Alaska-Alberta Railway Development Corporation

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by GreenC bot (talk | contribs) at 15:58, 23 August 2023 (Reformat 2 citations per Category:CS1 errors: archive-url. Wayback Medic 2.5). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Alaska-Alberta Railway Development Corporation
Overview
Other name(s)A2A Rail
StatusReceivership
OwnerMcCoshen Group
Termini
Connecting linesAlaska Railroad
Canadian National Railway
Websitehttps://a2arail.com/
Service
Typeinternational freight
Technical
Track length1,600 mi (2,600 km)
Number of trackssingle with passing sidings[1]
Track gauge1,435 mm (4 ft 8+12 in) standard gauge

The Alaska-Alberta Railway Development Corporation (also known as A2A for Alaska to Alberta) was an entity created to build, own, and operate a proposed 2,600-kilometre (1,600 mi) railroad between Delta Junction, Alaska, and Fort McMurray, Alberta.[2] In 2021, the company was put in receivership and the project was on hold due to financial irregularities between the A2A president and main financial backer Bridging Finance.[3]

The railroad was planned to interchange with and operate on part of the Alaska Railroad, in order to access Southcentral Alaska and its ports. As of 2020 the project was estimated to cost CA$20 billion.[2][non-primary source needed] A rival enterprise, G7G Railway, estimated in 2020 the capital cost to be just under US$20 billion. They proposed shipping oil, via the Trans-Alaska Pipeline, from rail cars in Delta Junction to the coast.[4]

Route

The A2A intended to connect the isolated Alaska Railroad (above) and the rest of the North America via connections in Alberta to the Canadian railway network (below)

The proposed A2A railway would have connected to the Alaska Railroad at Delta Junction, Alaska, and run through the Yukon to Fort Nelson, British Columbia, and from there to a terminus at Fort McMurray, Alberta.[5] The A2A Railway had also been negotiating with the Mat-Su Borough on an agreement to complete the Port Mackenzie Railway Extension.[4]

Planning and construction

The Van Horne Institute studied the route in 2013.[6][7] A survey of the proposed route by the development corporation began in July 2020.[8]

On September 25, 2020, US President Donald Trump announced he would issue a presidential permit to the railway,[1] which had an agreement with Alaska Railway[9] to develop a joint operating plan for the rail connection to Canada.

A2A announced that JP Gladu was joining as President of A2A Rail Canada.[10] In July 2020, the company expected to start early field activities and detailed engineering design by Q1 2021.[11][needs update] However, there is no evidence of substantive field work being undertaken.

Creditor protection

In 2021, the Ontario Securities Commission (OSC) began investigating irregularities in the business dealings between the main financier of the A2A project, Bridging Finance Inc., and A2A's president, Sean McCoshen. The OSC alleged that following the funding of loans to various McCoshen companies, McCoshen funnelled a total of $19.5 million to Bridging's CEO David Sharpe.[12] Additionally, the OSC also alleged that "millions of dollars pledged for A2A rail also went to McCoshen's personal bank account and to an apparently unrelated company controlled by him."[13]

With the investigation underway, Bridging Finance was placed under receivership in April 2021. Bridging's receiver, PricewaterhouseCoopers requested repayment of A2A's $149 million loan in early June 2021. A2A did not have the funds available to repay the loan and it filed for creditor protection in June 2021.[13] McCoshen no longer appeared on the A2A website as an officer of the company.

Work on the project was abandoned.[3]

See also

References

  1. ^ a b "Trump gives approval for Alberta-Alaska rail line to move resources". Must Read Alaska. September 25, 2020. Retrieved September 26, 2020.
  2. ^ a b "Our Railway". A2A Rail.com. Alaska to Alberta Rail. Retrieved July 15, 2020.
  3. ^ a b Ellis, Tim. "'Boondoggle': financial woes may jeopardize proposed Alaska-Canada railroad project". KTOO. KUAC-Fairbanks. Retrieved February 12, 2022.
  4. ^ a b Anderson, Dennis. "Is Alberta to Alaska Railway Port Mac's Sugar Savior?". frontiersman.com. Mat-Su Valley Frontiersman. Retrieved July 21, 2020.
  5. ^ "Ambitious railway dream is gathering steam". Whitehorse Star. July 10, 2020. Retrieved September 26, 2020.
  6. ^ Azizi, Joshua (July 5, 2019). "Group aims for Canada-Alaska railway through Yukon". Yukon News. Retrieved September 29, 2020.
  7. ^ "Alberta to Alaska Railway" (PDF). Pacific NorthWest Economic Region. Van Horne Institute. Retrieved September 29, 2020.
  8. ^ Cuenca, Oliver. "Alberta – Alaska railway surveying to proceed". International Railway Journal. International Railway Journal. Retrieved July 15, 2020.
  9. ^ "Engineering Spotlight: A2A Rail aims to carve out railway corridor between Alberta, Alaska". Journal of Commerce by ConstructConnect. July 15, 2019. Retrieved September 26, 2020.
  10. ^ "A2A Rail Welcomes New Addition to Executive Team". newswire.ca. 22 June 2020. Retrieved 11 February 2023.
  11. ^ "With start of surveying activities, A2A Rail achieves another development milestone". Cision. CNW Group Ltd. July 7, 2020. Retrieved August 23, 2020.
  12. ^ George-Cosh, David. "OSC seeks $1M fines, penalties for ex-Bridging Finance execs". BNN Bloomberg. Archived from the original on 24 April 2022. Retrieved 11 February 2023.
  13. ^ a b Rieger, Sarah (23 June 2021). "Alberta to Alaska rail project files for creditor protection after lender goes into receivership". CBC. Archived from the original on 15 February 2023. Retrieved 15 February 2023.