Jump to content

Lindhurst Wind Farm

Coordinates: 53°06′58″N 01°08′48″W / 53.11611°N 1.14667°W / 53.11611; -1.14667
From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Rehman (talk | contribs) at 17:45, 25 March 2020 (Fix parameter errors. See Template:Infobox power station for the full list.). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Lindhurst Wind Farm
Map
CountryEngland, UK
LocationRainworth, Mansfield, East Midlands, Nottinghamshire
Coordinates53°06′58″N 01°08′48″W / 53.11611°N 1.14667°W / 53.11611; -1.14667
StatusOperational
Commission date10 September 2010 (10 September 2010)
Owner(s)Npower Renewables
Wind farm
TypeOnshore
Hub height60 m (197 ft)
Rotor diameter90 m
Site elevation120 m
Power generation
Units operational5
Make and modelVestas Wind Systems: Vestas V90
Nameplate capacity9 MW

Lindhurst Wind Farm is a wind farm located in Mansfield, England. The wind farm, which was built for Npower Renewables, produces electricity from five wind turbines. It has a total nameplate capacity of 9 MW of electricity, providing enough power to serve the average needs of 5,400 homes. The site occupies land between Mansfield and Rainworth in Nottinghamshire.

The wind turbines stand 125 metres (410 ft) high to the rotor tip, making them the tallest in Nottinghamshire.[citation needed]

History

Lindhurst Wind Farm was approved by the local planning committee at Newark and Sherwood District Council in September 2007. Local councillors voted 8-3 in favour of the application, which had been recommended for approval by the council's planning officer and supported by 3,300 local residents petition of support.[citation needed]

Preparatory work for the site began in 2008, with the wind turbines being erected in August 2010. The turbines went live on 10 September 2010.[citation needed]