New South Wales D set
D set | |
---|---|
In service | 2022 (expected)[1] |
Manufacturer | Hyundai Rotem |
Built at | Changwon, South Korea |
Replaced |
|
Constructed | 2019–present |
Entered service | December 2022 (expected)[1] |
Number under construction | Total delivery of 610 carriages (61 4-car sets and 61 6-car sets) |
Formation |
|
Fleet numbers |
|
Operators | NSW TrainLink |
Depots | Kangy Angy Maintenance Centre |
Lines served | |
Specifications | |
Car body construction | Stainless steel |
Train length |
|
Car length |
|
Width | 3,034 mm (9 ft 11+1⁄2 in) |
Height | 4,402 mm (14 ft 5+1⁄4 in) |
Doors | Plug-style, 2 per side |
Maximum speed | 160 km/h (99 mph) |
Weight |
|
Traction system | Mitsubishi SiC–VVVF[2] |
Traction motors | 3-phase AC induction motor[2] |
Acceleration | 0.8 m/s2 (2.6 ft/s2) |
Deceleration | 1.01 m/s2 (3.3 ft/s2) (service) 1.1 m/s2 (3.6 ft/s2) (emergency) |
Electric system(s) | 1,500 V DC (nominal) from overhead catenary |
Current collector(s) | Pantograph |
UIC classification |
|
Coupling system | Dellner |
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge |
The NSW TrainLink D sets, also referred to as the Mariyung trains, are a class of electric multiple units being built to replace NSW TrainLink's Intercity electric multiple unit fleet, slated to replace the entire V set fleet and allow the H sets to be reallocated to Sydney suburban services. The trains will operate on services from Sydney to Newcastle, Lithgow and Kiama.
The first trains were delivered in December 2019, and are expected to enter service by December 2022.[1]
History
In May 2014, the Government of New South Wales announced its intention to purchase new carriages for the NSW TrainLink Intercity network. The new trains will replace the V sets and allow the H sets to be cascaded to Sydney Trains services.[3][4]
In August 2014, expressions of interest from manufacturers were called for.[5][6] The following parties responded:[7][8]
- Alstom
- Bombardier Transportation
- CAF
- Downer Rail / CNR Changchun
- Hyundai Rotem
- Stadler Rail
- UGL Rail / Mitsubishi Electric / CSR Corporation
In July 2015, the government announced that Alstom, Downer/Changchun, Stadler, and UGL/Mitsubishi Electric/CSR had been shortlisted to tender.[9] Following the merger of CSR and the parent company of Changchun Railway Vehicles, Hyundai Rotem replaced CSR as a partner in the UGL/Mitsubishi Electric consortium.[10] The consortia provided two variants of their designs - a longer train and shorter train.[10] The Hyundai Rotem/UGL/Mitsubishi Electric consortium was announced as the successful bidder in August 2016.[11][12] The companies formed a joint venture called RailConnect to manage the project.[13] The trains are being built by Hyundai Rotem's Changwon factory in South Korea.[14]
The initial contract covered the supply and maintenance of the 512 carriages which would consist of 77 4-car trains and 34 6-car trains, as well as the construction of the Kangy Angy Maintenance Centre.[9][15][16] which was completed in August 2020.[17] The maintenance contract runs for fifteen years from the delivery of the first train with an option for a five-year extension.[14] In February 2019, a further 42 carriages were ordered to extend 21 of the 77 4-car trains into 6-car trains to allow for more 10-car train operations especially on the South Coast line during peak hour.[18]
A contract was let to Downer EDI to make modifications and upgrades to existing rail infrastructure across the electrified network to accommodate the new fleet.[19] Platform extensions at multiple stations were also required to accommodate 10-car trains.
The first two 10-carriage trains were delivered in December 2019 and testing started the following month.[4][20]
During early ordering stages, the trains were simply referred to as the New Intercity Fleet. In April 2021, the name Mariyung, a Darug word for emu, was officially designated for the fleet.[21]
In July 2021, the Mariyung fleet received its final approval to carry passengers from the independent Office of the National Rail Safety Regulator and would enter service "as soon as possible". At the time, 16 trains were being tested on the network and 8 of which were ready to progressively enter passenger service.[22]
In September 2021, 56 additional carriages were ordered, bringing the total number of carriages to 610, meaning that there would be 61 of both the 4 car and 6 car variants.[23]
Debates and criticism
Proportions
In 2015 the project reached a $1.1B blowout due to modifications that were required for the design of the train, changing proportions from almost identical to the V sets to the standard suburban double decker proportions. This was criticised by Shadow Transport Minister Ryan Park as "a very expensive mistake".[24]
In October 2016 it was announced that the D sets would be 3,034 mm (9 ft 11.4 in) wide, wider than the 2,900 mm (9 ft 6 in) wide V sets. This required several sections of the Blue Mountains line to be cleared between Springwood, Katoomba and Lithgow, including the heritage listed Ten Tunnels Deviation, as well as Linden and Warrimoo stations being too short to accommodate the trains.[25] Labor MP Trish Doyle accused the Baird government of jumping "head-first into a project without actually running the measuring tape over the narrowest point the trains have to pass through", going on to say that "Instead of buying 'off-the-shelf' designs, they should have brought the project in-house to the experts at Railcorp and designed a new train with our local conditions in mind from the outset, The Minister [Andrew Constance] hasn't done his homework, and after boasting about getting a cheap deal on new trains, we now discover that the trains won't actually fit down the line. You couldn't make this stuff up."
Work started on clearing the line in 2017, with Labor MP Jodi McKay saying the amount of work needed to make the line capable of handling the new trains was "astonishing."[26]
Union battle and safety concerns
In 2018 Gladys Berejiklian would announce that the trains would have a maximum of 2 staff members on board, suggesting that the train guard be either replaced by a customer service role or merged with a customer service role, ruling out Driver Only Operation. Rail Tram and Bus Union (RTBU) state secretary Alex Claassens welcomed any announcement regarding safety and retaining train guards.[27]
However, in 2019 it was announced that Driver Only Operation would be implemented, with the driver viewing the side of the train via several CCTV cameras. The RTBU criticised this move as being "unsafe", due to the lack of microphones on the train.[1][failed verification]
In February 2020 the RTBU announced that members would refuse to staff the New Intercity Fleet over safety and employment concerns.[2]
On 27 November 2020 a snap strike in protest of the safety concerns was performed by the RTBU, shutting down all intercity services effective immediately until 7 am.[28]
A confidential 2018 report to the NSW government revealed that the doors could easily fail when opened at speed, which was only announced to the public in 2021. Gladys Berejiklian knew of these issues as of 2020. [3]
On 5 February 2021 an incident where a commuter fell between a train and the platform at Hornsby station in January was highlighted as a potentially fatal situation if it had occurred with a D set.[29]
On 2 March 2021 the RTBU claimed "WE WON" after the Customer Service Guard position was cancelled.[30]
In November 2021 an 18-month delay of entry into service was announced due to the union standoff and the COVID-19 pandemic, with Labor transport spokesperson Jo Haylen saying it was "yet another transport procurement debacle” from the government.[31]
Over December 2021 the RTBU would carry out a series of industrial actions as follows:
- 1/12/2021 - Station staff and shunters wearing shorts indefinitely
- 6/12/2021 - Drivers sounding horns at all stations during daylight hours
- 7/12/2021 - Ban on operating Public-Private Partnership (PPP) rolling stock (M sets, H sets, A sets, B sets and D sets)
- 8/12/2021 to 13/12/2021 - Ban on cleaning hazardous waste and graffiti
- 14/12/2021 - Ban on operating PPP rolling stock
- 15/12/2021 - 24 hour ban on issuing fines
- 17/12/2021 - Work to rule indefinitely
- 20/12/2021 - Full overnight stoppage network wide
- 21/12/2021 to 23/12/2021 - Ban on performing work where contractors are present[32][33]
On 22 March 2022 Nine News Australia would bring light to the RTBU regarding the CCTV cameras as unsafe, highlighting the lack of microphones, viewing blackspots, and poor vision quality, especially in the rain.[34]
Approval of the fleet by the Office of the National Safety Regulator
In July 2021, the independent Office of the National Rail Safety Regulator deemed the fleet to be safe, endorsing the Government's position on the matter.[35] Sue McCarrey, CEO of the ONRSR, outlined that they had worked with the operator since design stage right through to testing, pledging that ongoing safety audits would continue through to their operation. Additionally, McCarrey concluded that there was no greater risk than the current older fleet and in fact the use of technology on the new fleet would make them even safer; "We believe that risk is being managed through the technology on the train. The operating model we have approved for the NIF includes the use of a driver, a guard and the use of CCTV cameras at each door providing both the guard and the driver a view down the entire platform. Both the driver and the guard have access to screens to show them what is actually happening along the entire platform". McCarrey made it clear that as an independent regulator she is not part of the current negotiations between the RTBU and the train operator (NSW Trains) and nor should she be however if those negotiations resulted in a change to the operating model then the ONRSR would have to relitigate those proposed changes and once again complete that independent check to ensure that the changes proposed to the train operations continue to effectively manage the risks.[36]
Network disruptions
The February Shutdown
The NSW government directly shut down the entire passenger rail network in response to the RTBU's protected industrial action on 21 February 2022, with no replacement bus services occurring and zero prior notice. Overcrowding onto buses was widespread at locations such as Chatswood and Parramatta. The RTBU started a protest against the shutdown at Central Grand Concourse, with the RTBU saying "This is not a strike, we are not on strike".
Dominic Perrotet, the premier of NSW stated that it was a "coordinated attack by the Labor party and the union movement". Former Prime Minister Scott Morrison stated that the unions "put on a strike at 2 am this morning, throwing Sydneysiders into complete chaos".[37][38][39][40]
Documents would go on to show that the NSW Government was planning on a two-week-long shutdown.[41]
Fair Work Commission
On 18 February 2022, Sydney Trains and Transport for NSW would lodge an application to the Fair Work Commission seeking to suspend or terminate any further industrial action from the RTBU regarding the D sets, the Transport Asset Holding Entity, wages and any other cause.[42] After the February shutdown the Fair Work action was suspended.[43]
Kangy Angy
In September 2017 the Central Coast Express Advocate opposed the Kangy Angy Maintenance Centre citing issues of noise and flooding.[44]
In December 2021 it was announced that only 20 out of 300 jobs would be made from the Kangy Angy Maintenance Centre, which was heavily criticised by several Labor MPs including Chris Minns.[45]
Design
The trains are double deck electric multiple units measuring 163 m (534 ft 9 in) for an 8-car set or 204 m (669 ft 3 in) for a 10 car-set.[46] They will include accessible toilets and dedicated space for luggage, prams, bicycles and wheelchairs. Fixed seats on the upper and lower decks will be in a two by two arrangement. The seating will include cup holders, tray tables and arm rests. Each seat will feature a charging station for mobile devices.[13] The trains are being designed to be operated with or without guards, with tender documents stating the trains must support one-man operation.[47]
The new trains are wider than the V sets they replace and required modifications to be made to parts of the Blue Mountains line route to create sufficient clearance from adjacent structures.[16] A contract was awarded to the Continuum Alliance, an alliance between Transport for NSW, CPB Contractors and Lendlease, to make these modifications. Work started in February 2019[48] and was completed in July 2020.[49][50] They are scheduled to enter service in 2022.[51][52]
Services
The trains are expected to operate on the following services:[4]
- Blue Mountains: Central to Lithgow
- Central Coast & Newcastle: Central to Newcastle
- South Coast: Bondi Junction / Central to Port Kembla & Kiama
References
- ^ a b c Rabe, Tom; Smith, Alexandra (12 May 2022). "NSW government attacks rail unions over mothballed $2b train fleet". The Sydney Morning Herald. Retrieved 12 May 2022.
- ^ a b "Mitsubishi Electric to Supply Railway Systems for TfNSW" (PDF). Mitsubishi Electric. 5 September 2016. Retrieved 13 October 2021.
- ^ NSW Government to invest $2.8 billion in new intercity trains, making all trains air-conditioned Transport for NSW 8 May 2014
- ^ a b c "New Intercity Fleet". Transport for NSW. 12 January 2020. Retrieved 12 January 2020.
- ^ Expressions of interest called for new $2.8 billion intercity train fleet Transport for NSW 11 August 2014
- ^ New $2.8 billion intercity train fleet for NSW Rail Express 13 August 2014
- ^ Strong local and international interest in $2.8 billion intercity fleet project Transport for NSW 9 October 2014
- ^ Firms line up for intercity train deal PSnews online 15 October 2014
- ^ a b "Transforming regional train travel: Shortlist announced for new intercity fleet". Transport for NSW. 9 July 2015. Retrieved 9 July 2015.
- ^ a b "Industry asked to tender for delivery of new intercity fleet". Transport for NSW. 4 September 2015.
- ^ New Intercity fleet UGL
- ^ Transport for NSW extends New Intercity Fleet order International Railway Journal 4 May 2019
- ^ a b "Comfort comes first with New Intercity Trains". Transport for NSW. 18 August 2016.
- ^ a b "UGL as part of RailConnect NSW to deliver $2. 3 billion New Intercity Fleet" (PDF). UGL Limited. 18 August 2016.
- ^ "New Intercity Fleet Maintenance Facility - Notice to Residents and Businesses (September 2015)" (PDF). Transport for NSW. Transport for NSW. Archived from the original (PDF) on 2 October 2015. Retrieved 1 October 2015.
- ^ a b New intercity trains too wide for rail line to stations in Blue Mountains Sydney Morning Herald 5 October 2016
- ^ "Construction completed on Kangy Angy Rail Facility". Coast Community News. 25 August 2020. Retrieved 31 August 2020.
- ^ Explosion in growth; extra Intercity trains purchased to cope with demand Sydney Morning Herald 20 February 2019
- ^ "New Intercity Fleet Stations and Signalling Modifications". Transport for NSW. Retrieved 17 May 2019.
- ^ "The New Intercity Fleet trains are almost here". Transport for NSW. 3 December 2019. Retrieved 3 December 2019.
- ^ "First ride on New Intercity Fleet". NSW Government. 1 April 2021. Retrieved 6 April 2021.
- ^ "Mariyung fleet receives final safety tick". Transport for NSW. 30 July 2021. Retrieved 30 July 2021.
- ^ "$100m contract extension for UGL". Rail Express. 14 September 2021. Archived from the original on 8 October 2021.
- ^ O'Sullivan, Matt (26 November 2015). "$1.1b cost blowout for NSW's new 'off-the-shelf' intercity trains". The Sydney Morning Herald. Retrieved 19 June 2022.
- ^ O'Sullivan, Matt (6 October 2016). "New intercity trains too wide for rail line to stations in Blue Mountains". The Sydney Morning Herald. Retrieved 19 June 2022.
- ^ O'Sullivan, Matt (9 August 2017). "'Too wide and long': Work starts next year to make line big enough for new trains". The Sydney Morning Herald. Retrieved 19 June 2022.
- ^ O'Sullivan, Matt (21 October 2018). "Berejiklian government promises two staff for each new intercity train". The Sydney Morning Herald. Retrieved 19 June 2022.
- ^ Singhal, Tom Rabe, Pallavi (27 November 2020). "Snap strike throws NSW's train network into chaos". The Sydney Morning Herald. Retrieved 19 June 2022.
{{cite web}}
: CS1 maint: multiple names: authors list (link) - ^ "Close call at Hornsby highlights dangers of NIF". RTBU Express. 4 February 2021. Retrieved 19 June 2022.
- ^ "WE WON: FWC Rules No such thing as a Customer Service Guard or an Intercity Specialist Driver". RTBU Express. 2 March 2021. Retrieved 19 June 2022.
- ^ O'Sullivan, Matt (7 November 2021). "18-month delay to state's new intercity trains arriving from South Korea". The Sydney Morning Herald. Retrieved 19 June 2022.
- ^ "Rail, Tram and Bus Union NSW Branch - Updates to Industrial Action Calendar: It has been necessary to update a couple of the actions on our industrial action calendar. The "Work to Rule" action has been changed to 17 December 2021, and the "Ban on performing work where contractors are present" has been moved to 21 December 2021. All other actions remain the same. As always, you can find the calendar on the front page of our website, www.ourrightsourfight.com.au. | Facebook". www.facebook.com. Retrieved 19 June 2022.
- ^ Marks, Andy (15 December 2021). "Long and the short of it: rail workers have a point about their uniform". The Sydney Morning Herald. Retrieved 19 June 2022.
- ^ Major safety issues revealed with new Sydney trains | 9 News Australia, retrieved 19 June 2022
- ^ "New train fleet declared safe". Central Coast News. 1 September 2021. Retrieved 25 June 2022.
- ^ "Breakfast". ABC Sydney. 27 June 2022. Retrieved 29 June 2022.
- ^ "The truth behind the shock shutdown of Sydney's train system revealed". www.9news.com.au. Retrieved 19 June 2022.
- ^ O'Sullivan, Tom Rabe, Matt (3 March 2022). "Split between transport agency, minister over Sydney train shutdown". The Sydney Morning Herald. Retrieved 19 June 2022.
{{cite web}}
: CS1 maint: multiple names: authors list (link) - ^ "Everything you need to know about NSW's train shutdown, and what happens next". ABC News. 21 February 2022. Retrieved 19 June 2022.
- ^ "The politics of the Sydney train strike that wasn't". Australian Financial Review. 25 February 2022. Retrieved 19 June 2022.
- ^ "NSW transport made plans for two-week rail shutdown as early as last week, documents show". the Guardian. 24 February 2022. Retrieved 19 June 2022.
- ^ NSW, Transport for (18 February 2022). "Application to Fair Work Seeks to Halt Industrial Action from Disrupting Customers and Damaging the NSW Economy". www.transport.nsw.gov.au. Retrieved 19 June 2022.
- ^ ABC, Source (22 February 2022). "NSW transport minister drops fair work action against unions after Sydney trains shutdown – video". The Guardian. ISSN 0261-3077. Retrieved 19 June 2022.
- ^ New Kangy Angy rail maintenance facility approved, retrieved 19 June 2022
- ^ "Kangy Angy rail facility employs 20 – not the 300 jobs promised". Central Coast News. 7 December 2021. Retrieved 19 June 2022.
- ^ "New Intercity Fleet Fact Sheet - 2019" (PDF). Transport for NSW. p. 5. Retrieved 8 December 2018.
{{cite web}}
: CS1 maint: url-status (link) - ^ O'Sullivan, Matt (26 September 2016). "Train guards in firing line from NSW's $2.3 billion intercity fleet renewal". The Sydney Morning Herald.
- ^ New Intercity Fleet Springwood to Lithgow Rail Corridor Modifications Transport for NSW Reviewed 9 January 2020
- ^ "Blue Mountains Line ready for New Intercity Fleet". Rail Express. 21 July 2020. Retrieved 31 August 2020.
- ^ "Upgrades to Blue Mountains Line now complete". Transport for NSW. 20 July 2020. Retrieved 31 August 2020.
- ^ McKinney, Max (17 October 2020). "More delays for trains". Newcastle Herald. Retrieved 1 November 2020.
- ^ Safety is no joke: Constance must not allow unsafe trains on the network The Rail, Tram and Bus Union (RTBU) NSW 1 April 2021
External links
Media related to NSW TrainLink D sets at Wikimedia Commons