Purple Line (Bangkok)
MRT Purple Line or Chalong Ratchatham Line สายฉลองรัชธรรม | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Overview | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Owner | Mass Rapid Transit Authority | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Locale | Nonthaburi Province and Bangkok | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Termini |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stations | Total : 33 stations 16 (operational) 17 (under construction) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Color on map | Purple | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Service | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Type | Rapid transit | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
System | MRT | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operator(s) | Bangkok Expressway and Metro | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Depot(s) | Khlong Bang Phai Kru Nai (under construction) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Rolling stock | J-TREC Sustina S24-EMU : 21 three-car trainsets | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Daily ridership | 70,303 (๋July 2024) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
History | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Commenced | 10 November 2009 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Opened | 6 August 2016 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Technical | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Line length | Total :43.70 km (27.15 mi) 20.92 km (13.00 mi) (operational) 22.78 km (14.15 mi) (under construction) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Number of tracks | 2 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Character | Elevated: 30.63 km (19.03 mi) Underground : 13.07 km (8.12 mi) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electrification | 750 V DC third rail | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operating speed | 80 km/h (50 mph) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Signalling | Bombardier CITYFLO 650 moving block CBTC ATC under ATO GoA 2 (STO), with subsystems of ATP, ATS and CBI[1] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
The MRT Purple line (Thai: รถไฟฟ้ามหานคร สายสีม่วง) or MRT Chalong Ratchatham line (Thai: รถไฟฟ้ามหานคร สายฉลองรัชธรรม) is Bangkok's fifth rapid transit line, following the Sukhumvit Line, Silom Line, MRT Blue Line, and Airport Rail Link. The line is 23 km (14 mi) long,[2] serving the north-western area of Bangkok running from Tao Poon to Klong Bang Phai in Nonthaburi Province.
The line opened on 6 August 2016.[3][2] It is the second line of MRT system and is operated by BEM under a concession contract. Daily ridership is 70,000.[4][5]
A 23.63 km (14.68 mi), 17 station southern extension of the line consisting of a 14.3 km (8.89 mi) underground section and a 9.3 km (5.78 mi) elevated section [6] commenced construction in August 2022. The cost of the southern extension is 82 billion baht and it is planned to open at the end of 2027.[7] By the end of May 2023, construction had progressed to 11.50%.[8]
Route alignment
[edit]The Purple line starts from Khlong Bang Phai station in Bang Bua Thong District. The line travels south along Kanchanaphisek Road before turning eastward near Central WestGate, onto Rattanathibet Road. It continues along Rattanathibet Road, passing through a large residential area in Bang Yai District and crosses the Chao Phraya River on a bridge parallel to the Phra Nang Klao Bridge and runs towards Nonthaburi Civic Center station. The line then turns southward onto Tiwanon Road, passing the Ministry of Public Health and turns southeast onto Krung Thep-Nonthaburi Road, entering Yaek Tiwanon station. The line then enters Bangkok city limits at Bang Sue district and passes Bang Son station before terminating at the upper platforms of Tao Poon station, with a total length of 23 kilometres (14.29 mi), serving 16 stations.
History
[edit]Officially named the Chalong Ratchadham Line (Thai: สายฉลองรัชธรรม) – "To Celebrate the Great King's Reign with Righteousness"[9] – but informally known as the "Purple Line", the rapid transit line provides a north–western corridor in Bangkok's Mass Rapid Transit Master Plan. The line also incorporated an extension of the Blue Line from nearby Bang Sue station to Tao Poon Station.
In the 1990s, the plan for the Purple Line was to run from Bang Phut to Bang Sue for 12 kilometres (7.5 mi), with an extension to Thewet for 6.7 kilometers (4.2 mi).[10]
This line was created from the adjustment of the 1994 mass transit rail system master plan, which connected the original extension of the Blue Line from Tao Poon to Bang Yai, while the original Purple Line would have run from the National Library to Tao Poon and the original Orange Line from Samsen (National Library) to Rat Burana, becoming a new line designated as the Purple Line, included in the master plan of the Office of Transport and Traffic Policy and Planning (OTP) for the first time in 2004. Five years later, the line's construction began.
Construction was divided into six contracts, three of them for civil works. The contracts were signed from late 2009 to early 2010 and completion was originally scheduled for the end of 2014.[11][12][13][14] The third contract included construction of four park and ride buildings at the Khlong Bang Phai, Sam Yaek Bang Yai, Bang Rak Noi Tha It, and Yaek Nonthaburi 1 stations. On 31 March 2017, the fifth contract was effectively terminated and became part of a new Blue Line concession agreement.[15][16]
The 2011 Thailand floods delayed the construction of the line for nearly 1 year. [citation needed] In June 2013, five people were injured when six beams fell onto vehicles below Tao Poon station.[17] In July 2014, the civil work was 94 percent complete;[18][19] in October 2014, civil work was stated to be 99% complete.[20]
The line opened on August 6, 2016, when His Majesty King Bhumibol Adulyadej graciously appointed Her Royal Highness Princess Maha Chakri Sirindhorn to represent him in presiding over the opening ceremony and officially pressing the button to open the electric train system.[3][21] However, the MRT Blue Line extension to Tao poon was delayed, so when it opened the Purple Line couldn't interchange with the Blue line as planned. This resulted in low line usage. Even with a reduced fare, the line only attracted about 22,000 passengers daily compared to a goal of 100,000. A shuttle bus service was in operation between Tao Poon MRT station and Bang Sue MRT station to connect with the Blue Line.[22] When the Blue line extension finally opened a year later, on 11 August 2017,[23][24] ridership significantly increased. In 2019, daily ridership was 70,000.[4][5]
Contract | Section | Length (kilometers) |
---|---|---|
1 | Bang Sue to Tao Poon and Tao Poon to Phra Nangklao Bridge[11] | 12 |
2 | Phra Nangklao Bridge to Khlong Bang Phai[12] | 11 |
3 | Depot at Khlong Bang Phai, four park and ride buildings[13] | |
4 | Purple Line rolling stock, systems, operation and maintenance (contractor BEM)[25][26][27][28] | |
5 | Blue Line (Bang Sue to Tao Poon) systems, operation and maintenance (contractor BEM)[29] | |
6 | Trackwork (contractor ITD)[30][31] |
Rolling stock
[edit]In November 2013, BEM contracted with Marubeni Corp, Toshiba Corp, and East Japan Railway Company to install E&S systems, supply 21 three-car trains (total of 63 cars) rolling stock, and provide maintenance for 10 years as part of a contract worth 12.6 billion baht.[32] East Japan Railway train manufacturing subsidiary J-TREC built them in Yokohama with the first sets delivered in early 2016.[33] The trains are owned by the MRTA which paid for the rolling stock at BEMs request.[34] The southern extension will acquire 17 additional trains, along with the current ones, to create a total of 38 trains.
In total, line is service by 21 three-car trains.[9] Trains are powered by 750 V DC via third rail system, are air-conditioned and capable of traveling at up to 80 km/h (50 mph).
-
MRT Purple Line train entering a station.
-
Purple Line train spotted near Central Westgate.
-
Interior of a train.
-
Interior of a train.
-
Dynamic route map
-
Platform Level at Bang Phlu station
Operation
[edit]The 16-station Purple Line runs from Khlong Bang Phai to Tao Poon and has a carrying capacity of 30,000 people in each direction per hour. The line operates daily from 06:00-24:00 with an interval of under 6 minutes during peak hours and 9 minutes during off-peak hours.[35] All stations on the line are equipped with platform screen doors. Stations are built to accommodate six-car trains, but only three-car trains are used. The line has 1 depot near Khlong Bang Phai station
The MRTA has proposed to BEM to introduce multi-trip package fares to reduce prices[36] which follows an earlier proposal by the Department of Railways to offer 40% discounts during off peak travel.[37]
Southern section
[edit]As the northern section of the Purple line was built first, the 2nd phase of the Purple Line south from Tao Poon via Rattanakosin - Bangkok's old town to Rat Burana would fully complete the line. The length of the southern extension is 23.63 km (14.68 mi) (14.29 km (8.88 mi) underground, 9.34 km (5.80 mi) elevated with 17 stations - ten underground and seven elevated).[6]
The Thai Cabinet was expected to approve the tender in mid 2017 with a tender then to be issued in the second half of 2017.[38] On 25 July 2017, Cabinet approval was given,[39][40] but the tender was then delayed until 2018.[41][42] By December 2018, a tender had still not been issued and was further delayed.[43] In August 2019, subject to final land acquisition, a March 2020 tender was planned.[34] In mid 2020, the Ministry of Transport still aimed for a tendering process within 2020 despite COVID-19 related delays.[44] The MRTA then expected to issue a tender in February 2021.[45] and if construction had begun in 2021, the extension was projected to enter service sometime in 2027.[46] However, the tender was delayed yet again and subsequently cancelled in August 2021 until it was finally issued in November 2021.[47]
Construction contracts were signed on 11 March 2022 with a 2005 construction period for an ambitious planned 2027 opening date.[48]
Construction progress
[edit]Contactors were issued with a Notice to Proceed on 25 April 2022 giving them access to sites along the route with actual construction planned to begin from August 2022.[49] Construction began in early August for two contract sections, 3 & 4.[50] Some 410 lots and 500 buildings will need to be appropriated to build the extension and as of May 2022 many of them were still to be surveyed.[7]
Construction progress was at 3.45% complete at the end of September 2022.[51] By the end of November 2022, construction progress was at 4.30%. [52] At the end of February 2023, construction had progressed to 7.73%.[53]
By the end of May 2023, construction had progressed to 11.50%. [54]
Construction contracts
[edit]Contract | Notes | Contractor(s) | Length (km) |
Progress (August 2024) |
Cost[55] |
---|---|---|---|---|---|
1 | Tao Poon to National Library | CKST Joint Venture | 4.8 | 56.85% | ฿19,430 million |
2 | National Library to Phan Fah | 3.44 | 48.21% | ฿15,878 million | |
3 | Phan Fah to Memorial Bridge | ITD-NWR Joint Venture | 3.1 | 38.43% | ฿15,109 million |
4 | Memorial Bridge to Dao Khanong | Unique Construction and Engineering | 4.1 | 40.14% | ฿14,982 million |
5 | Dao Khanong to Kru Nai & Depot | Italian-Thai Development | 9 | 20.84% | ฿19,904 million |
6 | Track and Electrical | 32.49% | ฿3,589 million | ||
7 | Rolling stock | TBA | TBA | ||
Total Progress | 42.18%[56] | ฿82,083 million |
Stations
[edit]Code | Station Name | Opened | Platform Type | Position | Park & Ride |
Transfer | Notes | |
---|---|---|---|---|---|---|---|---|
English | Thai | |||||||
Khlong Bang Phai - Tao Poon: 20.92 km (operational) | ||||||||
PP01 | Khlong Bang Phai | คลองบางไผ่ | 6 August 2016 | Island | Elevated | √ | Exit to: • Khlong Bang Phai Depot • DHL Supply Chain & Distribution | |
PP02 | Talad Bang Yai | ตลาดบางใหญ่ | Island | - | Exit to: • Big C Extra Bangyai • The Square Bang Yai • Kasemrad International Hospital Ratthanatibeth • Home Pro Rattanathibet • Big C Supercenter Rattanathibet 1 • Decathlon Bangyai • Index Living Mall Bang Yai • Central Westgate • IKEA Bangyai • Bang Yai Market | |||
PP03 | Sam Yaek Bang Yai | สามแยกบางใหญ่ | Island | √ | ||||
PP04 | Bang Phlu | บางพลู | Island | - | Exit to Megahome Rattanathibet | |||
PP05 | Bang Rak Yai | บางรักใหญ่ | Island | - | Exit to Wat Bang Rak Yai | |||
PP06 | Bang Rak Noi Tha It | บางรักน้อย-ท่าอิฐ | Island | √ | Proposed connecting station to BTS (future) | |||
PP07 | Sai Ma | ไทรม้า | Island | - | ||||
PP08 | Phra Nang Klao Bridge | สะพานพระนั่งเกล้า | Island | - | Connecting station, without paid-area integration to Phra Nang Klao pier for • Mine Smart Ferry • CHAOPHRAYA EXPRESS |
Exit to: • Wat Noi Nok • Wat Chaeng Sirisamphan • Tonsak Market • Rajamangala University of Technology Suvarnabhumi - Nonthaburi Campus - North Area | ||
PP09 | Yaek Nonthaburi 1 | แยกนนทบุรี 1 | Island | √ | Exit to: • Central Rattanathibet • Owl Market | |||
PP10 | Bang Krasor | บางกระสอ | Island | - | Exit to: • Big C Supercenter Rattanathibet 2 • Grand Richmond Stylish Convention Hotel | |||
PP11 | Nonthaburi Civic Center | ศูนย์ราชการนนทบุรี | Island | - | Connecting station, without paid-area integration, to • MRT , via a 350-metre elevated pedestrian walkway. • MRT (future) |
Exit to: • National Broadcasting and Telecommunications Commission • Nonthaburi Civic Center • Esplanade Cineplex Ngamwongwan – Khae Rai • Siam Business Administration Nonthaburi Technological College • Makut Rommayasaran Park | ||
PP12 | Ministry of Public Health | กระทรวงสาธารณสุข | Island | - | Exit to: • Ministry of Public Health • Srithanya Hospital • Regional Revenue Office 4 | |||
PP13 | Yaek Tiwanon | แยกติวานนท์ | Island | - | ||||
PP14 | Wong Sawang | วงศ์สว่าง | Island | - | Exit to Big C Market Place Wong Sawang | |||
PP15 | Bang Son | บางซ่อน | Island | - | Connecting station, without paid-area integration, to • SRT • SRT Southern Line |
Exit to Bang Son Market | ||
PP16 | Tao Poon | เตาปูน | Island | - | Interchange station to MRT | Exit to: • Tao Poon Market • Lotus's Prachachuen | ||
Tao Poon - Kru Nai: 22.78 km (under construction) | ||||||||
PP17 | Parliament House | รัฐสภา | 2027 (expected) |
Island | Underground | - | Exit to: • Thai Parliament • Defence Industrial Department • 4th Armoured Regiment, 1st Division King's Royal Guard • Air Defence Division • Wat Mai Thongsen • Wat Kaew Fah Chulamanee | |
PP18 | Sri Yan | ศรีย่าน | Stacked | - | Exit to: • Supreme Complex • Makro Samsen • Royal Irrigation Department • Medium Irrigation Water Resources Development Division • Wimol Sriyan Commercial College | |||
PP19 | Vajira Hospital | วชิรพยาบาล | Stacked | - | Exit to: • Vajira Hospital • Sukhothai Palace • Market Place Dusit • Suan Dusit University • Saint Gabriel's College | |||
PP20 | National Library | หอสมุดแห่งชาติ | Side | - | Exit to: • Suan Sunandha Rajabhat University • The National Library • Rajamangala University of Technology Phra Nakhon | |||
PP21 | Bang Khun Phrom | บางขุนพรหม | Stacked | - | Exit to: • Bank of Thailand • Bank of Thailand Museum • Bang Khun Phrom Palace • Wat Sam Phraya | |||
PP22 | Democracy Monument | อนุสาวรีย์ประชาธิปไตย | Stacked | - | Interchange station to MRT (under construction) | Exit to: • Mahakan fort • Rattanakosin Exhibition Hall • Queen Sirikit Gallery • Royal Pavilion Mahajetsadabadin • Wat Saket Formerly Phan Fa | ||
PP23 | Sam Yot | สามยอด | Island | - | Interchange station to MRT | Exit to: • Khlong Ong Ang • Mega Plaza Saphan Lek • Phahurat • Rommaninat Park • The Old Siam Plaza | ||
PP24 | Memorial Bridge | สะพานพุทธฯ | Island | - | Proposed connecting station to Prachathipok station for MRL | Exit to: • Suksanari School • Wat Prayurawongsawat Worawihan • Wat Phitchaya Yatikaram Worawihan • Wat Anongkharam Worawihan • Nan Ah Hospital • Big C Supercenter Itsaraphap | ||
PP25 | Wongwian Yai | วงเวียนใหญ่ | Island | - | Connecting station, without paid-area integration to • BTS via 270-metre underground walkway • SRT via 120-metre covered walkway (future) |
Exit to: • Wongwian Yai Market • Wongwian Yai | ||
PP26 | Somdech Phra Pinklao Hospital | โรงพยาบาลสมเด็จพระปิ่นเกล้า | Island | - | Exit to: • Somdech Phra Pinklao Hospital • Samre Market Formerly Samre | |||
PP27 | Dao Khanong | ดาวคะนอง | Side | Elevated | - | Exit to: • Big C Supercenter Dao Khanong • Wat Mongkhon Wararam | ||
PP28 | Bang Pakaeo | บางปะแก้ว | Side | - | ||||
PP29 | Bang Pakok | บางปะกอก | Side | √ | Exit to: • Wat Bang Pakok • Bang Pakok Wittayakom School • Bangpakok 1 Hospital • Bang Pakok Fresh Market • Lotus's Bangpakok | |||
PP30 | Yaek Pracha Uthit | แยกประชาอุทิศ | Side | - | Exit to: • Bangkok Employment Office Area 2 • Han Clan Foundation of Thailand • Wat Sarod School • Wat Sarod Formerly Rama 9 Bridge | |||
PP31 | Rat Burana | ราษฎร์บูรณะ | Side | √ | ||||
PP32 | Phra Pradaeng | พระประแดง | Side | - | Exit to: • Phra Pradaeng Arcade Market • HomePro Suk Sawat • Big C Supercenter Suksawat • Thaiwatsadu Suk Sawat | |||
PP33 | Khru Nai | ครุใน | Side | - | Exit to Wat Kru Nai |
Ridership
[edit]When the Purple line first opened daily ridership was only 22,000 compared to projected numbers of 100,000.[57] After the opening of the Blue Line extension to Tao Poon 1 year later in August 2017, daily average ridership increased significantly from 33,000 to 50,000.[58]
In August 2018, the MRTA Deputy Governor stated that daily ridership had increased to 60,000 each weekday.[59] By late 2019, this had increased to 70,000.[4] In 2023 the purple line saw an average of 50385 passengers per day. [60]
On 16 October 2023, MRT Purple Line began using the new fare rates of 14 to 20 baht (down from 16 to 42 baht) after the '20 Baht Transit Max Fares Policy' was approved by the Thai government.[61]
MRT Purple Line Ridership[62] | |||||
---|---|---|---|---|---|
Year | Quarter | Quarterly Ridership | Daily Ridership | Annual Ridership | Remarks |
2016 | Q1 | 3,074,389 | |||
Q2 | |||||
Q3 | 1,161,989 | 20,731 | PP01 Khlong Bang Phai - PP16 Tao Poon section opened on 6 August 2016. | ||
Q4 | 1,912,400 | 20,796 | |||
2017 | Q1 | 1,969,874 | 21,888 | 11,626,990 | |
Q2 | 2,196,900 | 24,142 | |||
Q3 | 3,437,488 | 37,364 | BL10 Tao Poon - BL11 Bang Sue section on MRT Blue Line opened on 11 August 2017. | ||
Q4 | 4,022,728 | 44,206 | |||
2018 | Q1 | 4,005,632 | 44,508 | 17,644,588 | |
Q2 | 4,120,533 | 45,281 | |||
Q3 | 4,791,613 | 52,083 | |||
Q4 | 4,726,810 | 51,379 | |||
2019 | Q1 | 4,699,831 | 52,221 | 19,726,225 | |
Q2 | 4,665,231 | 52,419 | |||
Q3 | 5,298,016 | 57,588 | |||
Q4 | 5,063,147 | 55,035 | |||
2020 | Q1 | 4,719,549 | 51,863 | 16,836,638 | 1st wave of COVID-19 outbreaks (January 2020 - May 2020) |
Q2 | 2,208,015 | 24,264 | |||
Q3 | 4,840,866 | 52,619 | |||
Q4 | 5,068,208 | 55,089 | 2nd wave of COVID-19 outbreaks (December 2020 - February 2021) | ||
2021 | Q1 | 3,475,384 | 38,615 | 9,841,934 | |
Q2 | 1,993,392 | 21,668 | 3rd wave of COVID-19 outbreaks (April 2021 - June 2021) | ||
Q3 | 1,417,404 | 15,407 | 4th wave of COVID-19 outbreaks (July 2021 - early 2022) | ||
Q4 | 2,955,754 | 32,128 | |||
2022 | Q1 | 2,946,430 | 32,739 | 16,450,757 | |
Q2 | 3,569,128 | 39,222 | |||
Q3 | 4,691,107 | 50,991 | |||
Q4 | 5,244,092 | 57,001 | |||
2023 | Q1 | 5,122,816 | 56,921 | 21,508,224 | |
Q2 | 4,897,809 | 53,823 | |||
Q3 | 5,623,257 | 61,123 | |||
Q4 | 5,864,342 | 63,742 | Began using 14-20 Baht fare rates from 16 October 2023.[61] | ||
2024 | Q1 | 6,005,239 | 65,992 | 16,167,201 | |
Q2 | 5,718,198 | 62,837 | |||
Q3 | 4,443,763 | 71,674 | As of August 2024. | ||
Q4 |
Network map
[edit]See also
[edit]- Mass Rapid Transit Master Plan in Bangkok Metropolitan Region
- Bangkok Metro
- MRT Blue Line
- MRT Brown Line
- MRT Grey Line
- MRT Light Blue Line
- MRT Orange Line
- MRT Pink Line
- MRT Yellow Line
- BTS Skytrain
- Sukhumvit Line
- Silom Line
- Airport Rail Link (Bangkok)
- SRT Dark Red Line
- SRT Light Red Line
- Bangkok BRT
- BMA Gold Line
- BMA Bang Na-Airport Line
References
[edit]- ^ "Bombardier Projects in Mass-transit signalling" (PDF). Archived from the original (PDF) on 23 November 2021.
- ^ a b c Mokkhasen, Sasiwan (10 May 2016). "Sign up to test ride new MRT Purple Line". Khaosod English. Thailand. Archived from the original on 13 November 2021. Retrieved 13 November 2021.
- ^ a b "Purple Line: Newly launched, but few using it". Bangkok Post. Retrieved 21 June 2020.
- ^ a b c https://www.khaosod.co.th/economics/news_2933591. Khaosod ,30 September 2019
- ^ a b "MRTA to issue measure to reduce fares to attract passengers".
- ^ a b "MRTA Purple Line project".
- ^ a b "Construction of southern Purple Line to begin in August". The Nation. 22 April 2022.
- ^ "MRT Purple Line construction update June 2023". MRTA PR Facebook. 8 June 2023.
- ^ a b "BEM บริษัททางด่วนและรถไฟฟ้ากรุงเทพจำกัด (มหาชน)". metro.bemplc.co.th (in Thai). Retrieved 22 June 2020.
- ^ "Urban Railway Projects In Bangkok - Measures for Securing Financial Resources" (PDF).
- ^ a b "ลงนามสัญญาที่1 รถไฟสีม่วง ช.การช่างได้เฮ". thairath.co.th (in Thai). 26 August 2009. Retrieved 21 June 2020.
- ^ a b "รฟม.ลงนามสัญญา 2 สายสีม่วง มูลค่า 1.31 หมื่นล้านแล้ว". thairath.co.th (in Thai). 20 January 2010. Retrieved 21 June 2020.
- ^ a b "รฟม.ตัดเค้กสัญญา 3 รถไฟฟ้าสายสีม่วง "อิตาเลียนไทย" ได้ทานแห้ว". mgronline.com. 23 June 2009. Retrieved 25 June 2020.
- ^ "รถไฟฟ้าสายสีม่วงบางซื่อ-บางใหญ่ฉลุยเซ็นรับเหมาครบ3สัญญา ลงมือก่อสร้างก.พ.นี้ 3 ปีครึ่งเสร็จ !!". www.thailog.org. Retrieved 25 June 2020.
- ^ "ปิดดีลเดินรถสีน้ำเงิน ครม.ผ่านฉลุย เร่งเซ็นสัญญาจ้าง Bem ทยอยเปิดเดินรถปลายปี 62". mgronline.com. 28 March 2017. Retrieved 25 June 2020.
- ^ "BEM significant event in 2017" (PDF).
- ^ "MRTA Purple line accident injures 5". Bangkok Post. 7 June 2013.
- ^ "คมนาคมตามความคืบหน้ารถไฟฟ้า 10 สาย เร่งสีม่วงเปิดปลายปี'58 ชงคสช.อนุมัติอีก 6 สาย : ประชาชาติธุรกิจออนไลน์". Archived from the original on 17 October 2014. Retrieved 28 July 2014.
- ^ "ระบบรถไฟฟ้าในกทม.และปริมณฑล".
- ^ "หนังสือพิมพ์บ้านเมือง » คมนาคม เผยความคืบหน้ารถไฟฟ้า". Archived from the original on 9 October 2014. Retrieved 9 October 2014.
- ^ พิธีเปิดการเดินรถ และกดปุ่มเปิดระบบรถไฟฟ้าอย่างเป็นทางการ
- ^ "Fare cut boosts Purple Line riders, but still below target". Bangkok Post. Retrieved 11 September 2016.
- ^ "Purple Line to connect with MRT on Aug 11". Bangkok Post. Retrieved 24 April 2020.
- ^ "เปิดวิ่งเชื่อมต่อสถานีเตาปูน-บางซื่อ 12.00 วันนี้". bangkokbiznews.com/. 11 August 2017. Retrieved 25 June 2020.
- ^ "รถไฟฟ้าสายสีม่วงคืบหน้าแล้วกว่า70%". posttoday.com. 4 September 2013. Retrieved 25 June 2020.
- ^ "Purple Line O&M contract (PDF)" (PDF).
- ^ 'Purple Line deal agreed BEM signs 30-year contract with MRTA'. Bangkok Post, 5 September 2013
- ^ "Bangkok Purple Line contract awarded". International Railway Gazette. 22 October 2012. Retrieved 6 May 2013.
- ^ "BMCLอนุมัติเซ็นสัญญารถไฟฟ้าสายสีม่วงสัญญาที่5". bangkokbiznews.com/. 21 August 2015. Retrieved 25 June 2020.
- ^ "ITD closer to Purple Line contract". The Nation. Bangkok. 17 May 2012. Retrieved 26 November 2012.
- ^ isranews (4 October 2012). "รฟม.จ้างอิตาเลียนไทยฯสร้างรถไฟฟ้า". สำนักข่าวอิศรา (in Thai). Retrieved 25 June 2020.
- ^ 'Japanese firms win Purple Line deal'. Bangkok Post, 6 November 2013
- ^ "First Sustina export order". International Railway Gazette. 23 September 2014.
- ^ a b Member Yappofloyd meeting with MRTA Planning Division on 7 August 2019 at MRTA Headquarters
- ^ "แผนที่เส้นทาง". metro.bemplc.co.th (in Thai). Retrieved 22 June 2020.
- ^ "Discounted multi-trip packages proposed for Blue, Purple lines". Bangkok Post. 1 October 2019.
- ^ "Rail regulator weighs off-peak discounts". Bangkok Post. 3 September 2019.
- ^ http://www.bangkokpost.com/archive/b358bn-rail-projects-expected-to-go-ahead/1256406. Bangkok Post, 26 May 2017
- ^ "ครม.ไฟเขียวรถไฟฟ้าม่วงใต้ 1.101 แสนล้าน "อาคม" จ่อชงอีก 4 สายครบโครงข่าย". 25 July 2017.
- ^ http://www.nationmultimedia.com/detail/Economy/30321793. The Nation, 25 July 2017
- ^ https://www.bangkokpost.com/archive/purple-line-south-link-bid-faces-delay/1357647. Bangkok Post, 10 Nov 2017
- ^ https://www.bangkokpost.com/news/transport/1541274/tor-for-slate-of-transport-projects-set-for-fast-track. Bangkok Post, 17 September 2018
- ^ "Purple Line, Phuket light rail among projects up for PPP". Bangkok Post. Retrieved 25 June 2020.
- ^ "'ศักดิ์สยาม'สั่งลุยเปิดประมูลรถไฟฟ้าสายสีส้ม-ม่วงใต้ภายในปีนี้". Thai Post | อิสรภาพแห่งความคิด. Retrieved 25 June 2020.
- ^ เช็กคืบหน้ารถไฟฟ้าทุกสี ต้นปี 64 เปิดประมูล สีม่วง “เตาปูน-ราษฎร์บูรณะ. Prachachat, 1 December 2020
- ^ Theparat, Chatrudee (30 October 2020). "Tangled lines". Bangkok Post. Retrieved 31 October 2020.
- ^ "REANNOUCEMENT OF INVITATION TO TENDER THE MRT Purple Line Project, Tao Pun - Rat Burana (Kanchanapisek Road) Section". 10 November 2021.
- ^ "Purple Line southern section construction to start this year". 11 March 2022.
- ^ "ประมูลคุมงานก่อสร้าง"สีม่วงใต้"คึกคัก บริษัทที่ปรึกษาแห่ยื่นชิงเค้ก 2.8 พันล้าน". Manager Online. 25 April 2022. Retrieved 25 June 2020.
- ^ "รฟม. ส่งมอบพื้นที่ชุดแรกสร้างรถไฟฟ้า "สีม่วงใต้" สัญญา 3-4 แล้ว". Daily News. 2 August 2022.
- ^ "เปิดไซต์ก่อสร้างรถไฟฟ้า 4 สาย ส้ม เหลือง ชมพู คืบเกิน 90% สีม่วง เตาปูน-ราษฎร์บูรณะ เดินหน้าแล้ว 3.42%". Matichon. Archived from the original on 8 October 2022. Retrieved 8 October 2022.
- ^ "MRT Purple Line construction update December 2022". MRTA PR Facebook. 8 December 2022.
- ^ "MRT Purple Line construction update March 2023". MRTA PR Facebook. 8 March 2023.
- ^ "MRT Purple Line construction update June 2023". MRTA PR Facebook. 8 June 2023.
- ^ "รายละเอียดโครงการ | โครงการรถไฟฟ้าสายสีม่วง ช่วงเตาปูน-ราษฎร์บูรณะ (วงแหวนกาญจนาภิเษก)". www.mrta-purplelinesouth.com. Retrieved 9 October 2024.
- ^ "ความก้าวหน้าของงานก่อสร้าง | โครงการรถไฟฟ้าสายสีม่วง ช่วงเตาปูน-ราษฎร์บูรณะ (วงแหวนกาญจนาภิเษก)". www.mrta-purplelinesouth.com. Retrieved 9 October 2024.
- ^ "Fare cut boosts Purple Line riders, but still below target - Bangkok Post Property finance advice". Bangkok Post. Retrieved 11 September 2016.
- ^ "Purple Line use up 47% since 'missing link' completed". Bangkok Post. Bangkok. 8 September 2017.
- ^ http://www.thansettakij.com/content/309472. Thansettakij, 27 August 2018
- ^ "Minisery of rail transport".
- ^ a b "รฟม. ลดค่าโดยสารรถไฟฟ้า MRT สายสีม่วง สูงสุดไม่เกิน 20 บาท เริ่ม 16 ตุลาคม 2566 ตั้งแต่เวลา 11.00 น. เป็นต้นไป เพื่อลดภาระค่าครองชีพแก่ประชาชนตามนโยบายรัฐบาล".
- ^ "สถิติจำนวนผู้โดยสารโครงการรถไฟฟ้ามหานคร สายฉลองรัชธรรม (สีม่วง)". www.mrta.co.th (in Thai). Retrieved 22 September 2024.