==2007 Track renewals== |
|||
Due to the age and condition of most of the track on the Bury and Altrincham routes it was decided that the mostly 1960s trackwork was to be relaid. This construction work included improvements to stations along the lines. |
|||
'''Bury Line''' |
|||
The renewals commenced on [[29 May]] [[2007]] with the cessation of services between Bury and Whitefield. By [[22 June]] [[2007]] services on the Bury line terminated at Crumpsall. By [[23 July]] [[2007]] there was no service on the Bury line as all northbound Metrolink trams in public use terminated at Victoria. The Bury Line re-opened on [[13 September]] [[2007]]. |
|||
'''Altrincham Line''' |
|||
With the possible exception of the section between Stretford and Dane Road, the track along this route was not as worn as that on the Bury line and so not as much work was required. From [[2 July]] [[2007]] various sections of the line were shut down and serviced with a replacement bus service. The Altrincham Line re-opened on [[28 August]] [[2007]]. |
|||
As of mid-September 2007 all tram services were back in operation, the work having been completed on time. Since the track renewals the ride is much smoother and quieter than before. |
|||
==Changes to the system since original construction== |
==Changes to the system since original construction== |
Revision as of 22:08, 23 December 2007
This article needs additional citations for verification. (June 2007) |
Manchester Metrolink | |
---|---|
File:Stagecoachmetro.gif | |
Overview | |
Locale | Greater Manchester |
Transit type | Electrified (750 V DC) Tramway |
Number of lines | 3 |
Number of stations | 37 |
Daily ridership | 52,000 (19 million annually) in 2004 |
Operation | |
Began operation | 1992 |
Operator(s) | Stagecoach Group (since July 2007) |
Technical | |
System length | 37 km (23 miles) |
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) (standard gauge) |
Manchester Metrolink is an urban light-rail system in Greater Manchester, England centred on Manchester City Centre. It operates services to the towns of Bury, Altrincham and Eccles.
Metrolink is operated by Stagecoach Group, on behalf of GMPTE. The Metrolink network is approximately 23 miles (37 km) long, with 37 stops along the route. Because much of the Metrolink route was formerly main-line railway with platforms about 900 mm above ground level, the new stops in the city centre also have 900 mm-high platforms.
Many more extensions to the Metrolink System are planned providing funding can be found. The ambitious "Big Bang", now named Phase 3 would take services to Oldham and Rochdale, Ashton-under-Lyne, Stockport, Manchester Airport and to the Trafford Centre.
Construction history
For many years there had been plans to connect Manchester's two main railway stations, Piccadilly station to the south-east of the city centre, and Victoria station to the north. In the late 1960s and early 1970s, there were plans for a Picc-Vic tunnel to carry main-line trains, but the proposal was abandoned because of excessive cost. By the late 1980s, the power equipment on the electrified suburban railway line from Victoria to Bury, which had a unique-in-Britain side-contact third-rail power supply, was in need of replacement, and it was decided, rather than replace the equipment on a like-for-like basis, to construct a light rail system that would connect the Victoria–Bury line via on-street lines with the line to Altrincham, south-west of the city, and in the city centre to Piccadilly station.
Phase 1
The Metrolink lines were formed by closing two electric train lines to trains between Altrincham and Cornbrook Junction (former Manchester South Junction and Altrincham Railway, electrified in 1931) and between Bury and Manchester Victoria, electrified by the Lancashire and Yorkshire Railway in 1916. This meant that trains ceased to operate to Bury and trains arriving at Altrincham from Knutsford, Northwich and Chester are diverted to Manchester via Stockport, adding at least 10 minutes to an already slow journey.
The disbenefits of Metrolink's creation to the rail users of south Manchester and north Cheshire were considerable and remain so today (2007).
Authority to construct Phase 1 of Metrolink (Bury to Altrincham via city centre, with a spur to Piccadilly station) was granted in January 1988, with construction of the on-street section beginning in March 1990. Metrolink opened between Bury and Victoria on 6 April 1992, through the city centre between Victoria and G-Mex (the former Manchester Central railway station, now an exhibition centre) on 27 April 1992, and between G-Mex and Altrincham on 15 June 1992. The system was formally opened by Queen Elizabeth II on 17 July 1992, and trams started operating into Piccadilly station on 20 July 1992, completing Phase 1 of the system.
In each case, conversion of the existing railway lines to Metrolink took far longer than had been indicated by Metrolink's promoters and local politicians alike. The Altrincham line was closed for 6 months, rather than one month as promised, with bus substitution during that period. Metrolink initially indicated that the cause was trackwork in poorer condition than expected, but no substantiating evidence was ever produced, nor was any claim ever made against the former operator. In contrast, Metrolink's own new trackwork in Manchester's city centre required reinstalling twice in the first years of operation, due to inadequate quality controls and poor design work, such as placing switches directly where the blades could be expected to be repeatedly crossed by buses.
Phase 2
On 25 April 1997 work began on Phase 2, an extension from Cornbrook, on the Altrincham line, through Salford Quays to Eccles. Service started as far as Broadway on 6 December 1999 and to Eccles on 21 July 2000.
Planning permission was granted in October 2007 for a 400-metre long extension from a point between Harbour City and Broadway to the central plaza of the new Mediacity:uk development.[1]
Routes
Metrolink's Monday-Saturday service:
- Piccadilly station – Altrincham
- Piccadilly station – Bury
- Piccadilly station – Eccles
- Altrincham – Bury (Daytime only) (not via Piccadilly Gardens and Piccadilly station)
Metrolink's Sunday & Bank Holiday service:
- Piccadilly station – Altrincham
- Piccadilly station – Bury
- Piccadilly station – Eccles
The direct Altrincham-Bury (avoiding Piccadilly) service does not operate on Sundays. Passengers are required to change at Piccadilly Gardens.
Frequency on each service is every 12 minutes, but the interleaving of the Altrincham – Bury direct service with the services to Piccadilly Station mean that for much of the route there are two trams every 12 minutes, usually three and nine minutes apart.
Between Cornbrook and St Peter’s Square, with three services (Altrincham-Bury, Altrincham-Piccadilly and Eccles-Piccadilly) running every 12 minutes, the frequency is increased even more.
The current route length is:
Phase 1 | |
---|---|
Bury – Victoria | 9.9 miles (15.9 km) |
Victoria – G-Mex | 1.9 miles (3.1 km) |
Spur to Piccadilly station | 0.4 miles (0.6 km) |
G-Mex – Altrincham | 6.5 miles (10.5 km) |
Phase 2 | |
Cornbrook – Broadway | 1.9 miles (3.1 km) |
Broadway – Eccles | 2.2 miles (3.5 km) |
Transport Interchanges
Passenger rail interchanges are situated along the Metrolink route. These include Piccadilly, Victoria station, G-mex for Deansgate, Altrincham, Navigation Road and Eccles.
Major bus interchanges are also situated at Bury, Whitefield, Victoria, Shudehill, Piccadilly Gardens, Altrincham and Eccles Metrolink Stations.
Tram stop list
Bury Line | Altrincham Line | Eccles Line |
---|---|---|
|
|
Depots
The first Metrolink’s depot is located south of Queen’s Road (Cheetham Hill, M8) on the western side of the Bury line, between Victoria and Woodlands Road stops. The depot connections face Bury. There is a staff halt, Queens Road, serving the depot [2]. This facility will not be able to handle the expanded network, therefore GMPTE have obtained the site for a second depot, near Old Trafford stop [3].
Fare structure
Fares are charged depending on the number of fare zones travelled through, and whether travel is in the peak period - before 09:30 on a weekday, except on public holidays. The zones are shown above.
Tickets are purchased from machines at each stop. Single journeys must be completed within 90 minutes, return journeys the same day. It is also possible to purchase tickets from the machines for travel all day, for groups, or all weekend. Some ticket machines accept only coins; the others will also accept banknotes, and give a maximum of £7 in change. Train users travelling into the city centre from stations in Greater Manchester are able to use the Metrolink in the central zone for free. These train tickets can be used between Victoria, Shudehill, Market Street, Piccadilly Gardens, Piccadilly, Mosley Street, St Peter's Square and G-Mex. [4]
All Metrolink tickets must be purchased before travel. A "standard fare" of upto £80 is charged for travelling without a ticket[1].
Metrolink staff often perform random ticket checks at mainline train stations with the presence of Greater Manchester Police, a ploy to tackle the aggressive fare dodgers.
Policing
Metrolink is policed by both the Greater Manchester Police, and the British Transport Police. The British Transport Police and British Transport Police Community Support Officers often travel on the trams between Manchester Piccadilly railway station, Manchester Victoria railway station and Altrincham station.
An initiative by Greater Manchester Police, which saw around 15 officers routinely patrolling the tram network, was stopped due to lack of funds. On-board ticket checks are done by Carlisle Security on behalf of the GMPTE.
Vehicles
As of December 2007 the Metrolink fleet consists of 26 Italian-built T-68 light-rail vehicles (LRV) built in 1991 and numbered in the 1000 series, and six T68a vehicles built in 1999 for the Eccles extension and numbered in the 2000 series. The LRVs are articulated in the centre and normally operate singly, except during the rush hours when there are a few double trams along the Bury–Altrincham route. Three 1000-series trams (1005, 1010, and 1015) and all 2000-series trams are modified for use on the Eccles line, which involves large amounts of street running, with retractable and covered couplers and covered bogies.
In April 2007, eight new trams were ordered for the Metrolink. These will be Flexity Swift high-floor trams based on the K5000 series currently employed in the German cities of Cologne and Bonn, and similar to the low-floor models already used by London’s Tramlink. When delivered in 2009 these 8 new trams will enable all the Bury - Altrincham direct services to operate as double trams, significantly increasing capacity. A further 4 trams of the same type have now been ordered by the GMPTE to allow for a new 12-minute service between Cornbrook and the new Mediacity:uk extension. [5]
Technical data (T68 and T68a trams)
The trams (bi-directional: with cabs at both ends and doors on both sides), are 30 m long and consist of two carriages, joined by an articulated section in the middle, with four doors per side. The front and rear bogies are powered, with two 750V, 105kW motors per bogie. The third bogie, located under the articulated part, is not powered. The maximum speed is 80km/h, with 50 km/h allowed for street running.
There are 83 seats per vehicle (plus 4 folding seats) and the nominal capacity is 200 passengers (250 maximum). Trams normally run singly, but up to four units can be operated by one driver.
List of Trams by name and number
Twenty-three of the trams have name plates, named after famous Mancunian people, achievements or places.
List of tram numbers and names |
---|
|
Patronage
Metrolink carried 18.8 million passengers in 2004, compared to 7.5 million who used the Bury and Altrincham rail services before Metrolink. According to Metrolink sources, at least two million fewer car journeys have been made each year along the tram route.
Metrolink has become something of a victim of its own popularity. Many services are extremely busy, especially at peak times at the city centre stations, and fares have risen at a rate far above that of inflation.
In the first two years of Metrolink operation, peak hour patronage was well below expected levels, but off-peak patronage exceeded expectations. Metrolink reacted by reducing peak fares which improved loadings.
Changes to the system since original construction
There have been a few modifications to the system since the opening of Phase I in 1992.
- Originally the stop in Market Street handled trams to Bury only, and the one around the corner in High Street handled trams from Bury only. When Market Street was closed to road traffic these stops were replaced by a new platform stop in the centre of Market Street, which handles trams in both directions. This stop opened on 10 August 1998.
- Crossover points were installed in the section approaching Piccadilly Station in order to allow inbound trams to access either platform without having first to proceed to the buffer stops at the far end of the Undercroft area; this in order to facilitate quicker tram turnaround times. This mode of operation seems to have been discontinued in recent years, however.
- Shudehill Interchange between Victoria station and Market Street opened in April 2003. The bus station complementing it opened on 29 January 2006.
- Cornbrook station on the Altrincham line was opened to provide an interchange with the new line to Eccles. There was initially no official public access to this station from the street, but this changed on 3 September 2005.
- On 15 July 2007 Stagecoach took over as the Metrolink operator from Serco.
Phase 3
Template:Future uk public transportation
The initial Metrolink network was formed of two converted railway lines, linked across the city centre (Phase 1). Since opening in 1992, one extension has been completed to the Salford town of Eccles via Salford Quays (Phase 2). Metrolink Phase 3, also known as the Big Bang, was an ambitious expansion programme which would have seen trams running to Oldham, Rochdale, Ashton-under-Lyne, Wythenshawe and Manchester Airport.
Phase 3a
Phase 3 has now been split into two sections: Phase 3a will involve taking over the main line railway to Oldham and Rochdale station, as well as extensions to Droylsden and to Chorlton-cum-Hardy. In December 2004 the government announced that £520 million would be authorised for Phase 3. A first stage of Phase 3 was given the go ahead by the Department for Transport in July 2006, with a £300m funding gap expected to be met by a loan. Phase 3a will begin construction in 2008 and is hoped to become operational in 2011/12.
Phase 3b
The second part of Phase 3, referred to as Phase 3b, will take the lines into Oldham and Rochdale town centres, Ashton-Under-Lyne, Didsbury and Manchester Airport.
Phase 3b forms part of Greater Manchester’s integrated transport strategy, which will recommend a package of transport investment and traffic management measures. In July 2007 GMPTE, along with AGMA submitted a bid to the Governments Transport Innovation Fund to secure the funding for this package which, if received, will guarantee the extensions to these destinations.
The outcome of this bid for funding will be known early in 2008.
Further extensions are also planned, continuing from Didsbury to onto Stockport, Mediacity at Salford Quays and to the Trafford Centre in Trafford Park. The Trafford Park line will continue on from Pomona viaduct on the Eccles line which has been built with the expansion in mind. The new line is expected to serve the Manchester United home ground at Old Trafford and Imperial War Museum North.
Concerns have been raised regarding the single route through the city centre which may become a bottleneck when new extensions are open - with six or seven services all running over the same track, questions have been raised about the possibility of a 'tram-jam'. The other issue is that the focus of the city centre is moving to quarters not currently served by Metrolink. GMPTE have reacted to this with an aditional favored line down Cross Street between GMex and Victoria. GMPTE say the line would also aid the city with additional tram stops, possibly around the Town Hall and Arndale Shopping Centre areas.
Project | Length | New trams required |
---|---|---|
Extension spur from Harbour City to Mediacity funded jointly by Peel Holdings and North West Development Agency, service to run between Cornbrook and Mediacity every 12 minutes | 0.25 miles (0.4 km) | 4 |
Additional route across Manchester city centre between Central and Victoria | 1 mile (1.6 km) | N/A |
Conversion of existing railway from Victoria to Oldham and Rochdale (plus some street running) | 14.9 miles (24.0 km) | 22 |
Extension to Manchester Airport | 13 miles (20.9 km) | 26 |
Extension to Ashton-under-Lyne | 6.2 miles (10.0 km) | 9 |
Extension to East Didsbury (optional, with possible further extension to Stockport) | 8.7 miles (14.0 km) | 9 |
Extension to the Trafford Centre shopping centre, which will stop at Old Trafford Football Ground, Imperial War Museum for the North and Trafford Park subject to private-sector funding | 4.3 miles (6.9 km) | Not Yet Known |
Completion of Manchester Airport loop subject to private sector funding | 4 miles (6.4 km) | Not Yet Known |
A bid for Transport Innovation Fund monies towards the second stage, plus an additional city centre crossing, which would take the total cost of Phase III to an estimated £1.2 billion with a road charging scheme is expected to be included to cover some of the cost.[7]
A network including all the proposed expansions will increase the size from 23 miles (37 km) with 37 stops to 70 miles (113 km) with at least 115 stops.
Failings
Metrolink attracted significant negative publicity in its early days. Delays in construction, closures for rebuilding defective trackwork and lack of thought in ticketing and information systems all attracted criticism. Politically, the system was deemed to be an immediate success, though the tax burden on Greater Manchester's ratepayers increased notably, since Metrolink attracted subsidies the previous trains had not.
Many of the initial problems have been addressed during the years, but ticketing and passenger information remain major failings. Through ticketing beyond the Manchester suburban area is nonexistent for travellers from Metrolink stations (though possible travelling inbound from elsewhere in Great Britain), leading to significant fare increases on journeys involving the wider rail system. When the Altrincham and Bury services were part of the national rail network, through ticketing was obviously possible. In this respect, Metrolink might appear to suffer from the Balkanisation common to all local Metro services split from the national rail network.
One of the criticisms levelled at Metrolink is that it does not reach the Trafford Centre, other than via a shuttle bus from Stretford Metrolink stop, and travel on this shuttle bus is not covered by the MetroMax ticket that allows travel through the rest of the network. The line from Manchester city centre to Eccles is also disappointing, as it takes longer than an equivalent bus journey following a more direct route (not via Salford Quays), despite buses not being able to use the dedicated Metrolink infrastructure.
References
- ^ Williams, Tony (21 November 2007). "21 November 2007: Mediacity:UK and Enhanced Salford Quays Service". Light Rail Transit Association. Retrieved 2007-12-08.
{{cite web}}
: Check date values in:|date=
(help) - ^ "Bury line description". Retrieved 2007-12-20.
- ^ "New Metrolink depot". Retrieved 2007-12-20.
{{cite web}}
: Check|url=
value (help) - ^ "Free tram rides for Greater Manchester's train passengers". GMPTE.
- ^ "Mediacity:UK and Enhanced Salford Quays Service". Light Rail Transit Association.
- ^ 'Trams except 1018' List of Trams at British Trams Online
- ^ 'Metrolink wins a "Little Bang"', article in the Manchester Evening News
- Holt, D., (1992), Manchester Metrolink, UK Light Rail Systems No. 1, Platform 5 Publishing, ISBN 1-872524-36-2
See also
External links
- Metrolink Information page and Metrolink Development page from GMPTE
- Metrolink website
- Metrolink route map (69KB PDF file)
- Transport Briefing Latest Metrolink developments, including news of phase 3 expansion approved in July 2006
- TheTrams.co.uk Photographs of Metrolink trams.
- Collection of Google Earth locations of Metrolink stations (Requires Google Earth software) from the Google Earth Community forum.
- Manchester Metrolink, Tony Williams, Manchester Area Officer, Light Rail Transit Association
- Picc-Vic, Full history of SELNEC Manchester Urban Rapid Transit Plans
- Metrolink Virtual, Virtual Manchester Metrolink route project for MSTS
- Flash Movie of the new Alstom Metrolink Tram from Luminova.net
- Flash Picture of the new Alstom Metrolink Tram from Luminova.net
- Schematic Map of the new Metrolink Network (100 Kb PDF file)
- Articles needing cleanup from December 2007
- Cleanup tagged articles without a reason field from December 2007
- Wikipedia pages needing cleanup from December 2007
- Manchester Metrolink stations
- Electric railways
- Light rail in the United Kingdom
- Transport in Greater Manchester
- Transport in Manchester
- Tram transport in the United Kingdom
- Bury