Jump to content

Simplon Tunnel

Coordinates: 46°19′25″N 8°00′11″E / 46.32361°N 8.00306°E / 46.32361; 8.00306
From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Zackmann08 (talk | contribs) at 18:04, 20 November 2016 (Fixing infobox not to use deprecated parameters). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Simplon Tunnel
Simplon Tunnel from the Italian side
Overview
Official nameTemplate:Lang-de, Template:Lang-it
LineSimplon line, (Lötschberg railway line)
LocationTraversing the Lepontine Alps between Switzerland and Italy
Coordinates46°19′26″N 8°00′25″E / 46.324°N 8.007°E / 46.324; 8.007 (Simplon Tunnel, northern portal)46°12′25″N 8°12′04″E / 46.207°N 8.201°E / 46.207; 8.201 (Simplon Tunnel, southern portal)
SystemSwiss Federal Railways (SBB CFF FFS)
CrossesLepontine Alps (Wasenhorn massif)
StartBrig, canton of Valais, Switzerland 683 m (2,241 ft)
EndIselle di Trasquera, Piedmont, Italy 633 m (2,077 ft)
Operation
Work begun22 November 1898 (east tunnel), 1912 (west tunnel)
Opened19 May 1906 (east tunnel), 1921 (west tunnel)
OwnerSBB CFF FFS
OperatorSBB CFF FFS
TrafficRailway
CharacterPassenger, Freight, Car Transport
Vehicles per dayPassenger: , Freight: unknown
Technical
Length19.803 km (12.305 mi) (east tunnel), 19.823 km (12.317 mi) (west tunnel)
No. of tracksTwo single-track tubes
Track gauge1,435 mm (4 ft 8+12 in) (standard gauge)
Electrifiedsince 1 June 1906, 15 kV 16.7 Hz since 2 March 1930
Highest elevation705 m (2,313 ft)
Lowest elevation633 m (2,077 ft) (south portal)
Grade2–7 ‰

length
in m
Visp
(MGBSBB)
Brig
(MGBSBB)
19,803
Iselle tunnel
628
Iselle di Trasquera
Trasquera tunnel
1,712
2,966
Varzo
Varzo tunnel
81
Mognatta tunnel
422
Gabbio Mollo tunnel
568
San Giovanni tunnel
425
Rio Confinale tunnel
51
Rio Rido–Preglia tunnel
2,266
Preglia
Domodossola
length
in m

The Simplon Tunnel is a railway tunnel that connects Brig, Switzerland and Domodossola, Italy, through the Alps, but not under Simplon Pass itself. It is straight except for short curves at either end.[1] It actually consists of two single-track tunnels built nearly 20 years apart. The first to be opened is 19,803 m (64,970 ft) long; the second is 19,824 m (65,039 ft) long, making it the longest railway tunnel in the world until the opening of the Daishimizu Tunnel in 1982.

Work on the first tube of the Simplon Tunnel commenced in 1898. The Italian king Victor Emmanuel III of Italy and the president of the National Council of Switzerland Ludwig Forrer opened the tunnel at Brig on 10 May 1906. The builders of the tunnel were Hermann Häustler and Hugo von Kager. Work on the second tube of the tunnel started in 1912 and it was opened in 1921.

History

Simplon Tunnel, 1906

Shortly after the opening of the first railway in Switzerland, each region began to favour a separate north-south link through the Alps towards Italy. Eastern Switzerland supported a line through the Splügen Pass or the Lukmanier Pass, Central Switzerland and Zürich favoured the Gotthard Pass and Western Switzerland supported the Simplon route.

In 1871 the first line was completed through the Alps, connecting Italy and France with the Fréjus Rail Tunnel.

On 1 July 1878, the Simplon Railway Company (French: Compagnie du chemin de fer du Simplon, S) was created to promote the project; it merged in 1881 with the company Western Swiss Railways (French: Chemins de Fer de la Suisse Occidentale, SO) to create the Western Switzerland–Simplon Company (French: Compagnie de la Suisse Occidentale et du Simplon, SOS). The French financiers of the SOS were able to secure finance for the tunnel in 1886. The company considered 31 proposals and selected one that involved the construction of a tunnel from Glis to Gondo, which would have been fully in Switzerland. From Gondo it would have continued on a ramp through the Divedro valley down to Domodossola.

At a Swiss-Italian conference held in July 1889, it was agreed, however, to build a nearly-20-kilometre-long base tunnel through the territory of both states. In order to secure credit for the tunnel, the SOS joined with the Jura–Bern–Luzern Railway to create the Jura–Simplon Railway (French: Compagnie du Jura–Simplon, SOS).

The participation of the Swiss government led to the signing of a treaty with Italy on 25 November 1895 concerning the construction and operation of a railway through the Simplon from Brig to Domodossola by the Jura–Simplon Railway. The route of the tunnel was determined by military considerations so that the state border between the two countries was in the middle of the tunnel, allowing either country to block the tunnel in the event of war.

On 1 May 1903, the Jura-Simplon Railway was nationalized and integrated into the network of the Swiss Federal Railways (SBB), which completed construction of the tunnel.

Construction

The construction of the tunnel was carried out by the Hamburg engineering company Brandt & Brandau, of Karl Brandau and Alfred Brandt. On average, 3,000 people a day worked on the site. They were mostly Italians, who suffered under very poor working conditions: 67 workers were killed in accidents; many died later of diseases. During the work, there were strikes, which led to the intervention of vigilantes and the Swiss army.

With up to 2,135 m (7,005 ft) of rock over the tunnel, temperatures of up to 42 °C (108 °F) were expected and a new building method was developed. In addition to the single-line main tunnel, a parallel tunnel was built, with the tunnel centres separated by 17 m, through which pipes supplied fresh air to the builders in the main tunnel. It was envisaged that the parallel tunnel could be upgraded to a second running tunnel when required. The first Simplon Tunnel (19,803 m (64,970 ft) in length) was built almost straight, with only short curves at the two tunnel portals.

On 24 February 1905, the two halves of the tunnel came together. They were out of alignment by only 202 mm (8.0 in) horizontally and 87 mm (3.4 in) vertically. Construction time was 7½ years, rather than 5½ years, due to problems such as water inflows and strikes.

Art Nouveau Silver Medallion by Giannino Castiglioni for the Milan International Exhibition 1906. The South Portal of the Simplon Tunnel is on the obverse.

Electrification and operation

Old poster for the train between Paris and Milan (from 1908, two years after opening, depicting two tracks, even though it got its second tunnel only in 1912).

Operations commenced through the tunnel on 19 May 1906. Because of its length among other things, it has operated with electric traction rather than steam from the beginning. The official decision to use electricity was made only half a year before its opening by the then-still-new SBB. Brown, Boveri & Cie (BBC) were commissioned to carry out the electrification. They decided in 1904 to use the three-phase system being introduced in Italy, with a three-phase power supply of 3,400 volts at 15.8 Hz[2] using two overhead wires with the track acting as the third conductor. BBC had no electric locomotives and initially acquired three locomotives built for the Ferrovia Alta Valtellina—the owner of the lines from Colico to Chiavenna and Tirano, which had been electrified with this system in 1901 and 1902[2]—from their owner, the Rete Adriatica railway company. These three locomotives hauled all traffic through the tunnel until 1908. On 2 March 1930, the Simplon tunnel was converted to 15 kV, 16.7 Hz AC (single-phase).

Expansion

Between 1912 and 1921, the 19,823-metre-long second tube, known as Simplon II, was built. On 7 January 1922 the northern section from the north portal to the 500-metre-long passing loop in the middle of the tunnel was brought into operation, followed on 16 October 1922 by the southern section from the passing loop to the south portal.

Second World War

During the Second World War, on both sides of the border there were preparations for the possible detonation of the tunnels. The explosives attached to the tunnel on the Swiss section were not removed until 2001.[citation needed] In Italy, the German army planned, as part of its 1945 withdrawal, to blow up the tunnel, but were thwarted by Italian partisans with the help of two Swiss officials and Austrian deserters.

Present and Future

Car-carrying shuttle trains

There is a car-carrying shuttle between Brig and Iselle di Trasquera, which provides a 20-minute train journey as an alternative to driving over the Simplon Pass. The service began on 1 December 1959. As roads over the Simplon Pass steadily improved throughout the 1970s and 1980s the tunnel's shuttle schedule was cut back, then ended altogether on 3 January 1993. Almost twelve years later, on 12 December 2004, the car shuttle service began again and now runs about every 90 minutes.

Piggyback transport

In the early 1990s, a project to implement the rolling highway system of piggyback operations for transalpine freight on the Lötschberg–Simplon axis was implemented. Such operations were possible under the existing profile of the Simplon Tunnel but capacity would have been heavily restricted. Its height was too low to carry trucks at the permitted maximum corner height of four metres. Therefore, the clearance in the tunnel was increased by lowering the rail line. The work to lower the tunnel's trackbed began in 1995 and lasted eight years. At the same time, the tunnel vault was rehabilitated, while the drainage tunnel was rebuilt. A total of 200,000 m³ of rock was removed with pneumatic breakers.

In addition, a new railway electrification system was installed using overhead electric rail instead of the tensioned cable normally used for overhead electrification so that the required 4.90-metre height clearance could be achieved. In the late 1980s, a one kilometre (0.62 miles) long overhead electric rail had been tested at 160 km/h (99 mph). Before this experiment, trains running under overhead electric rails in Switzerland had been limited to 110 km/h (68 mph) and internationally to 80 km/h (50 mph).[3]

Rail operations with restrictions were maintained during the entire construction period.

Expansion of access routes

In order to expand the Lötschberg-Simplon axis into a powerful transit axis, various extensions to the access lines (from Bern and Lausanne in the north and from Novara and Milan in the south) have been made in recent years and decades. The largest projects have dealt with the northern access from Basel-Bern via Lötschberg. Between 1976 and 2007 there were three major transformations. First, the remaining single-track line between Spiez and Brig was dualled. Later, adjustments were made to the tunnel profile for piggyback traffic; in places only widening one track was possible. Finally, in 2007, the Lötschberg base tunnel opened, although part of this is still single in order to save costs.

Clearances were also raised for the piggyback traffic on the Italian side as well on the Simplon southern approach. Here, too, for financial reasons, at times only one line was cleared for the rolling highway. South of Domodossola, the single line to Novara via Lake Orta was electrified and modernized.

The classic approach to the Simplon from Paris and Lausanne—less important for today's transit traffic—was upgraded in the context of a nationwide rail upgrading project, Rail 2000, between 1985 and 2004. Further adjustments are proposed. In November 2004, the 7 km-long new line between Salgesch and Leuk in the Rhone Valley was completed to replace the last single-track bottleneck on the route. Under the ZEB ("Future rail development projects") package, the maximum speed on the long straight sections of the Rhone valley lines will be increased from 160 to 200 km/h (99 to 124 mph).

2011 fire

On 9 June 2011, a 300 m (1,000 ft) section of the Simplon II tunnel's roof was seriously damaged when a northbound BLS freight train suffered a fire and was stopped 3 km into the tunnel. The temperature exceeded 800 °C (1,500 °F) and took more than two weeks to cool back to normal. By agreement all repairs to the tunnels are the responsibility of the SBB, which expected to reopen the tunnel in December 2011. The other tunnel remained in service.[4]

Repair work was completed in November 2011.[5]

Facts and figures

  • Length of tunnel I: 19,803 m (12.305 mi)
  • Length of tunnel II: 19,823 m (12.317 mi)
  • Elevation at north portal, Brig: 685.80 m (2,250.0 ft)
  • Elevation at crest of the tunnel: 704.98 m (2,312.9 ft)
  • Elevation at south portal, Iselle: 633.48 m (2,078.3 ft)
  • Gradient on north side: 0.2%
  • Gradient on south side: 0.7% ( 1 in 143) [1]
  • Maximum rock overlay: 2,200 m (7,200 ft) (below the Tunnelspitz of the Wasenhorn massif
  • Start of construction on north side: 22 November 1898
  • Start of construction of south side: 21 December 1898
  • Breakthrough: 24 February 1905
  • Inauguration: 19 May 1906
  • First electrical operation: 1 June 1906

Spiral tunnel

On the rail line north from Domodossola prior to the Simplon tunnels is the 2,968-metre (9,738 ft) "Varzo Spiral Tunnel", probably the longest spiral tunnel in the world. See the route diagram at the start of this subject.

In the 1957 novel From Russia, with Love by Ian Fleming, protagonist James Bond fights his enemy, SMERSH agent Donovan Grant, eventually killing him, while passing through the Simplon Tunnel on the Orient Express.

Notes

  1. ^ a b "THE SIMPLON TUNNEL". The Capricornian. Rockhampton, Qld: National Library of Australia. 15 October 1904. p. 21. Retrieved 19 March 2013.
  2. ^ a b Kalla-Bishop, P. M. (1971). Italian Railways. Newton Abbott, Devon, England: David & Charles. p. 98.
  3. ^ "Erfolgreiche Stromschienenversuche im Simplontunnel (Successful track trials in the Simplon tunnel)". Die Bundesbahn (in German) (3). Darmstadt: 268. 1989. ISSN 0007-5876.
  4. ^ "Simplon badly damaged by fire". Modern Railways. Ian Allan. October 2011. p. 81.
  5. ^ http://www.uic.org/com/article/switzerland-cleanup-and-repair?page=thickbox_enews

References

  • Michel Delaloye (Hrsg.): Simplon, histoire, géologie, minéralogie. Ed. Fondation Bernard et Suzanne Tissières, Martigny 2005. ISBN 2-9700343-2-8 (in German)
  • Frank Garbely: Bau des Simplontunnels. Die Streiks! Unia, Oberwallis 2006 (in German)
  • Thomas Köppel, Stefan Haas (Hrsg.): Simplon – 100 Jahre Simplontunnel. AS-Verlag, Zürich 2006. ISBN 3-909111-26-2
  • Wolfgang Mock: Simplon. Tisch 7 Verlagsgesellschaft, Köln 2005. ISBN 3-938476-09-5 (in German)
  • M. Rosenmund: Über die Anlage des Simplontunnels und dessen Absteckung, in: Jahresberichte der Geographisch-Ethnographischen Gesellschaft in Zürich, Band Band 5 (1904–1905), S. 71ff. (Digitalisat) (in German)
  • Hansrudolf Schwabe, Alex Amstein: 3 x 50 Jahre. Schweizer Eisenbahnen in Vergangenheit, Gegenwart und Zukunft. Pharos-Verlag, Basel 1997. ISBN 3-7230-0235-8 (in German)
  • Georges Tscherrig: 100 Jahre Simplontunnel. 2. Auflage. Rotten, Visp 2006. ISBN 3-907624-68-8 (in German)
  • Enzyklopädie des Eisenbahnwesens. Bd 9. Urban & Schwarzenberg, Berlin 1921 Directmedia Publishing, Berlin 2007 (Repr.), S.68–72. ISBN 3-89853-562-2 (in German)
Records
Preceded by Longest tunnel
1906–1982
Succeeded by

46°19′25″N 8°00′11″E / 46.32361°N 8.00306°E / 46.32361; 8.00306