Second Avenue Subway
Second Avenue Subway | |
---|---|
Overview | |
Status | Phase I under construction, Phase II under planning |
Owner | City of New York |
Locale | Manhattan, New York City, United States |
Termini |
|
Stations | 16 |
Service | |
Type | Rapid transit |
System | New York City Subway |
Operator(s) | New York City Transit Authority / MTA Capital Construction |
History | |
Opened | First phase: December 30, 2016[1] | (projected)
Technical | |
Line length | 8.5 mi (13.7 km) |
Track gauge | 4 ft 8+1⁄2 in (1,435 mm) |
The Second Avenue Subway (officially the IND Second Avenue Line; abbreviated to SAS) is a long-envisioned rapid transit subway line, part of the New York City Subway system. As of 2014[update], Phase I, a new line between the existing BMT 63rd Street Line and 96th Street and Second Avenue, is under construction beneath Second Avenue in the borough of Manhattan. This first phase is scheduled to be opened on December 30, 2016,[1][2] and will serve approximately 200,000 daily riders when open. When the whole line is completed, which MTA Capital Construction President Dr. Michael Horodniceanu says may be as early as 2029,[3] it is projected to serve about 560,000 daily riders.[4] As of December 19, 2014[update], the first phase of construction was 76% done.[5]
The Second Avenue Subway has been a plan, and occasional construction project, since 1929. The reasons for the line's many false starts and delays are numerous and complex. The line is sometimes referred to as "The Line That Time Forgot".[6][7]
After several starts and interruptions, mostly because of lack of funds, the most recent and financially secure construction plan was launched when a tunnelling contract was awarded to the consortium of Schiavone/Shea/Skanska (S3) by the Metropolitan Transportation Authority (MTA) on March 20, 2007.[8] This followed preliminary engineering and a final tunnel design completed by a joint venture between AECOM and Arup.[9][10] Parsons Brinckerhoff is the Construction Manager of the project. This contract, and the full funding grant agreement with the Federal Transit Administration, which was received in November 2007, is for Phase I of the project, consisting of two miles (3.2 km) of tunnel and three stations.[11] Phase I will be within budget, costing $4.45 billion;[12] the total cost of the 8.5-mile (13.7 km) line is expected to exceed $17 billion.[6]
A ceremonial ground-breaking for the Second Avenue Subway was held on April 12, 2007. The contractor prepared the initial construction site at 96th Street on April 23, 2007. A tunnel boring machine (TBM) was originally expected to arrive six to eight months after construction began, but the utility relocation and excavation required to create its "launch box" delayed its deployment until May 2010.[11] By May 2010, the TBM launch box was complete, and on May 14, 2010, MTA's contractors completed the TBM installation and turned it on.[13][14][15] On March 28, 2011, S3, having completed the west tunnel to 65th Street, began drilling for the east tunnel. The TBM completed its run to the 63rd Street station's bellmouth on September 22, 2011.[16]
Background
Second Avenue Subway | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Originally proposed in 1929 as part of a massive expansion of the Independent Subway System (IND), work on the line never commenced, as the Great Depression crushed the economy of the state and country. Need for the Second Avenue Subway line grew along with the population of Manhattan's East Side. Currently, the lone rapid transit option on the Upper East Side is the four-track IRT Lexington Avenue Line. The most crowded in the country, the line sees an average of 1.3 million daily riders, more than the entire Washington Metro system (which has the second-highest ridership in the U.S.) and more than the rail transit systems of San Francisco and Boston combined.[17] Local bus routes are just as crowded during various times of the day, with the surface Second Avenue Line, carrying the M15 and M15 SBS buses, seeing an annual ridership of 17.5 million, or a daily ridership of about 47,945.[18] The construction of the Second Avenue line would add another two tracks to fill the gap that has existed since the elevated IRT Second Avenue Line was demolished in 1940–42[19] and the IRT Third Avenue Line was removed in 1955–56.[20]
The city started planning, again, in 1945, to build the new subway and bought a prototype train (the R11) in 1949 for use on the new line.[21] New York voters approved bond acts for its construction in 1951 and in 1967. Money from the 1951 bond measure was diverted to buy new cars, lengthen platforms, and maintain other parts of the aging New York City subway system. The proceeds of the 1967 bond act were partly used to begin tunneling under Second Avenue. Digging began in 1972; however, a few years later, the city became insolvent.[22] "It's the most famous thing that's never been built in New York City, so everyone is skeptical and rightly so," said Gene Russianoff, an advocate for subway riders since 1981. "It's much-promised and never delivered."[23]
On November 8, 2005, voters in New York State passed the Transportation Bond Act, which will, among other projects, partially fund construction of the line. Its passage had been seen as critical to its construction. After warning that failure to pass the act would doom the project, MTA chairman Peter S. Kalikow stated that "Now it's up to us to complete the job" given its approval by a 55–45 percent margin.[24]
In August 2006, the MTA revealed that all future subway stations, including ones built for the Second Avenue subway, the 7 Subway Extension, and the new South Ferry station will be outfitted with air-cooling systems to reduce the temperature along platforms.[25] In November 2007, Mary Peters, the United States Secretary of Transportation announced that the Second Avenue Subway would receive $1.3 billion in federal funding for the project's first phase, to be funded over a seven-year period.[26]
Initial attempts
Initial planning
The need for a subway line under Manhattan's Second Avenue was recognized shortly after the First World War. In 1919, the New York Public Service Commission launched a study at the behest of engineer Daniel L. Turner to determine what improvements were needed in the city's public transport system. The Second Avenue Elevated operated above Second Avenue north of the Queensboro Bridge until 1940, and south to downtown, part of the way on First Avenue, until June 13, 1942.[19] The Third Avenue Elevated operated a block to the west until 1955.[20] Turner's final paper, titled Proposed Comprehensive Rapid Transit System, was a massive plan calling for new routes under almost every north-south Manhattan avenue, extensions to lines in Brooklyn and Queens, and several crossings of the Narrows to Staten Island. Massively scaled-down versions of some of Turner's plans were found in proposals for the new city-owned Independent Subway System (IND).[27] Among the plans was a massive trunk line under Second Avenue consisting of at least six tracks and numerous branches throughout Brooklyn, Queens, and the Bronx.[28]
In 1929, the Board of Transportation of the City of New York tentatively approved the expansion, which included a Second Avenue Line with a projected construction cost of $98,900,000, not counting land acquisition. From north to south, the 1929 plan included four tracks from the Harlem River (where it would continue north as a Bronx trunk line with several branches) to 125th Street, six tracks from 125th Street to a link with the IND Sixth Avenue Line at 61st Street, four tracks from 61st Street to Chambers Street, and two tracks from Chambers Street to Pine Street.[28] Due to the Great Depression, the soaring costs of the expansion became unmanageable. Construction on the first phase of the IND was already behind schedule, and the city and state were no longer able to provide funding. A scaled-down proposal including a turnoff at 34th Street and a connection crosstown was postponed in 1931.[28]
Further revision of the plan and more studies followed. By 1939, construction had been postponed indefinitely, and Second Avenue was relegated to "proposed" status. The 1939 plan for subway expansion took the line not only into the Bronx (by now as a single line to Throggs Neck) but also south into Brooklyn, connecting to the stub of the IND Fulton Street Line at Court Street.[28] The United States' entry into World War II in 1941 halted all but the most urgent public works projects, delaying the Second Avenue Line once again.[28]
After World War II
Finally, in 1945, plans for the Second Avenue Subway were again revised. The southern two-track portion was abandoned as a possible future plan for connecting the line to Brooklyn.[28]
A 1947 plan once again connected the Second Avenue Line to Brooklyn, but via the BMT trackage over the Manhattan and Williamsburg Bridges. A connection would allow trains from these bridges to go onto the IND Sixth Avenue Line rather than the Second Avenue Line. Other connections to the Second Avenue Line were to be provided at 57th Street, via a line connecting to the Sixth Avenue Line; two express tracks would be built along that line north of West Fourth Street. The IRT Pelham Line would be switched to the combined IND/BMT division (this plan also includes other connections, which have been built), and connected to the Second Avenue Line. The Second Avenue Line would end just north of that connection, at 149th Street, with transfers to the IRT White Plains Road Line and the elevated IRT Third Avenue Line, the latter of which would be demolished south of 149th Street. Another plan in 1951 mirrored this intention.[29]
In 1949, the New York Board of Transportation accepted delivery of ten new prototype subway cars made of stainless steel from the Budd Company, named by their contract, R11, specifically intended for the Second Avenue Subway. They cost US$100,000 (US$1,280,559 in 2024 dollars[30]) each; the train became known as the "million dollar train". The cars featured porthole style round windows and a new public address system. Reflecting public health concerns of the day, especially regarding polio, the R11 cars were equipped with electrostatic air filters and ultraviolet lamps in their ventilation systems to kill germs.[21][31]
By 1950, the plans called for a connection from Second Avenue at 76th Street to 34th Avenue in Queens, via a new tunnel under the East River. The city was barely able to raise money for the construction effort, but the onset of the Korean War caused soaring prices for construction materials and saw the beginning of massive inflation.[29]
A 1954 plan added another feeder, an East River tunnel at 76th Street, connecting existing Long Island Rail Road (LIRR) trackage (which would be converted for subway use) to the Second Avenue Line towards downtown. This plan has been revitalized as part of the 2005 Transportation Bond Act, which would connect the LIRR trackage to Grand Central Terminal via the 63rd Street Tunnel as part of the East Side Access project.[29]
The southernmost part of the 1947 plan, connecting the two BMT bridges to the IND Sixth Avenue Line, was built in the 1960s and opened in 1967 as the Chrystie Street Connection. Other parts of that plan were carried out, including the connection at 57th Street (moved to 63rd Street) and the abandonment of the IRT Third Avenue Line south of 149th Street, but the rest of the Second Avenue Line was not built. Plans now call for an additional two tracks in the Chrystie Street area for the Second Avenue mainline; current plans have the new tracks under the old ones, while older plans had one track on each side of the Chrystie Street Connection. However, track maps on the MTA's website show that all stations, except for Hanover Square and 125th Street, will have two tracks and one island platform. (72nd Street was conceived as a three-track, two-platform station, as are 125th Street and Hanover Square. However, 72nd Street is being constructed with two tracks and one platform.)[32][33]
1970s: Completed segments
In 1964, Congress passed the Urban Mass Transportation Act, promising federal money to fund mass transit projects in America's cities via the Urban Mass Transportation Administration. In 1967, voters approved a $2.5 billion Transportation Bond Issue, which provided over $600 million for New York City projects, including for a 1968 Program for Action. The Second Avenue project, for a line from 34th Street to the Bronx, was given top priority. The City secured a Urban Mass Transportation Administration (UMTA) grant for initial construction, and a groundbreaking ceremony was held on October 27, 1972. Construction began shortly thereafter at Second Avenue and 103rd Street.[34]
However, the city soon experienced its most dire fiscal crisis yet. The stagnant economy of 1975, combined with the massive outflow of city residents to the suburbs, led to a fiscal disaster for the city. Construction of the subway was halted, with only three sections of tunnel having been completed, excluding the Chrystie Street Connection. These sections are between Pell and Canal Street, between 99th and 105th Streets,[35] and between 110th and 120th Streets.[35][36] The section between 99th and 105th is being renovated with tail tracks[37] and will be used for train storage north of the 96th Street station in Phase One of the SAS. The section between 110th and 120th Streets will be used in Phase Two of the project (96th to 125th). The section from Pell to Canal will not be used under the current preferred alternative. Instead, the current proposal calls for the subway to pass under Confucius Plaza, which is adjacent to this segment. Some construction work also took place between 2nd and 9th Streets, though the extent is disputed. Some reports say that only utilities were relocated, while others that it was excavated but filled back in.[36]
In 2007, the MTA reported that the 1970s-era tunnel segments are in pristine condition.[38] A section of tunnel adjacent to the Confucius Plaza, however, was shown to be lightly graffitied in June 2005.[39]
To date, the three portions completed in the 1970s (excluding the BMT 63rd Street Line and the Chrystie Street Connection) have no infrastructure or track,[38] except for the 99th–105th Streets section, which had its track installed starting in winter 2013.[1]
Construction
Current development
Template:NYCS logoTemplate:NYCS logo With the city's economic and budgetary recovery in the 1990s, there was a revival of efforts to complete construction of the SAS. Rising ridership on the IRT Lexington Avenue Line, the only subway trunk line east of Central Park, demonstrated the need for the Second Avenue Line, as capacity and safety concerns rose.
The MTA's final environmental impact statement was approved in April 2004; the latest proposal is for a two-track line from 125th Street and Lexington Avenue in Harlem, down Second Avenue to Hanover Square in the Financial District. The new subway line will actually carry two services. The full-length Second Avenue line, extending from Harlem to the Financial District, probably will be given the turquoise[40] T as its letter designation. However, it is the other service, a proposed reroute of the Q, which will begin carrying passengers first.
The MTA plan calls for building the Second Avenue Subway in four segments with connections to other subway lines. The first segment (Phase One) is a proposed reroute of the Q, BMT Broadway Line across 63rd Street and north along Second Avenue to the Upper East Side at 96th Street. Phase Two will extend the rerouted Q train to 125th Street. In Phase Three, the new T train will run from 63rd Street to Houston Street. The final phase will extend T train service from Houston Street to Hanover Square in Lower Manhattan.[41]
More spacious stations like those on the Washington Metro, quieter trains, and better ventilation allowing for temperatures in the summer 10 percent cooler than outside are also promised.[42]
New York voters passed a transportation bond issue in November 2005, allowing for dedicated funding allocated for Phase One. The U.S. Department of Transportation announced on December 18, 2006, they would allow the MTA to commit up to $693 million in funds to begin construction of the Second Avenue Subway Line and that the federal share of such costs would be reimbursed with FTA transit funds, subject to appropriations and final labor certification.[43] In March 2007, the MTA awarded the first construction contract.[44][45][46] A ceremonial groundbreaking took place in April 2007, in a tunnel segment built in the 1970s at 99th Street.[47]
In June 2008, the MTA, facing cost increases for construction materials and diesel fuel affecting the prices of contracts not yet signed, announced that certain features of the Second Avenue Subway would be simplified to save money. One set of changes, which significantly reduces the footprint of the subway in the vicinity of 72nd Street, is the alteration of the 72nd Street Station from a three-track, two-platform design to a two-track, single island platform design, paired with a simplification of the connection to the BMT Broadway Line's Second Ave extension. Supplemental environmental impact studies covering the changes to for the proposed 72nd Street and 86th Street stations were completed in June 2009.[48][49][50]
Deep bore tunneling methods are being used in construction to avoid the disruptions for road traffic, pedestrians, utilities and local businesses produced by cut-and-cover methods of past generations. Stations will retain cut-and-cover construction.[51]
The construction site extends from 105th Street and Second Avenue to 63rd Street and Third Avenue.[52] Construction began with moving utility pipes, wires, and other infrastructure, which took 14 months, far more than the MTA's anticipated eight months. For boring, a trench was dug from 96th to 93rd Streets. The tunnel boring machine started work in May 2010, beginning at 92nd Street and boring southward to connecting shafts built at 86th and 72nd Streets.[53][54] Tunneling work was completed in September 2011.[55]
First phase construction
In March 2007, the MTA awarded a contract for constructing the tunnels between 92nd and 63rd Streets, a launch box for the tunnel boring machine (TBM) at 92nd to 95th Streets, and access shafts at 69th and 72nd Streets. This contract, valued at $337 million, was awarded to a joint venture of Schiavone Construction, Skanska USA Civil and San Francisco-based J.F. Shea Construction.[56]
The ceremonial groundbreaking for the first phase of the Second Avenue subway was held on April 12, 2007.[57] Actual construction work began, on the surface of Second Avenue between 91st and 95th Streets, on April 23, 2007.
On May 28, 2009, the MTA awarded a $303.8 million contract to E.E. Cruz and Tully Construction Co., a joint venture and LLC, to construct the 96th Street station box.[58] Work began in July on site clearing and utility relocation necessary to prepare for the installation of slurry walls between 95th and 99th Streets where the station connects to the existing tunnel section built in the 1970s.
In June 2009, the first of three contracts for the 86th Street Station was awarded for the advance utility relocation work and construction of cut and cover shaft areas at 83rd and 86th Streets. This contract provided two vertical starter shafts that will be used by a subsequent contractor to excavate the station cavern in the rock between 83rd and 86th Streets.
On June 5, 2009, an apartment building at 1772 Second Avenue was evacuated by the NYC Department of Buildings (DOB) after it was determined that the building was in danger of collapse.[59] Then on June 29, 2009, the DOB evacuated a mixed use building at 1768 Second Avenue/301 East 92nd Street because it too was in danger of collapse.[60] The evacuation of these two buildings delayed the contractor's plan to use controlled blasting to remove bedrock in the southern section of the launch box.[61] Until the blasting permits could be issued, MTA required contractors to use mechanical equipment to remove the bedrock, which is slower than blasting out the rock.[62] As of October 2009[update], one building had been shored up, and work was in progress on the second; MTA had rescheduled blasting to begin during the week of November 2.[63]
On October 1, 2010, MTA awarded a $431 million contract to SSK Constructors (a joint venture) for the mining of the tunnels connecting the 72nd St station to the existing 63rd Street station, and for the excavation and heavy civil structures of the 72nd St Station. Subsequent contracts will be awarded for the following: excavation of the cavern at 86th Street Station; architectural and mechanical and electrical work at 72nd, 86th and 96th Street Stations; rehabilitation of the 63rd Street Station; and the Systems Contract (track, signals and communications) for the entire Phase 1 area. On January, MTA awarded Judlau Contracting a 40-month, $176,400,000 contract to rebuild and enlarge the Lexington Ave/63rd Street Station.[64]
On May 14, 2010, the Tunnel Boring Machine was started at the Second Avenue Subway launch box at 96th Street. The TBM dug at a rate of approximately 50 feet (15 m) per day; the TBM finished its run at the planned endpoint under 65th Street on February 5, 2011.[65] S3 partially disassembled the TBM and backed it out of the tunnel. It was repositioned in the east starter tunnel to begin boring again.[66] Because the east side of Second Avenue has some soft ground not compatible with the Robbins TBM, ground-freezing was undertaken to prepare the soil for the TBM.[14][67][68] On March 28, 2011, S3, having completed its task of completing the 7,200-foot (2,200 m) west tunnel to 65th Street, began drilling the east tunnel, with the first 200 feet (61 m) being through soil frozen by S3 using calcium chloride fed through a network of pipes.[69] The TBM drilling the east tunnel will negotiate the curve onto 63rd Street and break through the bellmouth at the existing 63rd St subway station. The portion of the west tunnel remaining to be created will be mined using conventional drill-and-blast methods, because the curve S3 construction teams would have to negotiate is too tight for the TBM.
On September 22, 2011, the TBM completed its run to the Lexington Avenue – 63rd Street station's bellmouth.[70][71]
On a July 2013 "report card" that indicated the progress of the subway by Congresswoman Carolyn Maloney, it got a "B".[72]
By the winter of 2013, many of the tracks and signal panels began to arrive at the construction site, to be installed on the line over the next few years.[1] It was reported in November 2013 that one third of the tracks for the line had arrived, for the segments of track between 87th and 105th Streets;[1] the tracks were being stored at 96th Street station.[73]
Construction status
The MTA and its contractors on the project meet on a regular basis with the Manhattan Community Board 8 Second Avenue Subway Task Force and Manhattan Community Board 11 to report on construction progress and to seek input from the community.[74] The MTA maintains a Construction Look Ahead web page that summarizes the planned construction activity for the next three weeks.[75]
The MTA's forecasted opening date for Phase I is December 30, 2016, as of January 2, 2015[update].[76][1][77] Horodniceanu called earlier estimates lacking "the precision required."[42] On May 2, 2014, it was reported that Phase 1 of the line was 66% complete, and six of the ten construction contracts awarded were already being worked on. The agency was still targeting December 2016 as a completion date, and the project is still within budget at a cost of $4.45 billion,[78][79][80][81][82] while serving approximately 200,000 daily riders.
Estimated completion schedules have provided much fodder for critics. As of 2009[update], the proposed construction schedule showed the Second Avenue Subway opening for passenger service in 2016.[83] Other recent publications have listed expected construction dates as follows:
- 2007–16:[84] Phase 1 (96th St. to 63rd St.) State Funding In-Place, Federal Funding Approved.[85] In its 2008 capital improvement budget proposal, the MTA pushed back completion of Phase 1 from 2014 to 2015. In 2009, the MTA pushed it back again to 2016.[86] As of January 2015[update], the line is still scheduled to open in December 2016.[87][88]
- Phase 2 (125th St. to 96th St.) $1.5 billion in funding to be proposed in the MTA's 2015–2019 Capital Plan. If approved, money will be used to update the Phase 2 design and the necessary environmental review; construction would most likely not start until 2019 at the earliest.[89][90]
- Phase 3 (63rd St. to Houston St.) No funding commitments.[88]
- Phase 4 (Houston St. to Hanover Square) No funding commitments.[88]
Concrete testing controversy
American Standard Testing and Consulting Laboratories, company president Alan Fortich, and five other executives admitted filing false documents on "thousands" of New York City construction projects — including the Yankee Stadium, the Second Avenue Subway, and Memorial Sloan-Kettering Cancer Center — over 10 years. ASTCL had replaced Testwell Inc., another firm indicted for faking concrete tests, in 2008.[91]
Construction methods
Planned construction methods vary depending on the section of the line, due to varying underground conditions. The methods planned for each section are as follows:[92][93]
Streets | Construction method | Streets | Construction method | Streets | Construction method |
Lex–2 Aves | Tunnel Boring Machine | 101–95 | Cut and Cover | 43–41 | Mined with Cut and Cover |
125–123 | Mined with Cut and Cover | 95–87 | Tunnel Boring Machine | 41–34 | Tunnel Boring Machine |
123–120 | Tunnel Boring Machine | 87–84 | Mined with Cut and Cover | 34–32 | Cut and Cover |
120–117 | Existing | 84–73 | Tunnel Boring Machine | 32–24 | Tunnel Boring Machine |
117–114 | Cut and Cover | 73–71 | Mined with Cut and Cover | 24–22 | Mined with Cut and Cover |
114–109 | Existing | 71–58 | Tunnel Boring Machine | 22–15 | Tunnel Boring Machine |
109–106 | Cut and Cover | 58–56 | Cut and Cover | 15–13 | Cut and Cover |
106–101 | Existing | 56–43 | Tunnel Boring Machine | 13–Hanover | Undecided |
A number of methods will be used to tunnel for 13.7 kilometers (8.5 mi) underneath Manhattan, which is densely populated. 90% of the tunneling will be performed by a tunnel boring machine. The rest will be done using the cut and cover method and mined drill and blast, for sections, generally the 16 stations, that average 275 meters (902 ft) in length. The stations at 86th and 72nd Streets will be mined. This will be challenging, given the number of expensive high rise properties in their vicinities. The 96th Street cut-and-cover station will be at about 15 meters (49 ft) deep, making it one of the shallowest stations being built on the line. This is so that the new line can align with the preexisting piece of subway tunnel built in the 1970s between 99th and 105th Streets. Stations at the two mined stations will be between 25.9 and 27.4 meters (85 and 90 ft) deep in rock. The construction method that will be used should ease concerns for the above buildings, because only two shafts will be required for excavation.[94]
In Phase 1, there will be tunneling between East 63rd and 92nd Streets and a 248-by-23-meter-wide (814 by 75 ft) TBM launch box will be built. That will ultimately become part of the 15-meter-deep (49 ft) 96th Street Station. Two access shafts will be constructed for the East 72nd Street Station. Slurry or diaphragm walls, 1.1 meters (3.6 ft) wide and 6.1 meters (20 ft) long and about 35 meters (115 ft) deep, will be built alongside the sections between East 93rd and 95th Streets. Since the rock is shallower between East 91st and 93rd Streets, 1.1-meter-diameter (3.6 ft) secant piles will do the same work at shallower depths.[94]
Earth excavation will be conducted between walls, once they are installed, and a box structure will be built using a bottom-up construction method. Temporary decking will constitute the top of the box, and the decking will both brace the excavation and support the walls and Second Avenue traffic.[94]
The tunnels and stations will be up to about 30 meters (98 ft) below street level. Of the below-ground obstacles, Arup director of construction David Caiden says: "It’s a spaghetti of tunnels, utilities, pipes and cables — I’ve never seen anything like it."[94] Additionally, in later phases, the project must go over, or under, subway lines, Amtrak railway lines, and the Queens-Midtown Tunnel linking Manhattan and Queens.[94]
There are geological anomalies along the way. Manhattan's geology changes along the subway’s length, passing through rock and soft ground, consisting of sands, silts, and clays over Manhattan schist, and there are faults and shear zones as well as fractured rock. Hard-rock Tunnel Boring Machines 6.7 meters (22 ft) in diameter will tunnel during the first phase, progressing at anticipated rate of about 20 meters (66 ft) per day.[94]
The stations on the line are built so that they are more wide open than most other underground subway stations in the system;[95] they were likened to the stations on the Washington Metro by Dr. Michael Horodniceanu.[96]
Planned route/stations and designation
The plans for the Second Avenue Subway involve digging 8.5 miles (13.7 km) of new tunnel from 125th Street in Harlem south to Hanover Square, which is located in Manhattan's Financial District.[97][98] Initially, during Phase I, the line will begin at the intersection of Second Avenue and 96th Street, running south to join the BMT Broadway Line via the existing BMT 63rd Street Line. Phase I stations will be located at 96th Street, 86th Street and 72nd Street.[97][98] Plans call for the Q service to be routed to 96th Street,[98] and then in Phase II to 125th Street and Lexington Avenue.[98] After Phase III, the new[99] T service will operate from 125th Street to Houston Street.[98] After Phase IV opens, T service will run the full length of the line, from 125th Street to Hanover Square.[98]
The MTA decided to designate the main, full-length Second Avenue service the T in part for the following reasons:
- The letters O and I are too easily confused with the digits 0 and 1, respectively.[100]
- The letters H and K were used in the relatively recent past to denote services on the IND Eighth Avenue Line, as well as on the BMT Jamaica Line, and thus are not preferred.
- The letters P, U and Y are too similar to words.[100]
The letter T was the one selected by MTA for the new service.[101]
The proposed stations of the Second Avenue Line are as follows:[97]
Station | Phase | Transfers & Notes | |
---|---|---|---|
125th Street | 2 | 4, 5, 6, and <6> trains (IRT Lexington Avenue Line) at Lexington Avenue and 125th Street M60 Select Bus Service to LaGuardia Airport connection to Harlem – 125th Street (Metro-North Railroad) northern terminal station for Q train (Phase 2) and T train (Phase 3) | |
Provision for expansion to The Bronx | |||
116th Street | 2 | ||
106th Street | 2 | ||
96th Street | 1 | northern terminal station for Q train in Phase 1 | |
86th Street | 1 | ||
72nd Street | 1 | ||
Q train splits to BMT Broadway Line via BMT 63rd Street Line (Phase 1) | |||
T train continues down Second Avenue (Phase 3) | |||
55th Street[note 1] | 3 | E and M trains (IND Queens Boulevard Line) at Lexington Avenue – 53rd Street 4, 6, and <6> trains (IRT Lexington Avenue Line) at 51st Street | |
42nd Street[note 1] | 3 | 7 and <7> trains (IRT Flushing Line) S train (IRT 42nd Street Shuttle) 4, 5, 6, and <6> trains (IRT Lexington Avenue Line) at Grand Central – 42nd Street connection to Grand Central Terminal (Metro-North Railroad & Long Island Rail Road once East Side Access Project is completed) | |
34th Street | 3 | ||
23rd Street | 3 | ||
14th Street[note 1] | 3 | L train (BMT Canarsie Line) at Third Avenue | |
Houston Street[note 1] | 3 | F and <F> trains (IND Sixth Avenue Line) at Second Avenue southern terminal station for T train (Phase 3) | |
Grand Street | 4 | B and D trains (IND Sixth Avenue Line) at Grand Street | |
Chatham Square | 4 | at Worth Street | |
Seaport | 4 | at Fulton Street | |
Hanover Square | 4 | at Old Slip southern terminal station for T train (Phase 4) | |
Provision for expansion to Brooklyn |
The above stations will serve the Second Avenue main service, terminating at 125th Street and at Hanover Square.[97] In addition to the main service, tentatively dubbed the T, and colored turquoise, a connection is planned to the BMT Broadway Line, utilizing an existing connection via the BMT 63rd Street Line, as part of phase 1.[97] The Q service will most likely be extended northward from 57th Street – Seventh Avenue, curving east under Central Park on the unused portion of the BMT 63rd Street Line.[97] The Q train would stop at Lexington Avenue – 63rd Street with a cross-platform interchange to the IND 63rd Street Line (F train) before merging with the Second Avenue Line at 64th Street.[97] Thus, the residents of Spanish Harlem and the Upper East Side will have direct mass transit service down both Second Avenue and Broadway to the Financial District, and across the Manhattan Bridge to Brooklyn via the Q train.[97][98]
An additional two-track connection is planned between the line toward Lower Manhattan (around 63rd Street) and the IND 63rd Street Line toward Queens; current plans don't call for it to be used by regular service.[97][98]
Provisions are also being made for an extension north under Second Avenue past 125th Street to the Bronx, and an extension south to Brooklyn.[97][98]
Entrance and exit locations
Contrary to other subway stations, entrances are not located at every corner of the intersection that the station serves; rather, there are entrances spread across several intersections. Also, at each intersection, there will only be an entrance on one or two corners of the intersection.
The 72nd Street entrances are:[102][103]
- Entrance 1: Escalators (in station house) and two stairs (outside station house) on the NE corner of Second Avenue and 69th Street, at 301 East 69th Street[104][102]
- Entrance 2: Ancillary building and stairs/escalators on the NW corner of Second Avenue and 72nd Street[102]
- Entrance 3: Five elevators on the SE corner of Second Avenue and 72nd Street[104][102]
The 86th Street entrances are:[105]
- Entrance 1: Stairs/escalators on the NE corner of Second Avenue and 83rd Street[105]
- Entrance 2: Two stairs near the NE corner of Second Avenue and 86th Street (one along 86th Street at the corner; the other midblock on north side of 86th Street)[105]
- Entrance 3: Elevator on the SW corner of Second Avenue and 86th Street[105]
The 96th Street entrances are:[106]
- Entrance 1: Escalator bank and elevator on the SW corner of Second Avenue and 94th Street[106]
- Entrance 2: Escalator bank on the NE corner of Second Avenue and 94th Street[106]
- Entrance 3: Escalator bank on the SW corner of Second Avenue and 96th Street[106]
See also
Notes
References
- ^ a b c d e f MTA.info—Second Avenue Subway Quarterly Report Q4 2013
- ^ MTA releases Second Avenue subway images, says project on track NY Daily News, November 5, 2013
- ^ Nolan, Caitlin (May 16, 2014). "Second Avenue subway line construction is progressing: officials". NY Daily News. Retrieved May 19, 2014.
- ^ Smith, Stephen J. (October 2, 2013). "The Next 20 Years for New York's MTA – Next City". Nextcity.org. Retrieved June 5, 2014.
- ^ Andrew J. Hawkins (December 19, 2014). "Second Avenue subway's first phase is 76% done". Crain's Insider. Crain's New York. Retrieved December 24, 2014.
- ^ a b Sargent, Greg (March 29, 2004). "The Line That Time Forgot – Second Avenue Subway". Nymag.com. Retrieved August 2, 2009.
{{cite journal}}
: Cite journal requires|journal=
(help) - ^ "The line that time forgot". PlanNYC. April 5, 2004. Retrieved August 2, 2009.
- ^ MTA Press Release March 20, 2007—First Construction Contract Signed for Second Avenue Subway; Work to Begin in April
- ^ "Arup to design new Second Avenue Subway, New York". Arup. November 20, 2001. Archived from the original on February 5, 2009. Retrieved June 9, 2013.
- ^ "Second Avenue Subway – Transport Consulting". Arup. Archived from the original on February 2, 2009. Retrieved June 9, 2013.
- ^ a b "Second Avenue Subway – A Status Report" (PDF). Retrieved August 2, 2009.
- ^ Putzier, Konrad (May 14, 2014). "Real Estate Weekly » Blog Archive » Light at end of tunnel for Second Ave. subway". Rew-online.com. Retrieved June 5, 2014.
- ^ " "Blasting on Second Avenue". thelaunchbox.blogspot.com. March 22, 2010.
- ^ a b Siff, Andrew (May 14, 2010). "2nd Ave. Subway Tunnel Dig Begins". WNBC. Retrieved May 14, 2010.
- ^ "Tunneling Begins Under Second Avenue". MTA. May 14, 2010. Archived from the original on August 17, 2012. Retrieved May 17, 2010.
- ^ Various (September 23, 2011). "Second Avenue Subway has a breakthrough moment; several billion more are all the M.T.A. wants". Capital New York. Retrieved March 31, 2014.
- ^ "Second Avenue Subway in the Borough of Manhattan, New York County, New York Final Environmental Impact Statement And Final Section 4(f) and Section 6(f) Evaluation" (PDF). April 2004. pp. 1–5, 1–6. Retrieved September 22, 2011.
- ^ "mta.info – Facts and Figures". mta.info.
- ^ a b Staff. "Second Avenue 'El' Coming to a Stop", The Christian Science Monitor, June 13, 1942. Accessed October 12, 2008.
- ^ a b Last Train Rumbles on Third Ave. 'El', New York Times May 13, 1955 page 1
- ^ a b Neuman, William (March 24, 2007). "A Museum-Quality Car for a Subway Yet Unbuilt". New York Times. Retrieved February 20, 2010.
- ^ "Second Avenue Subway". web.mta.info. Metropolitan Transportation Authority. Retrieved April 7, 2014.
- ^ Chan, Sewell (November 14, 2005). "The Bond Passed. Now Comes the Hard Part: Actually Building a 2nd Avenue Subway". The New York Times. The New York Times. Retrieved April 7, 2014.
- ^ Chan, Sewell (November 9, 2005). "Voters Approve Transit Bonds for $2.9 Billion". The New York Times. Retrieved September 20, 2007.
- ^ Donohue, Pete (August 4, 2006). "Cooler Subways Coming Eventually". Daily News. New York. Archived from the original on October 10, 2007. Retrieved December 12, 2008.
- ^ Neuman, William (November 19, 2007). "U.S. Approves $1.3 Billion for 2nd Avenue Subway". The New York Times. Retrieved November 19, 2007.
- ^ 100 Miles of Subway in New City Project; 52 of them in Queens, New York Times September 16, 1929 page 1
- ^ a b c d e f "www.nycsubway.org". www.nycsubway.org.
- ^ a b c "Board of Transportation – 1951". Thejoekorner.com. Retrieved March 25, 2014.
- ^ 1634–1699: McCusker, J. J. (1997). How Much Is That in Real Money? A Historical Price Index for Use as a Deflator of Money Values in the Economy of the United States: Addenda et Corrigenda (PDF). American Antiquarian Society. 1700–1799: McCusker, J. J. (1992). How Much Is That in Real Money? A Historical Price Index for Use as a Deflator of Money Values in the Economy of the United States (PDF). American Antiquarian Society. 1800–present: Federal Reserve Bank of Minneapolis. "Consumer Price Index (estimate) 1800–". Retrieved February 29, 2024.
- ^ R-11 Datasheet
- ^ SAS track map, south of 57th Street
- ^ SAS track map, north of 57th Street
- ^ Second Avenue Subway: Timeline. Retrieved April 7, 2014.
- ^ a b "The Line That Time Forgot – Second Avenue Subway". Nymag.com. April 5, 2004. Retrieved April 10, 2014.
- ^ a b FAQ: Completed Portions of the 2nd Avenue Subway. Retrieved April 7, 2014.
- ^ "96th Street Station Area" (PDF). Second Avenue Subway Newsletter. February 2013. Retrieved June 9, 2013.
- ^ a b "Video: Explore The Abandoned Second Avenue Subway Tunnels". Gothamist. February 1, 2012.
- ^ "LTV Exploration // Abandoned subway stations, industrial buildings, and general decay in NYC chinatown tunnel". Ltvsquad.com. June 19, 2005. Retrieved April 3, 2014.
- ^ Train Line Far From Arrival Has a Color to Be Noticed
- ^ "MTA Capital Construction – Second Avenue Subway Project Description". mta.info. MTA. Retrieved October 5, 2013.
- ^ a b Rivoli, Dan, "Second Avenue Subway Scenes," amNew York, May 2–4, 2014, p.6
- ^ "U.S. Transportation Secretary Signs Record $2.6 Billion Agreement to Fund New Tunnel Network To Give Long Island Commuters Direct Access to Grand Central Station". United States Department of Transportation. December 18, 2006. Archived from the original on July 9, 2009. Retrieved September 20, 2007.
- ^ Olshan, Jeremy (March 21, 2007). "Second Ave. Tunnel Vision". New York Post. Archived from the original on April 16, 2009. Retrieved January 9, 2009.
- ^ "MTA Signs Second Ave. Subway Contract". New York Sun. March 21, 2007. Retrieved February 20, 2010.
- ^ 2nd Avenue Subway Contract Signed – WNYC Newsroom, March 21, 2007
- ^ "MTA Capital Construction – Second Avenue Subway: History". mta.info. MTA.
- ^ "Microsoft PowerPoint – 0080617_CB8_Final [Compatibility Mode]" (PDF). Retrieved August 2, 2009.
- ^ "Microsoft PowerPoint – 080729_CB8_Final_distribution version" (PDF). Retrieved August 2, 2009.
- ^ "MTA Capital Construction – Second Avenue Subway: Documents". mta.info. MTA. Retrieved October 5, 2013.[dead link ]
- ^ Stabile, Tom (May 2006). "New York's Subway System Finally Starting Major Expansion". newyork.construction.com. Archived from the original on May 9, 2008. Retrieved December 12, 2008.
- ^ Nonko, Emily (January 30, 2014). "Updates on NYC's Biggest Subway Projects: Second Avenue and East Side Access – January 30, 2014". NewYork.com. Retrieved June 5, 2014.
- ^ "MTA Launches Second Avenue Subway Tunnel Boring Machine". MTA Press Releases. May 14, 2010. Retrieved October 5, 2013.
- ^ Exclusive: Ground Breaking For 2nd Avenue Subway Line Weeks Away – NY1, January 24, 2007
- ^ "Second Avenue Subway TBM Breakthrough 9/22/2011". MTAPhotos. MTA. Retrieved October 5, 2013.
- ^ NY Construction—Top Projects, page 1.
- ^ "Second Avenue subway groundbreaking: Is 4th time the charm?". The Journal News. April 12, 2007. Retrieved April 18, 2007.
- ^ "MTA Capital Construction Recent Contract Awards, retrieved May 30, 2009". Mta.info. Retrieved August 2, 2009.
- ^ Namako, Tom (June 6, 2009). "2nd Ave. Subway Caused Building Evac: Officials". New York Post.
- ^ Sutherland, Amber; Namako, Tom (July 1, 2009). "Second Ave. Tenants RIP 'Train Wreck'". New York Post.
- ^ Rivoli, Dan (September 2, 2009). "2nd Ave. Subway Delays". Our Town. Archived from the original on July 15, 2011. Retrieved February 20, 2010.
- ^ Simeone, Jessica; Namako, Tom (September 26, 2009). "Second Ave. on Snail Rail". New York Post.
- ^ Second Avenue Subway
- ^ "MTA Capital Construction – Procurement". mta.info.
- ^ COMMUNITY BOARD EIGHT PROJECT UPDATE, MTACC, February 15, 2011
- ^ "Excavation of West Tunnel for Second Avenue Subway Almost Complete". MTAcPress Release. Retrieved February 5, 2011.
- ^ "Boring Manhattan: Ceremony Launches Subway Project". WCBS-TV. Associated Press. May 14, 2010. Archived from the original on May 17, 2010. Retrieved May 14, 2010.
- ^ Roth, Jamie (May 14, 2010). "Boring for new 2nd Avenue subway begins". WABC-TV. Retrieved May 14, 2010.
- ^ "Tunneling for Second Avenue Subway Continues". Metropolitan Transportation Authority. March 28, 2011. Archived from the original on August 17, 2012. Retrieved September 24, 2011.
- ^ Greg B. Smith (June 2, 2013). "Second Avenue subway plagued with dangerous conditions and safety violations". NY Daily News. Retrieved May 4, 2014.
- ^ "Second Avenue Subway has a breakthrough moment; several billion more are all the M.T.A. wants". Capital NY. September 23, 2011. Retrieved May 27, 2014.
- ^ http://maloney.house.gov/sites/maloney.house.gov/files/documents/transportation/2ndavesubway/20130729Fourth2ndSubwayReportCardReport.pdf
- ^ Harshbarger, Rebecca (November 4, 2013). "MTA gives new peek at 2nd Ave. subway". New York Post. Retrieved May 13, 2014.
- ^ "Microsoft PowerPoint – 090323 S3 Construction Update _final [Compatibility Mode]" (PDF). Retrieved August 2, 2009.
- ^ Construction Look Ahead
- ^ "mta.info – Capital Programs Second Avenue Subway". mta.info.
- ^ The Launch Box—Fewer Than 1,000 Days to Go!
- ^ Andrea Gryme (May 1, 2014). "Progress Moves Ahead For Phase One Of Second Avenue Subway « CBS New York". CBS Local Media, a division of CBS Radio Inc. Retrieved May 4, 2014.
- ^ Sanders, Anna (May 1, 2014). "10 facts about the Second Avenue Subway". Metro.us. Retrieved May 4, 2014.
- ^ "Second Avenue Subway progress: Dec. 2016 end date on track". AM New York, Newsday. April 1, 2014. Retrieved May 4, 2014.
- ^ Watson, Leon. "Manhattan's colossal construction site for Q line subway extension | Mail Online". Associated Newspapers Ltd, Part of the Daily Mail, The Mail on Sunday & Metro Media Group. Retrieved May 4, 2014.
- ^ Michael Hession (May 2, 2014). "A Subterranean Stroll Through NYC's Newest Train Tunnel". Gizmodo.com. Retrieved May 4, 2014.
- ^ "090924_C1C2AC5ACombined_CB8_final+-+p.3.jpg (image)". bp.blogspot.com.
- ^ Neuman, William (May 18, 2007). "Manhattan: Budget Increases for New Subway". The New York Times. Retrieved May 24, 2007.
- ^ Earle, Geoff (April 17, 2006). "Feds Finally Aboard 2nd Avenue $ubway". New York Post. Archived from the original on June 14, 2006. Retrieved June 9, 2013.
- ^ Donohue, Pete (April 24, 2009). "Second Ave. subway set back – again". Daily News. New York. Retrieved February 20, 2010.
- ^ "mta.info – Capital Programs Second Avenue Subway". mta.info.
- ^ a b c Donohue, Pete (January 20, 2013). "Second Ave. subway on track to open in 2016: MTA". Daily News. New York. Retrieved March 25, 2013.
- ^ "MTA to propose $1.5B to Phase 2 of 2nd Ave. subway construction". NY Daily News.
- ^ "Second Avenue Subway Gets $1.5B for Phase 2 Construction". Curbed NY.
- ^ Smith, Greg B., "Concrete certification company American Standard Testing admits it faked safety and inspection reports on thousands of New York City buildings", New York Daily News, December 14, 2012. Retrieved December 14, 2012.
- ^ Second Avenue Subway
- ^ "IMG_9776c.JPG (image)". bp.blogspot.com.
- ^ a b c d e f Wynne, Alexandra (January 20, 2009). "Fairytale of New York – Second Avenue Subway takes shape | Features | New Civil Engineer". Nce.co.uk. Retrieved August 2, 2009.
- ^ Hession, Michael (May 2, 2014). "A Subterranean Stroll Through NYC's Newest Train Tunnel". Gizmodo. Retrieved May 13, 2014.
- ^ Rivoli, Dan (May 1, 2014). "Second Avenue Subway progress: Dec. 2016 end date on track". AM New York. Retrieved May 14, 2014.
- ^ a b c d e f g h i j "Final Summary Report" (PDF). Metropolitan Transportation Authority. October 11, 2001. Retrieved April 10, 2014.
- ^ a b c d e f g h i "Making the Case" (PDF). Federal Transit Administration. August 20, 2004. Retrieved April 10, 2014.
- ^ Hirschman, David (August 2008). "The T Train: NYC Will Get Its First New Subway Line in 70 Years". Wired.com (Aug '08). Wired Magazine: 36. Archived from the original on July 25, 2008. Retrieved April 8, 2014.
The old (1960s) T service was also called the West End train. The reference was to Brooklyn. By contrast, the new T service will serve the East Side of Manhattan, and "will unite the Upper and Lower East Sides."
- ^ a b V and W Trains join a long list of routes that have bowed out of the Subways, AM New York. Accessed April 8, 2014
- ^ Reeves, Hope (October 26, 2006). "The Second Avenue Subway Is Brought to You by the Letter T". New York Magazine. Retrieved August 2, 2009.
- ^ a b c d John Del Signore (May 16, 2013). "Photos: Deep Inside The Second Avenue Subway's 72nd Street Station". Gothamist. Retrieved May 14, 2014.
- ^ MTA.info—Newsletter February 2012
- ^ a b c d MTA.info—Newsletter February 2012
- ^ a b c d CB8 presentation March 2008
External links
- Second Avenue Subway – Project Home – the MTA's homepage for this project
- Second Avenue Subway Photos – MTA's Flickr Website
- Second Avenue Subway: A New York Transit Museum on-line exhibit
- The Launch Box – a blog about building the Second Avenue Subway
- The Second Avenue Sagas – blog about New York City transit; hosts news from the Second Avenue Subway project
- The Second Avenue Subway – nycsubway.org