Mumbai Metro Green Line 11 Extension
Overview
Other name(s)Bhakti Park (Wadala) to CSMT Metro
StatusApproved
OwnerMumbai Metropolitan Region Development Authority
Line numberMetro Line 11
LocaleMumbai, Maharashtra, India

Start = Anik Bus Depot End

SPM Chowk
Stations10
Service
TypeMetro
SystemMumbai Metro
Operator(s)Mumbai Metro
Depot(s)Owale & Gaimukh
Technical
Line length12.68 km (7.88 mi)
Number of tracks2
Character2 Elevated , 8 Underground
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Highest elevation3.90 m (12.8 ft)
Route map

Line 11
to Line 4
0.0000
Bhakti Park (Wadala)
on Line 1 (Mumbai Monorail)
1.9720
Ganesh Nagar
2.6399
BPT Hospital
5.0289
Sewri on Harbour line
5.8800
Hay Bunder
6.9044
Coal Bunder
8.0869
Darukhana
9.0644
Wadi Bunder
10.2108
Clock Tower
11.1001
Carnac Bunder
Indira Dock of
Mumbai Port Trust
on
Central line
and Harbour line
12.6846
CSMT on Line 3

Green Line 11 (Extension) of the Mumbai Metro is part of the metro system for the city of Mumbai, India. The project is expected to be completed around 2030.[1]

The 12.68 km (7.9 mi) line from Wadala–CSMT is estimated to cost ₹8,739 crores. The Government of Maharashtra is keen to implement the Master Plan Corridors recommended by DMRC on a fast track mode and to complete them in the next 3 to 4 years.[when?] To start with, it is decided to take up the task of updating of DPRs[clarification needed] and also preparation of new DPRs for the following potential elevated metro corridors. In January 2023, the government[which?] ordered that the rights to execute Line 11's construction be handed over to MMRCL (Mumbai Metro Rail Corporation), which further tweaked its alignment from an existing route (Wadala-CST) to a new route (Anik Bus Depot - Shyama Prasad Mukherjee Circle) passing through localities such as Nagpada Junction, Byculla, Bhendi Bazaar, and Crawford Market.[citation needed]

Stations

[edit]

Initially, a total of ten Stations were planned for this extension. Out of ten stations, eight are underground and two are elevated. The concourse of all elevated stations is proposed along the roads with sufficient right of way. The stations accommodate the passengers from the eastern port area of Mumbai. The average inter-station distance is 1.27 km (0.79 mi) approximately varying from 0.85 km (0.53 mi) to 2.1 km (1.3 mi) depending upon the site, operational and traffic constraints.[citation needed]

Metro line 11
Green Line 11
# Station Name Status Connections Layout
English Marathi
1 Anik Nagar Bus Depot अणिक नगर बस आगार Proposed Line 4 (Under Construction) Elevated
2 Bhakti Park (Wadala) भक्ति पार्क (वडाळा) Proposed Line 4 (Under Construction) Elevated
3 CGS Colony सीजीएस कॉलनी Proposed None To Be Decided
4 Ganesh Nagar गणेश नगर Proposed None To Be Decided
5 BPT Hospital बीपीटी हॉस्पिटल Proposed None To Be Decided
6 Sewri शिवडी Proposed None To Be Decided
7 Hay Bunder गवत बंदर Proposed None To Be Decided
8 Coal Bunder कोळसा बंदर Proposed None To Be Decided
9 Reay Road रे रोड Proposed None To Be Decided
10 Byculla भायखळा Proposed None To Be Decided
11 Nagpada Junction नागपाडा जंक्शन Proposed None To Be Decided
12 Bhendi Bazaar भेंडी बाजार Proposed None To Be Decided
13 Crawford Market क्रॉफर्ड मार्केट Proposed None To Be Decided
14 Chhatrapati Shivaji Maharaj Terminus छत्रपती शिवाजी महाराज टर्मिनस Proposed Line 3 (Under Construction) To Be Decided
15 Horniman Circle हॉर्निमन सर्कल Proposed None To Be Decided
16 SPM Circle एसपीएम सर्कल Proposed None To Be Decided

References

[edit]
  1. ^ Mehta, Manthank (17 February 2024). "Mumbai underground new metro to link Byculla, Crawford, Fort and Gateway". Times of India. Retrieved 24 December 2024.