.com.
  36. ^ "HS2 celebrates milestone in Chiltern grassland transformation". RailUK. 8 September 2022. Retrieved 11 September 2022.
  37. ^ "Green light for HS2's ambitious Chiltern tunnel chalk grassland project". railpro.co.uk. 21 June 2021.