Hyderabad Metro
Hyderabad Metro Rail | |||
---|---|---|---|
File:Hyderabad Metro logo1.jpg | |||
Overview | |||
Locale | Hyderabad, Telangana, India | ||
Transit type | Rapid transit | ||
Number of lines | 3 (Phase I) | ||
Number of stations | 66 (Phase I) | ||
Chief executive | NVS Reddy, MD[1] | ||
Headquarters | Metro Bhawan, Saifabad, Hyderabad | ||
Website | |||
Operation | |||
Operation will start | March 2015 | ||
Operator(s) | Hyderabad Metro Rail Ltd. (HMRL) | ||
Technical | |||
System length | 72.16 km (44.84 mi) (Phase I)[2] 97 km (60 mi) (Phase II) | ||
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge | ||
Electrification | 25kV, 50Hz AC overhead catenary | ||
Average speed | 34 km/h (21 mph) | ||
Top speed | 80 km/h (50 mph) | ||
|
![](http://upload.wikimedia.org/wikipedia/commons/thumb/5/52/Lnt-metrorail-hyderabad-girder.jpg/250px-Lnt-metrorail-hyderabad-girder.jpg)
![](http://upload.wikimedia.org/wikipedia/commons/thumb/b/b5/Hyderabad_Metro_Uppal_Station_under_construction_2.jpg/250px-Hyderabad_Metro_Uppal_Station_under_construction_2.jpg)
![](http://upload.wikimedia.org/wikipedia/commons/thumb/f/f6/Hyderabad_Metro_at_Uppal_01.jpg/250px-Hyderabad_Metro_at_Uppal_01.jpg)
![](http://upload.wikimedia.org/wikipedia/commons/thumb/7/7c/Hyderabad_Metro_at_KPHB_04.jpg/250px-Hyderabad_Metro_at_KPHB_04.jpg)
Hyderabad Metro Rail (HMR; Telugu: హైదరాబాద్ మెట్రో రైలు) is a rapid transit system, currently under construction, for the city of Hyderabad, Telangana.[3] It is in Secent Operational model. It is being implemented entirely on PPP mode, with the state government holding a minority equity stake.[4]
Awards and nominations
HMR project was showcased as one of the top 100 strategic global infrastructure projects at the Global Infrastructure Leadership Forum held in New York during February–March, 2013.[5][6]
The HMR project is considered to be the world’s largest project under public-private partnership[citation needed], with investments of over Rs 17,000 Crore.
Phase-1 of the Project was approved by the Union Government in April 2008 under Public-Private Partnership.[7] The total length of the first-phase after final revision is 71 km.
Construction Phases
The construction work will be undertaken in two phases. There are six stages of completion in Phase I.
Phase I
The Phase I of the project includes 3 lines covering a distance of around 71 km. The metro rail stretches between Nagole and Mettuguda (8 km) and between Miyapur and S. R. Nagar (12 km) are targeted to be operational by March 2015 as Ugadi gift.[8][9] In September 2012,
- Miyapur – L B Nagar - 29.87 km
- Nagole - Shilparamam - 26.51 km
- JBS – Falaknuma - 14.78 km
Six Stage Construction Schedule
Stage | Target Section | Distance (in km) | Line | Expected Completion date |
---|---|---|---|---|
Stage 1 | Nagole to Mettuguda | 8 | Line III | 21 March 2015 |
Stage 2 | Miyapur to S R Nagar | 11 | Line I | 15 August 2015 |
Stage 3 | Mettuguda to Begumpet | 10 | Line III | 14 November 2015 |
Stage 4 | Begumpet to Shilparamam | 9.51 | Line III | 15 August 2016 |
Stage 5 | SR Nagar to LB Nagar | 17.87 | Line I | 15 August 2016 |
Stage 6 | JBS to Falaknuma | 14.78 | Line II | 5 June 2017 |
Phase II
The Indian government is thinking for Phase II which is expected to start construction in 2015. It includes around 80 kilometers.[citation needed] Recently Government has sanctioned second phase of metro rail extending further 85 km.The proposed routes are as following:
- Miyapur - BHEL - Patanchervu 15 km.
- Faluknama - Shamshabad Airport 12 km.
- LB Nagar - Vanasthalipuram 4 km.
- Nagole - LB Nagar - Faluknama 15 km.
- JNTU - Shilparamam - Gacchibowli 14 km.
- JBS - Alwal 8 km.
- Gachibowli - ToliChowk - Lakdikapul 17 km.
TOTAL 85 km (Second Phase). The construction is yet to be started and might start at 2015. The total Metro rail coverage will be increased to 157 km (Including Second Phase).
Initial Bidding
The bidding process was completed by July 2008 and awarded to Maytas which failed to achieve financial closure for the project as per schedule By March 2009. In July 2009, the Andhra Pradesh Government canceled the contract and called for fresh bids for the project.
Re-bidding
In the July-2010 rebidding process, Larsen & Toubro (L&T) emerged as the lowest bidder for the ₹121.32 billion (US$1.5 billion) project. L&T came forward to take up the work for about ₹14.58 billion (US$170 million) as viability gap funding as against the sanctioned ₹48.53 billion (US$580 million).
Construction stage
Bhoomi Puja(shankusthapana) for the project was conducted on 26 April 2012 [10] the concessionaire started the pillar erection on the same day for Stage-I and on 6 June 2012 for Stage-II.[11] The work for Corridor 2 has been delayed due to traders in Koti and Sultan Bazar demanding realignment of the route to safeguard traders and age old heritage markets.[12]
Current Status
As of January 2015 end The Construction on line 3 is 95% completed with trial runs of the trains started, the construction of Nagole depot almost over, overhead traction lines laying started and on line -1 Construction of pillars maximum completed except at stretches mozam-zahi market to khirathabad. also viaduct construction is in full swing.
The construction of the entire 71.16 km has been split into 6 stages with the first stage scheduled to be completed by March 2015[13][14] with the entire project scheduled to be completed by July, 2017.[15][16]
In November 2013,L&T Hyderabad Metro started laying of rails on the metro viaduct between Nagole and Mettuguda, a stretch of 8 km.[17] Hyderabad Metro Rail will provide disabled-friendly system.[18][19]
The first train of the Hyderabad Metro Rail (HMR) came from Korea during the third week of May 2014. Stringent trial runs will commenced from June 2014 till February 2015, before the service on the first stage of the Nagole-Mettuguda sector is thrown open to the public on 21 March 2015.[20]
Three interchanges are planned at Mahatma Gandhi Bus Terminus, Parade Grounds and Ameerpet.[21]
Lines
Since the first version of the plans, the three corridors mostly remained the same, but minor changes were introduced. These include the lack of stop at Lalaguda, or a stop at Lakdikapul instead of Secretariat. Also, the lines have been marked with several different combination of colours.[22]
Line 1 (red): Miyapur – L B Nagar
Route Length — 29.87 kilometers
Number of Stations (All elevated) — 26
Link to other Corridors
- At Ameerpet – Connecting Corridors 1 and 3
- At Mahatma Gandhi Bus Station – Connecting Corridors 1 and 2
S.No | Station | S.No | Station |
---|---|---|---|
1 | Miyapur | 14 | Lakdi-ka-pul |
2 | JNTU College | 15 | Assembly |
3 | KPHB Colony | 16 | Nampally |
4 | Kukatpally | 17 | Gandhi Bhavan(Moazzam Jahi Market) |
5 | Moosapet | 18 | Medical College(Putli Bowli) |
6 | Bharatnagar | 19 | Imlibun(MG Bus Stand) |
7 | Erragadda Road | 20 | Malakapet |
8 | ESI Hospital | 21 | New Market(Super Bazaar) |
9 | S.R.Nagar | 22 | Musarambagh(TV Tower) |
10 | Ameerpet | 23 | Dilsukh Nagar |
11 | Punjagutta | 24 | Chaitanyapuri(Fruit Market) |
12 | Erra Manzil | 25 | Victoria Memorial(Kothapet) |
13 | Khairatabad | 26 | L.B. Nagar(Bahadurguda) |
Line 3 (blue): Nagole - Shilparamam
Route Length — 26.51 km
Number of Stations (All elevated) — 22
Link to other Corridors
- At Ameerpet – Connecting Corridors 3 and 1
- At Parade Grounds – Connecting Corridors 3 and 2
S.No | Station | S.No | Station |
---|---|---|---|
1 | Nagole | 13 | Begumpet |
2 | Uppal | 14 | Ameerpet |
3 | Survey Of India | 15 | Madhura Nagar |
4 | NGRI | 16 | Yousufguda |
5 | Habsiguda | 17 | Jubilee Hills Road No 5 |
6 | Tarnaka | 18 | Jubilee Hills Checkpost |
7 | Mettuguda | 19 | Peddamma Temple |
8 | Secunderabad | 20 | Madhapur PS |
9 | Parade Ground | 21 | Durgam Cheruvu |
10 | Paradise | 22 | Hitech City |
11 | Rasoolpura | ||
12 | Prakash Nagar |
Line 2 (green): JBS – Falaknuma
Route Length — 14.78 kilometers
Number of Stations (All elevated) — 16
Link to other Corridors
- At Parade Grounds – Connecting Corridors 2 and 3
- At Mahatma Gandhi Bus Station – Connecting Corridors 1 and 2
1 | Jubilee Bus Station | 0.000 | 0.000 |
2 | Parade Grounds | 0.700 | 0.700 |
3 | Secunderabad r.s. | 1.000 | 1.700 |
4 | Gandhi Hospital | 1.246 | 2.946 |
5 | Musheerabad | 0.641 | 3.587 |
6 | R.T.C. Cross Roads | 1.330 | 4.917 |
7 | Chikkadpally | 0.653 | 5.570 |
8 | Narayanguda | 1.010 | 6.580 |
9 | Sultan Bazaar | 0.779 | 7.359 |
10 | M.G. Bus Station | 0.826 | 8.185 |
11 | Salarjung Museum | 1.390 | 9.575 |
12 | Charminar | 1.540 | 11.115 |
13 | Shalibanda | 0.717 | 11.832 |
14 | Shamsherganj | 0.951 | 12.783 |
15 | Jangammet | 0.926 | 13.709 |
16 | Falaknuma | 0.474 | 14.183 |
Cost
The official estimated cost of the project stands at ₹14,132 crore (US$1.7 billion). The Central Government bears 10% of it, while L&T bears the remaining 90% of the cost.[15][23] However, construction work was supposed to commence on 3 March 2011. Since the project has already been delayed by a year, the interest component has accumulated to ₹1,825 crores. As a result, the final current cost (as of March 2012) of the project stands at ₹15,957 crores.[24]
Infrastructure
Rolling stock
On 12 September 2012, Larsen and Toubro Metro Rail Hyderabad Ltd (LTMRHL) announced that it has awarded tender for supply of rolling stock to Hyundai Rotem.[25][26] The ₹18 billion (US$220 million) tender is for 57 trains consisting of 171 cars which will be delivered in phases at least 9 months before the commencement of each stage.[27][28] On 2 October 2013, LTMRHL unveils its train car for Hyderabad Metro. A model coach which is half the size of the actual coach, is on public display at Necklace Road on the banks of Hussain Sagar in the heart of Hyderabad.[29] The trains will be 3.2m wide and 4m high.[30] There will be 4 doors on each side of each coach.[30]
On 10 April 2014 the first metro train for HMR rolled out of Hyundai Rotem Factory at Changwon in South Korea and is scheduled to reach Hyderabad by third week of May 2014.[31]
Ticketing
The L&T Hyderabad project will have an automated ticketing system with features such as contactless smart card based ticketing, slim automatic gates, payment by cash and credit/debit card, passenger operated ticket vending machine and provision of common ticketing system. It will also have a provision of NFC-based technology to enable usage of mobile phones as fare media and high performance machine to avoid long queues.[32] Samsung Data Systems India, a subsidiary of Korean firm Samsung, has been awarded the automatic fare collection system package for the L&T metro rail project. The package involves design, manufacture, supply, installation, testing and commissioning of the system.[32][33]
Stations
Otis of United States won the contract to supply and maintain 670 elevators.
Fare structure (2014)
Distance (km) | Metro Fare (![]() |
---|---|
0 - 5 | 9.00 |
5 - 6 | 10.00 |
6 - 10 | 12.00 |
10 - 14 | 14.00 |
12 - 15 | 16.00 |
15 - 18 | 17.00 |
> 18 | 20.00 |
See also
References
- ^ "Metro rail projects: Four new metromen and their challenges". The Times Of India. 18 December 2011.
- ^ "L&T set to bag Rs 12,132-cr Hyderabad metro rail project". The Hindu. 14 July 2010. Retrieved 17 May 2010.
- ^ [1][dead link]
- ^ "EPC vs PPP in metro rail". Projectsmonitor.com. 2 December 2007. Retrieved 18 April 2013.
- ^ "TheHindu.com Metro in best 100 global projects". www.thehindubusinessline.com.
- ^ "DeccanChronicle.com metro-among-100-global-projects". metro-among-100-global-projects.
- ^ "PPP Toolkit". Toolkit.pppinindia.com. Retrieved 18 April 2013.
- ^ "Sultan Bazaar blocks Metro Rail progress". Deccan Chronicle. Retrieved 28 September 2013.
- ^ "Metro sticks to time: Stage I by April 2015". Deccan Chronicle. 3 June 2013. Retrieved 28 September 2013.
- ^ "L&T performs Bhoomi Puja for Hyderabad metro". The Hindu. 26 April 2012.
- ^ "L&T metro rail schedule on track". The Hindu. Chennai, India. 7 June 2012.
- ^ "Metro Rail works picking up speed". The Deccan Chronicle. 31 August 2011. Retrieved 31 August 2011.
- ^ "Hyderabad Metro Rail phase-I to be completed by 2014". NDTV.com. 21 January 2013. Retrieved 18 April 2013.
- ^ Our Bureau. "Hyderabad Metro rail stage I to be flagged off by June 2014 - Business Line". Thehindubusinessline.com. Retrieved 18 April 2013.
- ^ a b "Hyderabad Metro Rail Project will be completed by 2017: Andhra Pradesh government". NDTV.com. 8 August 2012. Retrieved 18 April 2013.
- ^ "Hyderabad Metro to cost over Rs.14,000 crore-Aaj Ki Khabar". Aajkikhabar.com. 8 August 2012. Retrieved 18 April 2013.
- ^ http://www.thehindubusinessline.com/industry-and-economy/logistics/lt-hyderabad-metro-begins-laying-of-rails/article5370871.ece
- ^ "Metro Rail to provide disabled-friendly system". The Hindu. Chennai, India. 3 December 2013.
- ^ "First Metro train to arrive in May 2014". The Hindu. Chennai, India. 24 November 2013.
- ^ http://www.thehindubusinessline.com/companies/lt-hyderabad-metro-phase-i-to-be-ready-by-march-2015/article5325458.ece
- ^ Kumar, S. Sandeep (5 February 2014). "MGBS land sought for Metro Rail interchange station". The Hindu. Chennai, India.
- ^ http://www.hyderabadmetrorail.com/images/Metro%20Route%20Map.jpg
- ^ "Hyd Metro Rail Project will be completed on schedule: AP govt, IBN Live News". Ibnlive.in.com. 8 August 2012. Retrieved 18 April 2013.
- ^ "Metro rail cost overshoots estimates". The Times Of India. 8 March 2012.
- ^ "L&T Metro Rail grants Rs 1,800 cr contract to Hyundai Rotem". Zeenews.india.com. Retrieved 18 April 2013.
- ^ [2][dead link]
- ^ "Hyundai Rotem cars to run on metro tracks". The Times Of India. 12 September 2012. Retrieved 15 September 2012.
- ^ "L&T awards rolling stock contract to Hyundai Rotem". Ibnlive.in.com. 14 September 2012. Retrieved 18 April 2013.
- ^ [3]
- ^ a b [4]
- ^ "First train for Hyderabad Metro rolls out of Korean factory". IANS. news.biharprabha.com. Retrieved 10 April 2014.
- ^ a b Our Bureau (18 February 2013). "Samsung bags fare collection system contract for Hyderabad Metro | Business Line". Thehindubusinessline.com. Retrieved 28 September 2013.
- ^ Udgirkar, Trushna. "Hyderabad Metro in ticketing deal with Samsung". mydigitalfc.com. Retrieved 28 September 2013.
External links
![](http://upload.wikimedia.org/wikipedia/en/thumb/4/4a/Commons-logo.svg/30px-Commons-logo.svg.png)