Eglinton Crosstown line

From Wikipedia, the free encyclopedia
Jump to: navigation, search
Eglinton Crosstown Line
TTC - Line 5.svg
Looking down on the opening of the TBM, 2013 04 09 -aa--al.jpg
The underground portion of the line under construction
Overview
Type Light rail
Status Under construction
Locale Toronto, Ontario
Termini Kennedy
Mount Dennis
Stations 25
Operation
Opening 2020–2023 (expected)[1]
Owner Metrolinx
Operator(s) Toronto Transit Commission[2]
Depot(s) Black Creek Carhouse
Rolling stock Flexity Freedom
Technical
Line length 19 km (12 mi)
Track gauge 1,435 mm (4 ft 8 12 in) standard gauge
Electrification 750V DC overhead [3]
Operating speed 80 km/h
Route map
Mount Dennis
Kitchener GO
← to Union
to Kitchener
Black Creek Maintenance Facility
Black Creek Drive
Black Creek
Keele
Barrie GO
← to Union
to Allandale Waterfront
Caledonia
Dufferin
Oakwood
Eglinton WestBSicon SUBWAY.svg TTC - Line 1 - Yonge-University-Spadina line.svg Spadina line
← to Finch via Union
to Downsview
Bathurst
Chaplin
Avenue
EglintonBSicon SUBWAY.svg TTC - Line 1 - Yonge-University-Spadina line.svg Yonge line
[[s|← to Downsview via Union]]
[[s|to Finch →]]
Mount Pleasant
Bayview
Laird(formerly Brentcliffe)
Don River (West branch)
Leslie
CP Don branch
Don Mills
Ferrand
Don Valley Parkway
Wynford
Don River (East branch)
Richmond Hill GO
← to Union
to Richmond Hill
Bermondsey
Victoria Park
Pharmacy
Lebovic
Warden
Birchmount
Ionview
KennedyBSicon SUBWAY.svg TTC - Line 2 - Bloor-Danforth line.svg Bloor–Danforth line GO Transit logo.svg  G 
Stouffville GO
← to Union via Kennedy
to Lincolnville
BSicon ICTS.svg TTC - Line 3 - Scarborough RT line.svg Scarborough RT

The Eglinton Crosstown Line or Line 5 is a light rail line under construction in Toronto, Ontario, Canada, to be owned by Metrolinx and operated by the Toronto Transit Commission (TTC). It was conceived in 2007 by then Toronto Mayor David Miller and then chair of the TTC Adam Giambrone as part of Transit City, a large-scale transit expansion plan consisting of other proposed light rail transit lines.

Upon election of Rob Ford as mayor, a proposal was made to build the line fully underground as a rapid transit line, part of the Toronto subway and RT. After public debate about whether the line should be entirely underground or partially underground, Toronto City Council and Metrolinx decided to build the line according to the 2009 Transit City plan as a light rail line only partially underground, between Mount Dennis in York and Kennedy in Scarborough. Extending the line westward to Toronto Pearson International Airport has been part of the line's future expansion plans.

History[edit]

Concept[edit]

See also: Transit City

The Eglinton Crosstown Line was conceived as the Eglinton Crosstown LRT, a partially underground light rail line, announced in 2007 by Toronto Mayor David Miller and TTC chair Adam Giambrone. It was part of the Transit City plan, which included the implementation of six other light rail lines across Toronto. The original version of the line would have run from Pearson Airport along Silver Dart Road to Convair Drive. The line would have then turned southwest, bridging over Highway 401 to reach Commerce Boulevard on the other side, where it would run south to reach Eglinton Avenue and the east end of the Mississauga Transitway. The rest of the line would run east along Eglinton Avenue, including a portion along which the proposed Eglinton West subway line would have been built. The line would then cut across the city, intersecting every subway and RT line, except for the Sheppard line.

There were 43 stops planned for the Eglinton Crosstown LRT, 13 of which would be underground.[4] Surface stops would be spaced on average 500 metres (550 yd) apart and the underground stations would be 850m apart on average, as constructing numerous underground stops would be costly. The average speed would be 28 kilometres per hour (17 mph),[5] compared with the existing bus routes along Eglinton that have an average speed of 16 to 18 km/h (9.9 to 11.2 mph).[6] The line would terminate at Kennedy Station to the east in Scarborough where it would meet the Bloor–Danforth subway, the proposed Scarborough Malvern LRT and the Stouffville GO train line. The expected cost was $4.6 billion.[7] As a result of provincial funding cuts, construction of the line was divided into two phases: Phase One would end at Jane Street, and Phase Two would terminate as originally planned at Pearson Airport.

Redesigns[edit]

Miller's successor, Rob Ford, announced the cancellation of Transit City on 1 December 2010, the day he took office.[8] He redesigned the line and referred it to the "Eglinton–Scarborough Crosstown line", which put the 19-kilometre line along Eglinton Avenue completely underground. The line would then follow a renovated route of the Scarborough RT, thus forming a single line contiguously from Black Creek Drive to McCowan. The cost would almost double to $8.2 billion and, compared to the original plan, 18 fewer stops were planned. Most of the additional cost comes from putting 12 additional stations underground and for converting the Scarborough RT.

On 8 February 2012, in a special meeting, Toronto City Council, led by Karen Stintz, voted 25–18 to override Mayor Ford's modifications to the project.[9] The vote reinstated the original proposal to only construct the portion between Laird Drive and Keele Street underground while the remainder of the line is built along the surface.[9] On 30 November 2012, the environmental assessment was revised, such that the east tunnel portal location would be moved from east of Brentciffe to east of Don Mills,[10] however this was reversed in May 2013 after receiving community feedback.[11] In January 2013, Toronto City Councillors from Scarborough put forward an alternative plan to proceed with the construction of the Eglinton Avenue portion of the line as planned, but to exclude the Scarborough RT from the line. In July 2013, plans for an "Eglinton-Scarborough Crosstown" line were abandoned, thereby reverting the entire line back to its originally conceived plan under Transit City.[12][13]

Construction[edit]

The logo for the line.

The Eglinton Crosstown Line will run for 19 km (12 mi) from Black Creek Drive to Kennedy Station.[3] The line will run underground for 10 km (6.2 mi) before rising to the surface east of Brentcliffe Avenue.[14] There will be up to 26 stations, with an estimated 100 million trips annually in 2031.[15] The Presto card will be available for use across the line. The first part of tunnel construction involves the construction of a launch shaft for tunnel boring machines (TBMs) at Black Creek Drive, which began on October 2011. Metrolinx ordered four TBMs at a cost of $54 million on July 28, 2010.[16] These TBMs were expected to commence midtown tunneling in mid-2012.[17] However, the start was delayed to June 2013. The average excavation rate for a single machine is 75 metres (246 ft) a week of lined tunnel.

On 9 November 2011, in Keelesdale Park, Mayor Rob Ford and then-Premier Dalton McGuinty officially broke ground on the new project.[18] In addition, tunnel boring machines have arrived on February 22, 2013 in Keelesdale Park.[19] They are named Dennis, Lea, Humber, and Don. The names were chosen by Jason Paris, a moderator of the Urban Toronto blog and forums. Dennis is named after Mount Dennis, Lea is named after Leaside, Humber is named after the Humber River, and Don is named after the Don River. The names Dennis and Lea combined allude to the poet Dennis Lee.[20][21]

In January 2013, Infrastructure Ontario issued a request for qualifications to shortlist companies to construct the line. A request for proposal is expected in the summer of 2013.[22] Construction on the line began in June 2013.[23] As of 13 August 2014, Dennis is one block east of Dufferin Street, while Lea is one block west of Dufferin Street at Dynevor Road.[24]

The two western tunnel boring machines, Dennis and Lee started work in April 2013.[25]

Clearing the site where the two eastern tunnel boring machines, Don And Humber, will be installed, began in March 2014. They are scheduled to begin operation in the summer of 2014.

A segment of Eglinton will be dug up to extract the tunnel boring machines, when they reach Yonge Street, projected to be in 2016.[25]

Route[edit]

Stations[edit]

The following is the list of stops proposed as of 2013:[26]

Stop Type Description
Mount Dennis Underground See main article. Connection to GO Transit logo.svg Kitchener line
Keele Underground See main article
Caledonia Underground See main article. Potential GO Transit logo.svg Barrie line connection
Dufferin Underground See main article.
Oakwood Underground See main article.
Eglinton West Underground See main article. Connection to TTC - Line 1 - Yonge-University-Spadina line.svg University–Spadina line
Bathurst Underground See main article.
Chaplin Underground See main article.
Avenue Underground See main article.
Eglinton Underground See main article. Connection to TTC - Line 1 - Yonge-University-Spadina line.svg Yonge line
Mount Pleasant Underground See main article.
Bayview Underground See main article.
Laird Underground See main article.
Leslie At grade Westernmost of the at grade stops. Side platforms east of Leslie Street.[27]
Don Mills Underground See main article.
Ferrand At grade Side platforms west of Don Valley Parkway.[28]
Wynford At grade Side platforms on opposite sides of a new pedestrian crosswalk, which will cross Eglinton west of the bridge over Wynford Drive.[29] GO Transit's Richmond Hill line crosses under Eglinton a short diatance to the east, but no contingency has been made for a connection.
Bermondsey At grade Centre platform east of Bermondsey Road/Sloane Avenue.[30]
Victoria Park At grade Side platforms east from Victoria Park Avenue to O'Connor Drive.[31]
Pharmacy At grade Side platforms east of Pharmacy Avenue.[32]
Lebovic At grade Side platforms on opposite sides of Lebovic Avenue/Hakimi Avenue.[33]
Warden At grade Side platforms on opposite sides of Warden Avenue.[34]
Birchmount At grade Side platforms east of Birchmount Road.[35]
Ionview At grade Side platforms west of Ionview Road.[36]
Kennedy Underground See main article. Connection to TTC - Line 2 - Bloor-Danforth line.svg Bloor–Danforth line and GO Transit logo.svg Kennedy GO Station for Stouffville line

Operations[edit]

Here are some operating characteristics of the line:

  • Metrolinx intends to use automatic train control on the underground section of Eglinton Crosstown.[37]
  • On the surface, light rail vehicles will be in dedicated right-of-way transit lanes separate from regular traffic.[5]
  • On the surface, light rail vehicles will have priority signalling at intersections to ensure certainty in travel times.[5]
  • Light rail vehicles can travel as fast as 80 kilometres per hour (50 mph). However, actual speed is determined by the spacing of the stops and the speed limits of surrounding road traffic on the surface. Crosstown vehicles will have an average speed of 28 kilometres per hour (17 mph).[5]
  • The projected ridership of the line is 5,400 passengers per hour in the peak direction by 2031. The capacity of the vehicles is 15,000 passengers per hour per direction.[5]

See also[edit]

References[edit]

  1. ^ Chu, Showwei (29 May 2012). "Eglinton LRT unlikely to meet 2020 completion date: TTC report". Citytv News (Toronto). Archived from the original on 2012-09-09. 
  2. ^ Consiglio, Alex (3 October 2012). "TTC to operate city’s new LRT lines". Toronto Star. Retrieved 2012-11-01. 
  3. ^ a b "Eglinton LRT 2012 update". Metrolinx. February 2012. Retrieved 2013-11-01. 
  4. ^ "Eglinton Crosstown Light Rail Transit stops and stations" (PDF). City of Toronto. November 2010. Retrieved 2011-07-30. 
  5. ^ a b c d e "Eglinton Crosstown Backgrounder". Metrolinx. Retrieved 2013-11-08. 
  6. ^ Spears, John (9 August 2008). "Distance between LRT stops criticized". Toronto Star. Retrieved 2008-08-14. 
  7. ^ "Eglinton Transit City line may survive". CBC. 4 January 2011. Retrieved 2011-04-24. 
  8. ^ D'Cruz, Andrew (1 December 2010). "Mayor Rob Ford: "Transit City is over"". Toronto Life. Retrieved 2014-08-04. 
  9. ^ a b Kalinowski, Tess; Dale, Daniel (9 February 2012). "Special transit meeting: Mayor Rob Ford dismisses council’s vote against his subway plan". Toronto Star (Toronto). Archived from the original on 2012-09-09. 
  10. ^ http://thecrosstown.ca/news-media/whats-new/Online-Consultation-Laird-Don-Valley
  11. ^ Kalinowski, Tess (12 May 2013). "Metrolinx puts Leslie back on the Crosstown map". Toronto Star. Retrieved 8 November 2013. 
  12. ^ Kalinowski, Tess (6 May 2013). "Scarborough councillors seek subway line instead of LRT: A group of Toronto councillors wants to replace the planned LRT for Scarborough with a subway. But a subway would cost $500 million more". Toronto Star. Archived from the original on 2013-07-03. Retrieved 2013-07-03. "An LRT would use the same route as the SRT. It would be 9.9 km versus 7.6 km of subway. The LRT would have seven stations, the subway, only three." 
  13. ^ Kalinowski, Tess (17 January 2013). "TTC report threatens to reopen Scarborough subway debate: One commissioner says it's proof Scarborough can have a new subway line under construction within the decade, but Metrolinx dismisses that". Toronto Star. Archived from the original on 2013-07-03. Retrieved 2013-07-03. "Glenn DeBaeremaeker (Ward 38, Scarborough Centre) said the latest TTC report gives him new confidence that there will be a subway underway in Scarborough within a decade." 
  14. ^ "City of Toronto: Get Involved > Eglinton Crosstown Light Rail Transit (LRT) > Frequently Asked Questions > Stations and Stops". City of Toronto. 20 August 2011. Retrieved 2011-10-24. 
  15. ^ "Eglinton-Scarborough Crosstown Update" (pdf). Metrolinx. 23 June 2011. 
  16. ^ Kalinowski, Tess (28 July 2010). "Metrolinx orders tunneling machines". Toronto Star. 
  17. ^ "TTC Construction Update". Toronto Transit Commission (TTC). June 2011. 
  18. ^ Alcoba, Natalie (9 November 2011). "Ford, McGuinty get up-close look at Eglinton LRT construction". National Post. Retrieved 2014-08-04. 
  19. ^ Kalinowski, Tess (22 February 2013). "Eglinton Crosstown LRT tunneling a step closer". Toronto Star (Toronto Star Newspapers Ltd.). Retrieved 2014-08-04. 
  20. ^ http://thecrosstown.ca/news-media/whats-new/announcing-the-winning-names-of-the-tunnel-boring-machine-naming-contest
  21. ^ http://urbantoronto.ca/news/2013/06/eglinton-crosstown-tbms-get-personality-and-send
  22. ^ "Request for Qualifications Issued for the Eglinton Crosstown LRT and Scarborough LRT Lines". Infrastructure Ontario. 22 January 2013. Retrieved 2013-03-10. 
  23. ^ "Machines begin tunnelling for Eglinton Crosstown LRT". CBC. 5 June 2013. Retrieved 2013-07-05. 
  24. ^ Eglinton Crosstown TBM Tracker
  25. ^ a b Winsa, Patty (21 March 2014). "Metrolinx begins its big eastern dig on the Eglinton Crosstown LRT: Get ready for traffic". Toronto Star. Archived from the original on 2014-03-23. "Parts for the next two tunnel-boring machines to work on digging underground parts of the line — nicknamed Don and Humber — will arrive this summer and be assembled in the shaft, before they start drilling the 3.25-kilometre section west to Yonge St." 
  26. ^ "Stations and Stops". Metrolinx. Retrieved 2013-11-17. 
  27. ^ "Leslie Stop". Eglinton Crosstown. Retrieved September 2014. 
  28. ^ "Ferrand Stop". Eglinton Crosstown. Retrieved September 2014. 
  29. ^ "Wynford Stop". Eglinton Crosstown. Retrieved September 2014. 
  30. ^ "Bermondsey Stop". Eglinton Crosstown. Retrieved September 2014. 
  31. ^ "Victoria Park Stop". Eglinton Crosstown. Retrieved September 2014. 
  32. ^ "Pharmacy Stop". Eglinton Crosstown. Retrieved September 2014. 
  33. ^ "Lebovic Stop". Eglinton Crosstown. Retrieved September 2014. 
  34. ^ "Warden Stop". Eglinton Crosstown. Retrieved September 2014. 
  35. ^ "Birchmount Stop". Eglinton Crosstown. Retrieved September 2014. 
  36. ^ "Ionview Stop". Eglinton Crosstown. Retrieved September 2014. 
  37. ^ Munro, Steve. "Metrolinx Announces Design Changes and Public Meetings on Eglinton LRT (Update 8)". Steve Munro. Retrieved 2013-06-17. 

External links[edit]