In February 2012 President Sarkozy decided to extend the life of existing nuclear reactors beyond 40 years, following the [[Court of Audit of France|Court of Audit]] decision that this is the best option as new nuclear capacity or other forms of energy would be more costly and available too late. Within ten years 22 out of the 58 reactors will have been operating for over 40 years.<ref>{{cite news |url=http://www.reuters.com/article/2012/02/12/france-nuclear-idUSL5E8DC2UU20120212 |title=France to extend life of nuclear plants - minister |date=12 February 2012 |publisher=Reuters |location=Paris |accessdate=10 March 2012}}</ref> The court expects EDF's projected investment programme in existing plant, including post Fukushima safety improvements, will add between 9.5% and 14.5% to generation costs, taking costs to between €37.9 and €54.2 per MWh. However generation costs from the new Flamanville EPR reactor would be, depending on construction outcome, at least in the €70 to €90 per MWh range.<ref name=comptes-summary>{{cite report |url=http://www.ccomptes.fr/en/JF/documents/divers/Costs_nuclear_power_sector_summary.pdf |title=The costs of the nuclear power sector - Summary in English |date=January 2012 |publisher=Cour des Comptes |accessdate=11 March 2012}}</ref>
In February 2012 President Sarkozy decided to extend the life of existing nuclear reactors beyond 40 years, following the [[Court of Audit of France|Court of Audit]] decision that this is the best option as new nuclear capacity or other forms of energy would be more costly and available too late. Within ten years 22 out of the 58 reactors will have been operating for over 40 years.<ref>{{cite news |url=http://www.reuters.com/article/2012/02/12/france-nuclear-idUSL5E8DC2UU20120212 |title=France to extend life of nuclear plants - minister |date=12 February 2012 |publisher=Reuters |location=Paris |accessdate=10 March 2012}}</ref> The court expects EDF's projected investment programme in existing plant, including post Fukushima safety improvements, will add between 9.5% and 14.5% to generation costs, taking costs to between €37.9 and €54.2 per MWh. However generation costs from the new Flamanville EPR reactor would be, depending on construction outcome, at least in the €70 to €90 per MWh range.<ref name=comptes-summary>{{cite report |url=http://www.ccomptes.fr/en/JF/documents/divers/Costs_nuclear_power_sector_summary.pdf |title=The costs of the nuclear power sector - Summary in English |date=January 2012 |publisher=Cour des Comptes |accessdate=11 March 2012}}</ref>


Following [[François Hollande|François Hollande's]] victory in the [[French presidential election, 2012|2012 Presidential Election]], is is thought that there may be a partial [[nuclear phaseout]] in France. This follows a national debate in the run-up to the election, with President [[Nicolas Sarkozy]] backing nuclear power and François Hollande proposing a cut in nuclear power’s electricity contribution by more than a third by 2025.<ref name=nweek11>{{cite web |url=http://www.thedailybeast.com/newsweek/2011/11/27/post-fukushima-nuclear-power-changes-latitudes.html |title= Nuclear Power Goes Rogue |author= [[Henry Sokolski]] |date= Nov 28, 2011 |work=Newsweek }}</ref> It seems certain that Hollande will at least order the closure of the [[Fessenheim Nuclear Power Plant]], probably by 2017,<ref>[http://www.francesoir.fr/actualite/politique/presidentielle-hollande-confirme-sa-volonte-de-fermer-fessenheim-219201.html Présidentielle : Hollande confirme sa volonté de fermer Fessenheim] France Soir, published 2012-05-02, accessed 2012-05-08</ref> which has been the focus of opposition concerns over the dangers of seismic activity and flooding.
Following [[François Hollande|François Hollande's]] victory in the [[French presidential election, 2012|2012 Presidential Election]], is is thought that there may be a partial [[nuclear phaseout]] in France. This follows a national debate in the run-up to the election, with President [[Nicolas Sarkozy]] backing nuclear power and François Hollande proposing a cut in nuclear power’s electricity contribution by more than a third by 2025.<ref name=nweek11>{{cite web |url=http://www.thedailybeast.com/newsweek/2011/11/27/post-fukushima-nuclear-power-changes-latitudes.html |title= Nuclear Power Goes Rogue |author= [[Henry Sokolski]] |date= Nov 28, 2011 |work=Newsweek }}</ref> It seems certain that Hollande will at least order the closure of the [[Fessenheim Nuclear Power Plant]], probably by 2017,<ref>[http://www.francesoir.fr/actualite/politique/presidentielle-hollande-confirme-sa-volonte-de-fermer-fessenheim-219201.html Présidentielle : Hollande confirme sa volonté de fermer Fessenheim] France Soir, published 2012-05-02, accessed 2012-05-08</ref> which has been the focus of concerns over the dangers of seismic activity and flooding.


The Negawatt Institute have modelled the French energy system in detail including electricity production and have proposed a road map for a phased exit from nucleaur by 2050 to a dominant renewable energy system.<ref name=reu11>{{cite web |url=http://www.negawatt.org/scenario-negawatt-2011-p46.html |title=scénario négaWatt 2011}}</ref>
The Negawatt Institute have modelled the French energy system in detail including electricity production and have proposed a road map for a phased exit from nucleaur by 2050 to a dominant renewable energy system.<ref name=reu11>{{cite web |url=http://www.negawatt.org/scenario-negawatt-2011-p46.html |title=scénario négaWatt 2011}}</ref>

Revision as of 13:40, 8 May 2012

Electricity production in France has been dominated by Nuclear power ever since the early 80s with a large portion of that power exported today.
  thermofossil
  hydroelectric
  nuclear
  Other renewables

Nuclear power is the primary source of electric power in France. In 2004, 425.8 TWh out of the country's total production of 540.6 TWh of electricity was from nuclear power (78.8%), the highest percentage in the world.[1]

Due to the general inflexibility of modern reactor designs compared to fossil energy based power plant, to achieve this high load factor, France is also forced to be the world's largest net exporter of electric power (exporting 18% of its total production via 10 GW overall of interconnection capacity[2] to Italy, the Netherlands, Belgium, Britain, and Germany), to use 14.59 GW storage hydroelectricity 4.302 GW of pumped storage[clarification needed],[3] and the EJP load disconnection tarrif which is allied to the use of about 5 GW of diesel generators in private hands.[4] (It also has 6.16 GW run of river hydro irrelevant in this context of dealing with flexibility but is included for completeness)

France's electricity price is among the lowest in Europe,[5] however this figure should be treated with caution, since the stations were essentially built using French government sovereign debt, which is typically 3.5%. European Union rules now prevent this kind of indirect subsidy.

France's nuclear power industry has been called "a success story" that has put the nation "ahead of the world" in terms of providing cheap, CO2-free energy.[6] However, even with the great flexibility offered by the interconnections, the storage and pumped storage hydro and the EJP France's nuclear reactors are forced to be used in load-following mode and some reactors close on weekends because there is no market for the electricity.[7][8] This means that the capacity factor is low by world standards, which is not an ideal economic situation for nuclear plants.[7]

As of 2002, Électricité de France (EDF) — the country's main electricity generation and distribution company — manages the country's 59 nuclear power plants.[7] In 2006, the French Government asked Areva and EDF to build a next generation nuclear reactor, the EPR (European Pressurized Reactor), at the Flamanville Nuclear Power Plant. EdF is substantially owned by the French Government, with around 85% of EdF shares in government hands .[9] 78.9% of Areva shares are owned by the French public sector company CEA and are therefore in public ownership[10] EdF remains heavily in debt. Its profitability suffered during the recession which began in 2008. It made €3.9 billion in 2009, which fell to €1.02 billion in 2010, with provisions set aside amounting to €2.9 billion.[citation needed] The Nuclear industry has been accused of significant cost overruns and failing to cover the total costs of operation, including waste management and decommissioning.[11] EdF said its third-generation nuclear reactor EPR project at its Flamanville, northern France, plant will be delayed until 2016, due to "both structural and economic reasons," which will bring the project's total cost to EUR6 billion.[12] Similarly, the cost of the EPR to be built at Olkiuoto, Finland has escalated. Areva and the utility involved "are in bitter dispute over who will bear the cost overruns and there is a real risk now that the utility will default.[13] Despite recent setbacks which are largely political in nature rather than technical, nuclear power continues to be seen as a cornerstone in French energy security.

Following the 2011 Fukushima I nuclear accidents, the head of France's nuclear safety agency has said that France needs to upgrade the protection of vital functions in all its nuclear reactors to avoid a disaster in the event of a natural calamity,which will inevitably increase the cost of electricity, adding there was no need to close any plants. In November 2011, France is in the midst of a national debate over nuclear energy ahead of the 2012 presidential elections. The ruling UMP party is in favor of maintaining nuclear and the opposition Socialist party is in favor of closing the oldest 24 reactors by 2025.[14]

EdF has suggested that if the political environment causes the EPR costs to overrun, the design would be replaced with a cheaper and simpler Franco-Japanese design, the Atmea for which the design will be completed by 2013, or the already operating Franco-Chinese design, the CPR-1000.[15][16]

History

France has a long relationship with nuclear power, starting with Henri Becquerel's discovery of natural radioactivity in the 1890s and continued by famous nuclear scientists like Pierre and Polish born Marie Curie(Sklodowska).

Before World War II, France had been heavily involved in nuclear research through the work of the Joliot-Curies. In 1945 the Provisional Government of the French Republic (GPRF) created the Commissariat à l'Énergie Atomique (CEA) governmental agency, and Nobel prize winner Frédéric Joliot-Curie, member of the French Communist Party (PCF) since 1942, was appointed high-commissioner. He was relieved of his duties in 1950 for political reasons, and would be one of the 11 signatories to the Russell-Einstein Manifesto in 1955. The CEA was created by Charles de Gaulle on October 18, 1945. Its mandate is to conduct fundamental and applied research into many areas, including the design of nuclear reactors, the manufacturing of integrated circuits, the use of radionucleides for medical treatments, seismology and tsunami propagation, and the safety of computerized systems.

Nuclear research was discontinued for a time after the war because of the instability of the Fourth Republic and the lack of finances available.[17] However, in the 1950s a civil nuclear research program was started, a by-product of which would be plutonium. In 1956 a secret Committee for the Military Applications of Atomic Energy was formed and a development program for delivery vehicles started. In 1957, soon after the Suez Crisis and the diplomatic tension with both the USSR and the United States, French president René Coty decided the creation of the C.S.E.M. in the then French Sahara, a new nuclear tests facility replacing the C.I.E.E.S.[18] See France and nuclear weapons.

The first nuclear power plant in France was opened in 1963.[19]

Messmer Plan

As a direct result of the 1973 oil crisis, on March 6, 1974 Prime Minister Pierre Messmer unexpectedly announced what became known as the 'Messmer Plan', a huge nuclear power program aimed at generating all of France's electricity from nuclear power.[19] At the time of the oil crisis most of France's electricity came from foreign oil, and while it was strong in heavy engineering capabilities, France had few indigenous energy resources,[20]

The announcement of the Messmer Plan, which was imposed without public or parliamentary debate,[21][22] also led to the foundation of the Groupement des scientifiques pour l'information sur l'énergie nucléaire (Association of Scientists for Information on Nuclear Energy), formed after around 4,000 scientists signed a petition of concern over the government's action, known as the Appeal of the 400 after the 400 scientists who initially signed it.[21]

The plan envisaged the construction of around 80 nuclear plants by 1985 and a total of 170 plants by 2000.[21] Work on the first three plants, at Tricastin, Gravelines, and Dampierre started the same year[19] and France installed 56 reactors over the next 15 years.[23]

Recent developments

In 2001, Areva, was created by the merger of CEA Industrie, Framatome and Cogema (now Areva NC). Its main shareholder is the French owned company CEA, but the German government also holds, through Siemens, 34% of the shares of Areva's subsidiary, Areva NP, in charge of building the EPR (third-generation nuclear reactor).[24]

Following the 2011 Fukushima I nuclear accidents, the head of France's nuclear safety agency has said that France needs to upgrade the protection of vital functions in all its nuclear reactors to avoid a disaster in the event of a natural calamity, adding there was no need to close any plants. "There is a need to add a layer to protect safety mechanisms in reactors that are vital for the protection of the reactor such as cooling functions and electric powering," Jacques Repussard, head of the IRSN, said.[25] Opinion polls show support for atomic energy has dropped since Fukushima. Forty-percent of the French "are 'hesitant' about nuclear energy while a third are in favor and 17 percent are against, according to a survey by pollster Ifop published November 13".[25]

In February 2012 President Sarkozy decided to extend the life of existing nuclear reactors beyond 40 years, following the Court of Audit decision that this is the best option as new nuclear capacity or other forms of energy would be more costly and available too late. Within ten years 22 out of the 58 reactors will have been operating for over 40 years.[26] The court expects EDF's projected investment programme in existing plant, including post Fukushima safety improvements, will add between 9.5% and 14.5% to generation costs, taking costs to between €37.9 and €54.2 per MWh. However generation costs from the new Flamanville EPR reactor would be, depending on construction outcome, at least in the €70 to €90 per MWh range.[27]

Following François Hollande's victory in the 2012 Presidential Election, is is thought that there may be a partial nuclear phaseout in France. This follows a national debate in the run-up to the election, with President Nicolas Sarkozy backing nuclear power and François Hollande proposing a cut in nuclear power’s electricity contribution by more than a third by 2025.[28] It seems certain that Hollande will at least order the closure of the Fessenheim Nuclear Power Plant, probably by 2017,[29] which has been the focus of concerns over the dangers of seismic activity and flooding.

The Negawatt Institute have modelled the French energy system in detail including electricity production and have proposed a road map for a phased exit from nucleaur by 2050 to a dominant renewable energy system.[25]

Technical overview

Drawing such a large percentage of overall electrical production from nuclear power is unique to France. This reliance has resulted in certain necessary deviations from the standard design and function of other nuclear power programs. For instance, in order to meet changing demand throughout the day, some plants must work as peaking power plant, whereas most nuclear plants in the world operate as base load plants, and allow other fossil or hydro units to adjust to demand. Nuclear power in France has a total capacity factor of around 77%, which is low due to load following. However availability is around 84%, indicating excellent overall performance of the plants.

The first 8 power reactors in the nation were gas cooled reactor types (UNGG reactor), whose development was pioneered by CEA. Coinciding with a uranium enrichment program, EdF developed pressurized water reactor (PWR) technology which eventually became the dominant type. The gas-cooled reactors located at Brennilis, Bugey, Chinon, and Marcoule have all been shut down.

All operating plants today are PWRs with the exception of the Phénix, which was part of an initiative to develop sodium-cooled fast breeder reactor technology. The Superphénix, a larger, more ambitious version, has been shut down.

The PWR plants were all developed by Framatome (which is now Areva) from the initial Westinghouse design [citation needed]. All of the PWR plants are one of three variations of the design, having output powers of 900 MWe, 1300 MWe, and 1450 MWe. The repeated use of these standard variants of a design has afforded France the greatest degree of nuclear plant standardization in the world.

900 MWe class (CP0, CP1 and CP2 designs)

The Saint-Laurent site, showing two CP2, 900MWe class reactors and the cooling tower on the right

There are a total of 34 of these reactors in operation; most were constructed in the 1970s and the early 1980s. In 2002 they had a uniform review and all were granted a 10 year life extension.

With the CP0 and CP1 designs, two reactors share the same machine and command room. With the CP2 design, each reactor has its own machine and command room. Despite this difference, CP1 and CP2 types use the same technologies (the two types are frequently referred as CPY). Compared to CP0 they have an additional cooling circuit between the emergency system that allows to spraying water into the containment in case of an accident and the circuit which contains river's water, a more flexible control system and some minor difference in the layout of the building.[30]

This three loop design (three steam generators and three primary circulation pumps) was also exported to a number of other countries, including:

1300 MWe class (P4 and P'4 designs)

The Cattenom site houses four 1300 MWe class reactors

There are 20 reactors of this design (four steam generators and four primary circulation pumps) operating in France. The P4 and P'4 type have some minor difference in the layout of the building, especially for the structure which contain the fuel rods and the circuitry.[30]

1450 MWe class (N4 design)

The Civaux site houses two 1450 MWe class reactors, the most recent design operating today

There are only 4 of these reactors, housed at two separate sites: Civaux and Chooz. Construction of these reactors started between 1984 and 1991, but full commercial operation did not begin until between 2000 and 2002 because of thermal fatigue flaws in the heat removal system requiring the redesign and replacement of parts in each N4 power station.[32] In 2003 the stations were all uprated to 1500 MWe. It is unlikely that more of this class will be built because it is expected to be succeeded by the larger 1650 MWe EPR design.

1650MWe class (EPR design)

The next generation design for French reactors will be the European Pressurised Reactor (EPR), which will have a broader scope than France alone, with a pilot plant in Finland undergoing construction and with marketing activities extending to the United States and China. The first French EPR is under construction at the Flamanville Nuclear Power Plant, and should be operational in 2014. The second French EPR reactor will be built at the Penly Nuclear Power Plant, with construction starting in 2012 and completion scheduled for 2017.[33]

This reactor is one of the newest reactor designs in the world. It was developed by Areva contributing its N4 reactor technology and the German company Siemens contributing its Konvoi reactor technology. In keeping with the French approach of highly standardized plants and proven technology, it uses more traditional active safety systems and is more similar to current plant designs than international competitors such as the AP1000 or the ESBWR.

In 2005 EdF announced plans to replace the current nuclear plants with new 1600 MWe units as they reach the end of their licensed life, starting around 2020.[citation needed] This decision confirms that France is planning to continue indefinitely using nuclear power as its primary electricity source. In order to replace the current 58 reactors, one new large unit will have to be built about every year for about 40 years.

Fusion reactors

While fusion power is not expected to be feasible for many more decades, France has shown promise to be a forerunner in the technology by winning the bid to host the ITER reactor in Cadarache.[34] The ITER should start actual fusion around 2018. However, ITER does not plan to generate any commercially available energy. Instead the construction of another plant, named DEMO, will test the feasibility of commercial Fusion, before they are added to the energy supply.

Cooling

The majority of nuclear plants in France are located away from the coasts and obtain their cooling water from rivers. These plants employ cooling towers to reduce their impact on the environment. The temperature of emitted water carrying the waste heat is strictly limited by the French government, and this has proved to be problematic during recent heat waves.[35]

4 plants, equalling 14 reactors are located on the coast:

These 4 get their cooling water directly from the ocean and can thus dump their waste heat directly back into the sea, which is slightly more economical.

Fuel cycle

Active work going on for the ultimate underground repository.

France is one of the few countries in the world with an active nuclear reprocessing program, with the COGEMA La Hague site. Enrichment work, some MOX fuel fabrication, and other activities take place at the Tricastin Nuclear Power Centre. Enrichment is completely domestic and is powered by 2/3 of the output of the nuclear plant at Tricastin. Reprocessing of fuel from other countries has been done for the United States and Japan, who have expressed the desire to develop a more closed fuel cycle similar to what France has achieved. MOX fuel fabrication services have also been sold to other countries, notably to the USA for the Megatons to Megawatts Program, using Plutonium from dismantled nuclear weapons.

While France does not mine Uranium for the front end of the fuel cycle domestically, French companies have various holdings in the Uranium market. Uranium for the French program totals 10,500 tonnes per year coming from various locations such as:

  • Canada - 4500 tU/yr
  • Niger - 3200 tU/yr

Final disposal of the high level nuclear waste is planned to be done at the Meuse/Haute Marne Underground Research Laboratory deep geological repository.

Limitations

France's nuclear reactors comprise 90 per cent of EDFs capacity and so they are used in load-following mode and some reactors close at weekends because there is no market for the electricity.[7][8] This means that the capacity factor is low by world standards, usually in the high seventies as a percentage. This is not an ideal economic situation for nuclear plants, but is required due to the load-following nature of some reactors.[7]

During periods of high demand EDF has been routinely "forced into the relatively expensive spot and short-term power markets because it lacks adequate peak load generating capacity".[8] France heavily relies on electric heating, with about one third of existing and three quarters of new houses using electric space heating due to the low off-peak tariffs offered.[36] Due to this residential heating demand, about 2.3 GW of extra power is needed for every degree Celsius of temperature drop.[36] This means that during cold snaps, French electricity demand increases dramatically, forcing the country to import at full capacity from its neighbours during peak demand. In February 2012, Germany "came to the rescue of France during last week's cold snap by massively exporting electricity to its neighbour, silencing critics who slammed Berlin last year for abruptly shutting down 8 nuclear reactors after the Fukushima disaster". (Germany uses a variety of heating methods including gas and fuel oil heaters).[37]

All but four of EDFs plants are inland and require fresh water for cooling. Eleven of these 15 inland plants have cooling towers, using evaporative cooling, while the others use lake or river water directly. So in very hot summers, generation output may be restricted.[7]

According to Stephanie Cooke, nuclear power in France has not reduced the country's dependence on oil, as about 70 per cent of the total energy consumed in France during 2006 was still from fossil fuels.[8]

Another critique of the French situation is that it has over-invested in nuclear, which has meant that electricity has been exported to other countries or "dumped" on the French market, encouraging the use of electricity for space heating and water heating. This can be regarded as an environmentally wasteful practice.[7]

Accidents and incidents

Nuclear power accidents in France[38][39]
Date Location Description Cost
(in millions
2006 US$)
17 October 1969 Saint-Laurent, France 50 kg of Uranium in one of the reactors at the Saint-Laurent Nuclear Power Plant began to melt, an event classified at 'level 4' on the International Nuclear Event Scale (INES).[40] As of March 2011, this remains the most serious civil nuclear power accident in France.[41] ?
25 July 1979 Saclay, France Radioactive fluids escape into drains designed for ordinary wastes, seeping into the local watershed at the Saclay BL3 Reactor 5
13 March 1980 Loir-et-Cher, France A malfunctioning cooling system fuses fuel elements together at the Saint Laurent A2 reactor, ruining the fuel assembly and forcing an extended shutdown 22
14 April 1984 Bugey, France Electrical cables fail at the command centre of the Bugey Nuclear Power Plant and force a complete shutdown of one reactor 2
22 May 1986 Normandy, France A reprocessing plant at La Hague malfunctions and exposes workers to unsafe levels of radiation and forces five to be hospitalised 5
12 April 1987 Tricastin, France Tricastin fast breeder reactor leaks coolant, sodium and uranium hexachloride, injuring seven workers and contaminating water supplies 50
27 December 1999 Blayais, France An unexpectedly strong storm floods the Blayais Nuclear Power Plant, forcing an emergency shutdown after injection pumps and containment safety systems fail from water damage 55
21 January 2002 Manche, France Control systems and safety valves fail after improper installation of condensers, forcing a two-month shutdown 102
16 May 2005 Lorraine, France Sub-standard electrical cables at the Cattenom-2 nuclear reactor cause a fire in an electricity tunnel, damaging safety systems 12
13 July 2008 Tricastin, France 75 kg of natural uranium, in thousands of litres of solution, accidentally spilled on the ground and run off into a nearby river 7
12 August 2009 Gravelines, France Assembly system fails to properly eject spent fuel rods from the Gravelines Nuclear Power Plant, causing the fuel rods to jam and the reactor to shut down 2
12 September 2011 Marcoule, France One person has been killed and four injured, one seriously, in a blast at the Marcoule Nuclear Site. The explosion took place in a furnace used to melt “low to very low grade” metallic waste, a spokesman for the safety authority said, and did not represent a nuclear accident ?

In July 2008, 18,000 litres (4,755 gallons) of uranium solution containing natural uranium were accidentally released from Tricastin Nuclear Power Centre. Due to cleaning and repair work the containment system for a uranium solution holding tank was not functional when the tank filled. The inflow exceeded the tank's capacity and 30 cubic metres of uranium solution leaked, with 18 cubic metres spilled on the ground. Testing found elevated uranium levels in the nearby Gaffière and Lauzon rivers. The liquid that escaped to the ground contained about 75 kg of natural uranium, which is toxic as a heavy metal, but only slightly radioactive. Estimates for the releases were initially higher, up to 360 kg of natural uranium, but revised downward later.[42] French authorities banned the use of water from the Gaffière and Lauzon for drinking and watering of crops for 2 weeks. Swimming, water sports and fishing were also banned. This incident has been classified as Level 1 (anomaly) on the International Nuclear Event Scale.[43]

Shortly after the first incident, approximately 100 employees were exposed to minor doses of radiation (1/40 of the annual limit) due to a piping failure.[44]

Seismicity

The location of the Fessenheim Nuclear Power Plant in the Rhine Rift Valley near the fault that caused the 1356 Basel earthquake is causing concern.

Following the 2011 Fukushima I nuclear accidents there has been an increased focus on the risks associated with seismic activity in France, with particular attention focused on the Fessenheim Nuclear Power Plant.

General seismic risk in France is categorised on a five-point scale, with zone 1 being very low risk, through to zone 5 in areas with a 'very strong' risk.[45] In Metropolitan France the areas of highest risk are rated at 4, 'strong', and are located in the Pyrenees, Alps, the south of the Haut-Rhin département, the Territoire de Belfort and a few communes in Doubs.[45] A new zoning map comes into force on May 1, 2011, which significantly increases the rating for many areas.[45] The major nuclear research facilities at Cadarache are located in a zone 4 area near the fault that caused the 1909 Lambesc earthquake, while the Marcoule research centre and the nuclear power plants at Tricastin, Cruas, Saint-Alban, Bugey and Fessenheim (near the fault that caused the 1356 Basel earthquake) are all within zone 3.[46] A further 6 plants lie within zone 2.[46]

Hazard evaluation

The current process for evaluating the seismic hazard for a nuclear plant is set out in Règle Fondamentale de Sûreté (Fundamental Safety Rule) RFS 2001-01, published by the Institute for Radioprotection and Nuclear Safety, which uses more detailed seismotectonic zones.[47] RFS 2001-01 replaced RFS I.2.c, published in 1981, however it has been criticised for continuing to require a deterministic assessment (rather than a probabilistic approach) that relies primarily on the strongest 'historically known' earthquake near a site.[48] This leads to a number of problems including the short period (in geological timescales) for which there are records, the difficulty of assessing the characteristics of earthquakes that occurred prior to the use of seismometers, the difficulty of identifying the existence of all earthquakes that pre-date the historic record, and ultimately the reliance on one single earthquake scenario.[48] Other criticisms include the use of intensity in the evaluation method, rather than spectral acceleration, which is commonly used elsewhere.[48]

Nuclear safety

In 2012, France's Nuclear Safety Authority (the ASN) released a report announcing a sweeping safety upgrade to all the country's reactors. The ASN's report states plainly that a loss of coolant or electricity could, in the worst cases, see meltdowns at nuclear reactors in hours. It also lists many shortcomings found during 'stress tests', in which some safety aspects of plants were found not to meet existing standards.[49] It will now require all power plants to build a set of safety systems of last resort, contained in bunkers that will be hardened to withstand more extreme earthquakes, floods and other threats than plants themselves are designed to cope with. It will also adopt a proposal by EDF to create an elite force that is specifically trained to tackle nuclear accidents and could be deployed to any site within hours. Both moves are a response to the Fukushima nuclear disaster.[50]

Public opinion

Protest against new French nuclear plants (March 2007)

Following the 2011 Fukushima I nuclear accidents an OpinionWay poll at the end of March found that 57% of the French population were opposed to nuclear energy in France.[51] A TNS-Sofres poll in the days following the accident found 55% in favour of nuclear power.[51] In 2006 BBC / GlobeScan poll found 57% of the French opposed to nuclear energy.[52]

In May 2001, an Ipsos poll found that nearly 70% of the population had a 'good opinion' of nuclear power, however 56% also preferred not to live near a nuclear plant and the same proportion thought that a 'Chernobyl-like accident' could occur in France.[53] The same Ipsos poll revealed that 50% thought that nuclear power was the best way of solving the problem of the greenhouse effect, while 88% thought this was a major reason for continuing to use nuclear power.[53]

Historically the position has generally been favourable, with around two thirds of the population strongly supporting nuclear power,[23][54] while the Gaullists, the Socialist Party and the Communist Party were also all in favour.

When the Civaux Nuclear Power Plant was being constructed in 1997, it was claimed to be welcomed by the local community:

In France, unlike in America, nuclear energy is accepted, even popular. Everybody I spoke to in Civaux loves the fact their region was chosen. The nuclear plant has brought jobs and prosperity to the area. Nobody I spoke to, nobody, expressed any fear.[23]

A variety of reasons were cited for the popular support; a sense of national independence and reduced reliance on foreign oil, reduction of greenhouse gases, and a cultural interest in large technological projects (like the TGV and Concorde).[23]

Anti-nuclear movement

In the 1970s, an anti-nuclear movement in France, consisting of citizens' groups and political action committees, emerged. Between 1975 and 1977, some 175,000 people protested against nuclear power in ten demonstrations.[55]

In January 2004, up to 15,000 anti-nuclear protesters marched in Paris against a new generation of nuclear reactors, the European Pressurised Reactor (EPR).[56] On March 17, 2007, simultaneous protests, organised by Sortir du nucléaire, were staged in 5 French towns to protest construction of EPR plants.[57][58]

After Japan's 2011 Fukushima nuclear disaster, thousands staged anti-nuclear protests around France, demanding reactors be closed. Protesters' demands were focused on getting France to shut its oldest nuclear power station at Fessenheim. Many people also protested at the Cattenom nuclear plant, France's second most powerful.[59]

In November 2011, thousands of anti-nuclear protesters delayed a train carrying radioactive waste from France to Germany. Many clashes and obstructions made the journey the slowest one since the annual shipments of radioactive waste began in 1995.[60] Also in November 2011, a French court fined nuclear power giant Électricité de France €1.5m and jailed two senior employees for spying on Greenpeace, including hacking into Greenpeace's computer systems. Greenpeace was awarded €500,000 in damages.[61]

On the first anniversary of the Fukushima nuclear disaster, organisers of French anti-nuclear demonstrations claim 60,000 supporters formed a human chain 230 kilometres long, stretching from Lyon to Avignon.[62] Austrian Chancellor Werner Faymann expects anti-nuclear petition drives to start in at least six European Union countries in 2012 with the goal of having the EU abandon nuclear power.[63]

Environmental impact

In 2007 Areva NC claimed that, due to their reliance on nuclear power, France's carbon emissions per kWh are less than 1/10 that of Germany and the UK, and 1/13 that of Denmark, which has no nuclear plants. Its emissions of nitrogen oxide and sulfur dioxide have been reduced by 70% over 20 years, even though the total power output has tripled in that time.[64]

French environmentalist Bruno Comby started the group Environmentalists For Nuclear Energy in 1996, and said in 2005, "If well-managed, nuclear energy is very clean, does not create polluting gases in the atmosphere, produces very little waste and does not contribute to the greenhouse effect".[65]

See also

{{{inline}}}

Companies

References

  1. ^ EnerPub (2007-06-08). "France: Energy profile". Spero News. Retrieved 2007-08-25.
  2. ^ entsoe - european network of transmission system operators for electricity[failed verification]
  3. ^ eurostat[full citation needed]
  4. ^ Bergerat Monnoyer diesel generator suppliers seminar, H Leverton, Slough, England 1990
  5. ^ | last = EnerPub[full citation needed]
  6. ^ http://www.theledger.com/article/20080814/COLUMNISTS/808140356[full citation needed]
  7. ^ a b c d e f g Steve Kidd.Nuclear in France - what did they get right? Nuclear Engineering International, June 22, 2009.
  8. ^ a b c d Stephanie Cooke (2009). In Mortal Hands: A Cautionary History of the Nuclear Age, Black Inc., p. 359.
  9. ^ [c].Shareholding policy". Électricité de France. December 31, 2007
  10. ^ [d].http://en.wikipedia.org/wiki/Areva Retrieved 27 December 2011
  11. ^ .http://library.thinkquest.org/3471/nuclear_waste.html Retrieved 27 December 2011 On 20th July 2011[full citation needed]
  12. ^ [g]http://www.epcengineer.com/news/post/5662/edfs-french-epr-delayed-to-2016-total-cost-up-to-eur6-billion Retrieved 27 December 2011.
  13. ^ [h] http://en.wikipedia.org/wiki/Olkiluoto_Nuclear_Power_Plant Retrieved 27 December 2011"
  14. ^ Muriel Boselli (Nov 17, 2011). "France needs to upgrade all nuclear reactors". Reuters.
  15. ^ Ed Crooks (14 November 2011). "EDF searches for reactor suppliers". Financial Times. Retrieved 16 January 2012.
  16. ^ Marie-Caroline Lopez (13 November 2011). "FEn pleine polémique sur Flamanville, EDF se prépare à abandonner l'EPR". La Tribune.
  17. ^ Notice on France on Global Security Template:En icon
  18. ^ Sahara on the website of the French Minister of Defence Template:Fr icon
  19. ^ a b c Electricité de France Company History Electricité de France, accessed 2011-04-11
  20. ^ World Nuclear Association (2007). "Nuclear Power in France". Retrieved 2007-08-25. {{cite web}}: Unknown parameter |month= ignored (help) (alternate copy)
  21. ^ a b c Les physiciens dans le mouvement antinucléaire : entre science, expertise et politique Cahiers d’histoire, published 2007, accessed 2011-04-11
  22. ^ Nelkin, Dorothy and Michael Pollak, "Ideology as Strategy: The Discourse of the Anti-Nuclear Movement in France and Germany" Science, Technology, & Human Values, Vol. 5, No. 30 (Winter, 1980), p. 3.
  23. ^ a b c d Palfreman, Jon (1997). "Why the French Like Nuclear Energy". Frontline. Public Broadcasting Service. Retrieved 2007-08-25.
  24. ^ Lomazzi, Marc (13 August 2007). "Nucléaire: les dessous de l'accord entre la France et la Libye". Le Parisien (in Template:Fr icon).{{cite news}}: CS1 maint: unrecognized language (link)
  25. ^ a b c Tara Patel (Dec 2, 2011). "Atomic Spat Rocks French Election as Sarkozy Rival Backs Halts". Bloomberg. Cite error: The named reference "reu11" was defined multiple times with different content (see the help page).
  26. ^ "France to extend life of nuclear plants - minister". Paris: Reuters. 12 February 2012. Retrieved 10 March 2012.
  27. ^ The costs of the nuclear power sector - Summary in English (PDF) (Report). Cour des Comptes. January 2012. Retrieved 11 March 2012.
  28. ^ Henry Sokolski (Nov 28, 2011). "Nuclear Power Goes Rogue". Newsweek.
  29. ^ Présidentielle : Hollande confirme sa volonté de fermer Fessenheim France Soir, published 2012-05-02, accessed 2012-05-08
  30. ^ a b "Cinquième rapport national" (PDF). French Nuclear Safety Authority. July 2010. Retrieved 18 march 2011. {{cite web}}: Check date values in: |accessdate= (help)
  31. ^ "Nuclear Power in China". World Nuclear Association. 2 July 2010. Retrieved 18 July 2010.
  32. ^ "Facts about Olkiluoto 3 financing". olkiluoto.info. Retrieved 2009-07-10.
  33. ^ "New French nuclear to include oil interest". World Nuclear News. January 30, 2009. Retrieved 2009-01-31.
  34. ^ "ITER nuclear fusion reactor to be built in Southern France". PHYSORG. 28 Juin 2005. {{cite news}}: Check date values in: |date= (help)
  35. ^ Robin Pagnamenta (3 July 2009). "France imports UK electricity as plants shut". London: The Times. Retrieved 2009-07-10.
  36. ^ a b Mycle Schneider (11 April 2012). "Nuclear power post-Fukushima: Maybe France no exception after all". Kyodo News. Retrieved 27 April 2012.
  37. ^ Karolin Schaps (Feb 14, 2012). "Germany powers France in cold despite nuclear u-turn". Reuters.
  38. ^ Benjamin K. Sovacool. A Critical Evaluation of Nuclear Power and Renewable Electricity in Asia, Journal of Contemporary Asia, Vol. 40, No. 3, August 2010, pp. 393–400.
  39. ^ Benjamin K. Sovacool (2009). The Accidental Century - Prominent Energy Accidents in the Last 100 Years
  40. ^ "INES - The International Nuclear and Radiological Event Scale" (pdf). International Atomic Energy Agency. 2008-08-01. p. 2. Retrieved 2011-03-13.
  41. ^ Les Echos - 18/03/11 - A Saint-Laurent, EDF a renoncé à construire une digue contre les inondations Les Echos, published 2011-03-18, accessed 2011-03-30
  42. ^ Angelique Chrisafis (10-7-2008). "River use banned after French uranium leak". London: The Guardian. Retrieved 10-7-2008. {{cite news}}: Check date values in: |accessdate= and |date= (help)
  43. ^ "France bans water consumption over nuclear leak". 2008-07-09. Retrieved 2008-07-24.
  44. ^ Samuel, Henry (2008-07-24). "French nuclear leak prompts urgent security review". London: Telegraph.co.uk. Retrieved 2009-11-01.
  45. ^ a b c Zonage sismique de la France Le Plan Séisme, accessed 2011-04-13
  46. ^ a b Quatre centrales sur une zone sismique Les quatre éléments published 2011-03-15, accessed 2011-04-13
  47. ^ Evaluation de l’aléa sismique - La réglementation applicable aux sites nucléaires français Institut de radioprotection et de sûreté nucléaire, accessed 2011-04-13
  48. ^ a b c Centrale Nucléaire de Fessenheim : appréciation du risque sismique RÉSONANCE Ingénieurs-Conseils SA, published 2007-09-05, accessed 2011-03-30
  49. ^ "Get tough on nuclear safety". Nature. 12 January 2012 (481,113). {{cite web}}: Check date values in: |date= (help)
  50. ^ Declan Butler (11 January 2012). "France 'imagines the unimaginable'". Nature.
  51. ^ a b Majority of French want to drop nuclear energy-poll Reuters, published 2011-04-13, accessed 2011-04-13
  52. ^ "BBC World Service Poll". Retrieved 2010-04-28.
  53. ^ a b "Nuclear Notes from France Nº70". Embassy of France. 2001-10-04. {{cite web}}: |access-date= requires |url= (help); |archive-url= requires |url= (help); Missing or empty |url= (help)
  54. ^ Rene de Preneuf. "Nuclear Power in France — Why does it Work?". Archived from the original on 2007-08-13. Retrieved 2007-08-25.
  55. ^ Herbert P. Kitschelt. Political Opportunity and Political Protest: Anti-Nuclear Movements in Four Democracies British Journal of Political Science, Vol. 16, 1984, p. 71.
  56. ^ Thousands march in Paris anti-nuclear protest ABC News, January 18, 2004.
  57. ^ "French protests over EPR". Nuclear Engineering International. 2007-04-03. Retrieved 2007-04-10. {{cite news}}: Cite has empty unknown parameter: |coauthors= (help)
  58. ^ "France hit by anti-nuclear protests". Evening Echo. 2007-04-03. Retrieved 2007-04-10. {{cite news}}: Cite has empty unknown parameter: |coauthors= (help)
  59. ^ Arnaud Bouvier (Apr 25, 2011). "Thousands in France mark Chernobyl with protests". AFP.
  60. ^ "Thousands of Protesters Obstruct Nuclear Waste Transport". Spiegel Online. 11/28/2011. {{cite web}}: Check date values in: |date= (help)
  61. ^ Richard Black (10 November 2011). "EDF fined for spying on Greenpeace nuclear campaign". BBC. Retrieved 11 November 2011.
  62. ^ "Anti-nuclear demos across Europe on Fukushima anniversary". Euronews. 11 March 2011.
  63. ^ "Austria expects EU anti-nuclear campaign this year". Reuters. Mar 12, 2012.
  64. ^ "Nuclear energy and the green house effect". AREVA NC. Retrieved 2007-08-25.
  65. ^ "France's nuclear response to Kyoto". BBC. 2005-02-18. Retrieved 2007-08-25.

External links