Downtown MRT line
Downtown Line | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Overview | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Native name | Malay: Laluan MRT Pusat Bandar Chinese: 滨海市区地铁线 Template:Lang-ta | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Status | Operational (Stages 1, 2 & 3) Under construction (Hume, Stage 3 extension) Under planning (Stage 2 extension) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Owner | Land Transport Authority | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Locale | Singapore | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Termini |
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stations | 34 (Operational)[1] 3 (Under construction) 1 (Under planning) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Service | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Type | Rapid transit | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
System | Mass Rapid Transit (Singapore) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Services | 2 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operator(s) | SBS Transit DTL Pte Ltd (ComfortDelGro Corporation)[2] | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Depot(s) | Gali Batu Tai Seng East Coast (Future) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Rolling stock | Bombardier Movia C951(A) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Daily ridership | 251,556 (July 2020)[3] | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
History | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Planned opening | 2025 2025 (Hume) mid-2030s (Stage 2 extension) | (Stage 3e) |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Opened | 22 December 2013 27 December 2015 (Stage 2) 21 October 2017 (Stage 3) | (Stage 1)|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Technical | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Line length | 41.9 km (26.0 mi) (Operational)[1] 2.2 km (1.4 mi) (Under construction) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Character | Fully underground | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electrification | 750 V DC third rail | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operating speed | limit of 80 km/h | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
The Downtown Line (DTL) is a medium-capacity Mass Rapid Transit (MRT) line in Singapore operated by SBS Transit. It runs from Bukit Panjang station in the north-west to Expo station in the east via the Central Area. Coloured blue on the rail map, the line serves 34 stations, all of which are underground.[2] The DTL is the fifth MRT line on the network to be opened and the third line to be entirely underground. It is the second MRT line to be operated by SBS Transit, after the North East Line. The line also serves as an alternative to the East-West MRT Line running parallel from Bugis to Expo MRT Station.
Originally planned as three separate lines, the lines merged into the Downtown Line in 2007 and construction began in three stages. The first section, from Bugis to Chinatown station (formerly the Downtown Extension of the Circle Line), opened in December 2013, followed by the second section from Bukit Panjang to Rochor station (formerly the Bukit Timah Line) opening in December 2015. The third and final stage, from Fort Canning to Expo station (formerly the northern part of the East Coast Line), opened in October 2017. At 41.9 kilometres (26.0 mi), the DTL is the longest underground and automated rapid transit line in Singapore as of 2017[update].[1] The train utilises the Bombardier Movia C951 which runs in a three-car formation on the line.
The line is set to be further extended in the 2020s. Stage 3e, an extension of the line to Sungei Bedok, is under construction and is scheduled to begin operations in 2025,[4] while a new infill station, Hume station, is planned to open in 2025.[5] An extension to connect with the North South line at Sungei Kadut station is also being planned and set to open in the 2030s.[6] When fully completed in 2025, the line will be about 44 kilometres (27 mi) long with 37 stations, and will serve more than half a million commuters daily.[7]
History
Background and inception
At the official opening of the Dover station on 23 October 2001, then-Minister for Communications and Information Technology Yeo Cheow Tong announced three MRT lines, two of which―the Bukit Timah Line and the northern part of the Eastern Region Line―are part of today's DTL. The Bukit Timah Line aimed to alleviate the traffic problems along the Bukit Timah and Dunearn Road corridor, and provide a direct link to the city area for residents in Choa Chu Kang and Bukit Panjang. The proposed Eastern Region Line, slated to be a loop in the eastern regions, aimed to relieve the passenger load on the often-congested East West line and benefiting those living in Tampines, Bedok and Marine Parade.[8]: 16―17 [9][10]
On 14 June 2005, the Land Transport Authority (LTA) announced the Downtown Extension (renamed to "Downtown Line Stage 1"), which would serve the New Downtown at Marina Bay area, where an integrated resort (Marina Bay Sands) and Singapore's second botanical garden (Gardens by the Bay) were to be located. The 3.4-kilometre (2.1-mile) extension, estimated to cost S$1.4 billion, was initially announced to be part of the Circle line.[11] On 27 April 2007, then Transport Minister Raymond Lim announced that the Downtown Line would be built in three stages stretching 40 kilometres (25 miles) with 33 stations.[12][13][14][15]
Construction and opening
The line was built in 3 stages: Stage 1 of the Downtown line, stretching 4.3-kilometre (2.7 mi), started construction in January 2008 at Chinatown station,[8]: 30 where platform provisions were built to facilitate an interchange station during the construction of the North East line. It began service on 22 December 2013,[19] with its official inauguration made on the day before by Prime Minister Lee Hsien Loong.[20]
Stage 2, first conceptualized and announced as the Bukit Timah line on 23 October 2001, is 16.6 kilometres (10.3 mi) long with 12 stations connecting Bukit Panjang and Rochor stations, including four interchange stations. Construction for Stage 2 began on 3 July 2009 with a groundbreaking ceremony at Beauty World station.[21][22] The line inaugurated on 27 December 2015, with free travel for all 18 stations from 27 December 2015 to 1 January 2016.[23][24][25]
Stage 3 goes from Chinatown to Expo. The station locations and finalised route were unveiled on 20 August 2010.[26][27] Stage 3 of the Downtown line is 21 kilometres (13 mi) long and serve 16 stations.[1][28] The route opened on 21 October 2017,[29] with free travel for all DTL stations on the first two days of the line completion.[30][31]
The line, with an estimated cost of S$12 billion, was considered the government's most ambitious rail project. The cost exceeded those of the Circle Line (at $6.7 billion) and the North East Line (at $4.6 billion). Final costs of building the line may reach an estimated about S$20.7 billion, up more than 70% from the initial estimation, due to sharp rises in construction costs and a number of changes in plans.[32][8]: 19
In October 2014, it was announced that Stage 2's opening would be pushed back to the first quarter of 2016. This was because one of the main contractors for the DTL2, Alpine Bau (which was building King Albert Park, Sixth Avenue and Tan Kah Kee), went bankrupt in mid-2013.[33] On 28 June 2015, Transport Minister Lui Tuck Yew announced that the delay was "completely resolved" by the authorities and Stage 2's opening date was brought forward to 27 December 2015.[34][35] The DTL 3 started operations on 21 October 2017, officially opened by Transport Minister Khaw Boon Wan.[36][37][38]
To serve the line, the Gali Batu Depot was opened in December 2015 to stable 42 trains. It is situated at part of the former Kwong Hou Sua Teochew Cemetery off Woodlands Road.[39] Also in February that year, the Land Transport Authority announced that the capacity of the depot will be expanded to stable 81 trains by 2019.[40]
Future
On 17 January 2013, plans were announced for a southern extension extending from Expo to connect with the Eastern Region line (ERL); the ERL has since been subsumed into the Thomson-East Coast line. The extension was to provide more travel options and enhance connectivity for the residents along the East Coast.[41][42] The Downtown Line 3 extension (DTL3e) was finalised and announced on 15 August 2014, in conjunction with the announcement of the Thomson–East Coast line.[43] Two stations, Xilin MRT station and Sungei Bedok MRT station, will be added to the Downtown Line, with Sungei Bedok as an interchange station with the Thomson–East Coast line. It will lengthen the line by 2.2 km (1.4 mi).[43] Expected to be completed in 2025, Stage 3e will connect the current East West line at Expo station and the future TEL at Sungei Bedok station.[44]
On 7 March 2019, Hume station was announced to be opened by 2025 to better serve Hillview residents.[5][45] An additional extension to the Downtown Line to Sungei Kadut station from Bukit Panjang station was announced on 25 May 2019 by the LTA. The extension is set to cut down travel time to the downtown area by up to 30 minutes for those living in the northwestern area of Singapore. The extension is expected to be completed by the mid-2030s. A study will also be conducted to determine the stops to be added between the Sungei Kadut and the existing Bukit Panjang stations.[6]
Notable incidents
A malfunction in the platform screen doors at Botanic Gardens station resulted in trains bypassing the station and a seven-hour disruption on 3 May 2017. Downtown line operator SBS Transit said that the doors malfunctioned at 5:45 am due to a signalling-related fault, and could not open automatically. The fault was rectified at 12:54 pm and the platform reopened for passenger service, with the affected door remaining closed for repairs.[46]
Network and operations
Route
The Downtown line generally goes in an east–west direction from Bukit Panjang in the northwestern side of Singapore, through the downtown area of Singapore, to Tampines and the Singapore Expo in the east. It is 41.9 kilometres (26.0 mi) long and is entirely underground. Before Bukit Panjang station, there exists a brief northwards extension to the line's depot Gali Batu Depot. The line begins at the Bukit Panjang station and then goes in the southeast direction, running parallel to Upper Bukit Timah Road and along the Bukit Timah Canal through Bukit Timah. The line then enters the central area, passing through Little India station before reaching the Central Business District via Bugis station. The Downtown line runs parallel to the Circle line at the Promenade and Bayfront stations. Passing through the Downtown Core, the line interchanges with the North East line at Chinatown station.
After Chinatown station, the line goes in a northeast direction and under the Singapore River. Between the Bencoolen and Jalan Besar stations, the line intersects itself, the first MRT line to do so. After Geylang Bahru station, the line continues in a general eastwards direction, through the industrial areas of Kampong Ubi and Kaki Bukit (briefly paralleling Ubi Avenue 2 and Kaki Bukit Avenue 1), before continuing towards the Tampines Regional Centre and goes southwards, ending at Changi Business Park. The DTL3 extension (DTL3e) from Expo station will extend the line further towards the Thomson–East Coast line at Sungei Bedok station.[48]
Stations
Station codes for the line are blue, corresponding to the line's colour on the system map. Most stations have island platforms, with the exception of Downtown, Telok Ayer, Chinatown, and MacPherson stations having side platforms, and Stevens and Promenade stations having stacked side platforms.
Date | Project | Description |
---|---|---|
22 December 2013 | Stage 1 | Bugis – Chinatown |
27 December 2015 | Stage 2 | Bugis – Bukit Panjang |
21 October 2017 | Stage 3 | Chinatown – Expo |
2025 | Stage 3 Extension | Expo – Sungei Bedok |
2025 | Hume Station | Hume station between Hillview and Beauty World |
By mid-2030s | Stage 2 Extension | Sungei Kadut – Bukit Panjang |
Legend
Elevated |
Line terminus |
Transfer outside paid area |
Ground-level |
Wheelchair accessible |
Bus interchange |
Underground |
Civil Defence Shelter |
Other transportation modes |
List
Station code | Station name | Images | Interchange; Adjacent transportation |
Opening | Cost |
---|---|---|---|---|---|
DT NS6 Infill station |
Sungei Kadut | North–South Line (mid-2030s) | mid-2030s[6] | TBA | |
DT1 – BP6 |
Bukit Panjang | Bukit Panjang LRT ― Bukit Panjang |
27 December 2015; 8 years ago |
S$452.4 million[a] | |
DT2 |
Cashew | — | S$431 million[b] | ||
DT3 |
Hillview | ||||
DT4 Infill station |
Hume | 2025; 1 year's time |
S$259.538 million[c] | ||
DT5 |
Beauty World | Beauty World | 27 December 2015; 8 years ago |
S$339.88 million[d] | |
DT6 CR15 |
King Albert Park | Cross Island Line (2032) | S$574.7 million[e] | ||
DT7 |
Sixth Avenue | — | |||
DT8 |
Tan Kah Kee | S$572 million[f] | |||
DT9 CC19 |
Botanic Gardens | Circle Line | S$378.2 million[g] | ||
DT10 TE11 |
Stevens | Thomson–East Coast Line | |||
DT11 – NS21 |
Newton | North–South Line | S$356 million[h] | ||
DT12 NE7 |
Little India | North East Line | S$803.3 million[i] | ||
DT13 |
Rochor | — | |||
DT14 EW12 |
Bugis | East–West Line | 22 December 2013; 10 years ago |
S$582 million[j] | |
DT15 CC4 |
Promenade | Circle Line ― Marina Centre |
S$231 million[k] | ||
DT16 CE1 |
Bayfront | Circle Line Extension | S$463 million[l] | ||
DT17 |
Downtown | — | S$230.3 million[m] | ||
DT18 |
Telok Ayer | S$224.9 million[n] | |||
DT19 NE4 |
Chinatown | North East Line | S$160.3 million[o] | ||
DT20 |
Fort Canning | — | 21 October 2017; 7 years ago |
S$255.05 million[p] | |
DT21 |
Bencoolen | S$177.58 million[q] | |||
DT22 |
Jalan Besar | S$171.46 million[r] | |||
DT23 |
Bendemeer | S$215.24 million[s] | |||
DT24 |
Geylang Bahru | S$123 million[t] | |||
DT25 |
Mattar | S$199.85 million[u] | |||
DT26 CC10 |
MacPherson | Circle Line | S$188 million[v] | ||
DT27 |
Ubi | — | S$161.71 million[w] | ||
DT28 |
Kaki Bukit | S$93.8 million[x] | |||
DT29 |
Bedok North | S$480.38 million[y] | |||
DT30 |
Bedok Reservoir | S$196.46 million[z] | |||
DT31 |
Tampines West | S$226.92 million[aa] | |||
DT32 – EW2 |
Tampines | East–West Line ― Tampines Tampines Concourse |
S$118.5 million[ab] | ||
DT33 |
Tampines East | — | S$208.52 million[ac] | ||
DT34 |
Upper Changi | S$256.98 million[ad] | |||
DT35 CG1 |
Expo | EWL Changi Airport Branch Line (until 2040) Thomson–East Coast Line (after 2040) |
S$211.35 million[ae] | ||
Stage 3 Extension (under construction, to be ready by 2025) | |||||
DT36 |
Xilin | — | 2025; 1 year's time |
S$833.6 million[af] | |
DT37 TE31 |
Sungei Bedok | Thomson–East Coast Line (2025) | S$418 million[ag] |
Depots
Number | Depot name; Lines |
Location | Images | Line-specific stabling capacity |
Cost | Opening |
---|---|---|---|---|---|---|
1 |
Gali Batu | Sungei Kadut | 81 trains | S$410 million | 27 December 2015; 8 years ago | |
2 |
Tai Seng | Hougang | 18 trains | S$81.5 million | 21 October 2017; 7 years ago | |
3 |
East Coast EWL TEL |
Changi | 66 trains | S$1.99 billion[49][50][51] | 2025; 1 year's time |
Rolling stock
As of 2011[update], the Downtown line has one type of rolling stock, the Bombardier MOVIA C951(A) cars,[52] running in a three-car formation. They have been stabled at Gali Batu Depot since it opened with Stage 2 of the downtown line on 27 December 2015. For the period between the opening of Stage 1 and that of Stage 2, trains were stabled at a maintenance facility that was built at Marina Bay as part of the Circle line project. Kim Chuan Depot housed the Operations Control Centre for the Downtown Line Stage 1 until Gali Batu Depot was ready.[53]
On 12 October 2012, the first of 11 trains for the line arrived at Jurong Port. It was transported to Kim Chuan Depot to undergo testing by the LTA before it was handed over to SBS Transit.[54] As of 28 February 2013[update], Bombardier had delivered five of the 11 trains for Downtown line stage 1.[55] LTA together with the operator, SBS Transit, conducted the necessary tests to ensure safety standards, functional performance and systems compatibility requirements were met before revenue service began on 22 December 2013.[56]
Testing for Stage 2 began on 25 October 2015 and rolling stock that was delivered to Gali Batu Depot commenced service in Stage 1 on 21 October 2015, while SBS Transit slowly moved the equipment managing the DTL trains to Gali Batu Depot during non-revenue hours.[8] Kim Chuan Depot, together with the adjacent Tai Seng Facility Building, operated in a minor capacity until Stage 3 opened. A new depot, named the East Coast Integrated Depot, is planned to provide additional stabling capacity to the line in 2025.[57] Testing on the integration of systems of Stage 3 and the rest of the line started from 14 May 2017 till 27 August 2017.[58]
Train control
The Downtown line is equipped with Siemens (previously Invensys before Siemens acquisition) Trainguard Sirius Communications-based train control (CBTC) moving block signalling system with Automatic train control (ATC) under Automatic train operation (ATO) GoA 4 (UTO).[59] The subsystems consist of Automatic train protection (ATP) to govern train speed, Controlguide Rail 9000 Automatic Train Supervision (ATS) to track and schedule trains and Trackguard Westrace MK2 Computer-based interlocking (CBI) system that prevents incorrect signal and track points to be set.[60][61]
A fall-back signalling system, relying on conventional track-circuit occupancy detection, is included to ensure fully automatic operation and train protection independent of the radio system.
Platform screen doors (PSDs) along the line were installed by Westinghouse Signal (Invensys Rail Group), supplied by Faiveley.[62] The PSDs provide safety for passengers, offering protection from arriving and departing trains.[63][64]
Notes
- ^ DTL2 Contract 912
- ^ DTL2 Contract 913
- ^ S$225.2 for DTL2 Contract 915, S$34.338 million for Contract 915A for completion works
- ^ DTL2 Contract 916
- ^ S$320.7 million for DTL2 Contract 917, S$254 million for DTL2 Contract 917A for completion of works after insolvency of first contractor
- ^ S$350 million for DTL2 Contract 918, S$222 million for DTL2 Contract 918A for completion of works after insolvency of first contractor
- ^ DTL2 Contract 919
- ^ DTL2 Contract 920
- ^ DTL2 Contract 921
- ^ DTL1 Contract 903
- ^ DTL1 Contract 902
- ^ DTL1 Contract 906
- ^ DTL1 Contract 907
- ^ DTL1 Contract 908
- ^ DTL1 Contract 909
- ^ DTL3 Contract 937
- ^ DTL3 Contract 936
- ^ DTL3 Contract 935
- ^ DTL3 Contract 933
- ^ DTL3 Contract 932A
- ^ DTL3 Contract 932
- ^ DTL3 Contract 931
- ^ DTL3 Contract 930
- ^ DTL3 Contract 929
- ^ S$268.68 million for DTL3 Contract 928 for Bedok North station, S$211.7 million for DTL3 Contract C929A for reception tunnels to Tai Seng Facility Building
- ^ DTL3 Contract 927
- ^ DTL3 Contract 926
- ^ DTL3 Contract 925A
- ^ DTL3 Contract 925
- ^ DTL3 Contract 923
- ^ DTL3 Contract 922
- ^ DTL3e Contract T313
- ^ Contract T312; cost shared with Thomson–East Coast Line
References
- ^ a b c d "Projects – Downtown Line – Stages". Land Transport Authority of Singapore. 17 December 2013. Archived from the original on 3 July 2014. Retrieved 23 June 2014.
- ^ a b "Company Announcement – Incorporation of a Wholly-Owned Subsidiary" (PDF). Archived from the original (PDF) on 10 June 2015. Retrieved 5 September 2012.
- ^ "Land Transport DataMall". mytransport.sg. Archived from the original on 21 August 2020. Retrieved 20 August 2020.
- ^ "Downtown Line 3 Extension". Land Transport Authority. Archived from the original on 6 April 2019. Retrieved 28 April 2017.
- ^ a b "滨海市区线谦道站料2025年启用" [Hume Station on Downtown Line is expected to open in 2025]. 早报 (Zaobao) (in Chinese). 7 March 2019. Archived from the original on 7 March 2019. Retrieved 7 March 2019.
- ^ a b c Choo, Daryl (25 May 2019). "New MRT stations, line extensions and a possible new rail line: LTA's 2040 blueprint". TODAYonline. Archived from the original on 25 May 2019. Retrieved 29 May 2019.
- ^ "More Trains, More Capacity, More Often". Land Transport Authority. Archived from the original on 29 September 2013.
- ^ a b c d The Downtown Line: Soaring to new heights. The Straits Times. 2017.
- ^ "Speech by Mr Yeo Cheow Tong at the Official Opening of Dover Station on 23 Oct 2001". MOT. Archived from the original on 5 September 2020. Retrieved 11 July 2019.
- ^ Land Transport Authority (24 January 2014). "Circle Line Linking All Lines". The Straits Times. p. 50.
- ^ "Expanding The Rail Network With Downtown Extension". LTA. 14 June 2005. Archived from the original on 27 September 2007. Retrieved 30 August 2019.
- ^ "Speech By Mr Raymond Lim At The LTA Workplan Seminar on 27 April 2007". MOT. Archived from the original on 3 September 2020. Retrieved 11 July 2019.
- ^ "Govt approves S$12b MRT Downtown Line to be built by 2018". Archived from the original on 9 December 2012.
- ^ "Government Approves Building Of The Downtown Line". LTA. 27 April 2007. Archived from the original on 2 March 2012. Retrieved 6 September 2019.
- ^ "33-station Downtown line gets go-ahead, will be ready by 2018". The Straits Times. 28 April 2007. Archived from the original on 8 October 2019. Retrieved 8 October 2019 – via NLB.
- ^ Abdullah, Zhaki (20 October 2017). "Downtown Line Stage 3 to be opened". The Straits Times. Archived from the original on 31 May 2017. Retrieved 31 May 2017.
- ^ LTA (12 November 2016). "LTA Wins Top Accolade at International Tunnelling Awards". Land Transport Authority (Press release). Archived from the original on 19 September 2020. Retrieved 24 April 2020.
- ^ "Factsheet: Downtown Line 3 to Open on 21 October 2017". Land Transport Authority. Archived from the original on 3 July 2017. Retrieved 3 June 2017.
- ^ "Downtown Line". Land Transport Authority. Archived from the original on 3 July 2014. Retrieved 22 December 2013.
- ^ Sim, Royston (21 December 2013). "Downtown Line Stage 1 officially opened by PM Lee". The Straits Times. Archived from the original on 22 December 2013. Retrieved 22 December 2013.
- ^ Tan, Christopher (15 July 2008). "LTA unveils locations of DTL stage 2 stations". The Straits Times. Archived from the original on 13 August 2008.
- ^ Thia, Tyler (3 July 2009). "Work on MRT Downtown Line Phase 2 Starts". Channel NewsAsia. Archived from the original on 6 September 2009. Retrieved 21 August 2009.
- ^ "The Rail Report: 12 stations of Downtown Line 2 to Open on 27 December". Land Transport Authority. 6 August 2015. Archived from the original on 3 October 2015. Retrieved 6 August 2015.
- ^ "Downtown Line 2 to open ahead of schedule in December: Transport Minister Lui". Channel NewsAsia. 28 June 2015. Archived from the original on 30 June 2015. Retrieved 28 June 2015.
- ^ "LTA | Downtown Line 2 is Coming to Town….this December". www.lta.gov.sg. Archived from the original on 4 September 2020. Retrieved 19 September 2022.
- ^ "Downtown Line 3 (DTL3) Stations Unveiled". MOT Singapore. 20 August 2020. Archived from the original on 21 August 2020. Retrieved 24 April 2020.
- ^ Land Transport Authority (20 August 2010). "Downtown Line 3 station Locations Unveiled" (Press release). Archived from the original on 21 June 2011.
- ^ Land Transport Authority; SBS Transit (26 April 2017). "Train Services on Downtown Line to Start Later at 7.30am on Sundays to Facilitate Systems Integration Testing". Land Transport Authority (Press release). Archived from the original on 28 April 2017. Retrieved 28 April 2017.
- ^ "Factsheet: Downtown Line 3 to Open on 21 October 2017". Land Transport Authority. 31 May 2017. Archived from the original on 3 July 2017. Retrieved 31 May 2017.
- ^ Land Transport Authority. "Opening of Downtown Line 3: Free Travel on Entire Downtown Line on 21 and 22 October 2017". LTA (Press release). Archived from the original on 19 September 2020. Retrieved 24 April 2020.
- ^ Neo, Elizabeth (15 November 2017). "Doors open on Downtown line 3 for preview ahead of Oct 21 launch". Archived from the original on 3 March 2018. Retrieved 3 March 2018.
- ^ Tan, Christopher (30 October 2012). "Downtown Line costs soar by more than 70%". The Straits Times. Archived from the original on 29 October 2012.
- ^ Ng, Kelly (29 September 2014). "Stage 2 of Downtown Line to open in first quarter 2016". TODAYonline. Archived from the original on 11 October 2016. Retrieved 16 May 2016.
- ^ Choon, Chang May (3 October 2014). "Thumbs Up For Downtown Line's Earlier Opening". The Straits Times. Archived from the original on 3 April 2015. Retrieved 28 February 2015.
- ^ Land Transport Authority (4 November 2015). "Downtown Line 2 is Coming to Town....this December". LTA (Press release). Archived from the original on 4 September 2020. Retrieved 24 April 2020.
- ^ Tan, Christopher (20 October 2017). "Downtown Line 3 officially opens; Khaw Boon Wan announces review of fares incurred when switching between stations". The Straits Times. Archived from the original on 21 October 2017. Retrieved 21 October 2017.
- ^ "LTA Awards Contracts for Tampines West and Bedok Reservoir Stations". Mynewsdesk (Press release). 5 July 2011. Archived from the original on 8 August 2014. Retrieved 7 March 2020.
- ^ Neo, Elizabeth (31 May 2017). "Downtown Line 3 to open on Oct 21". Channel NewsAsia. Archived from the original on 31 May 2017. Retrieved 31 May 2017.
- ^ Perry, Margaret (26 February 2008). "Downtown Line depot to be located off Woodlands Road". Channel NewsAsia. Archived from the original on 1 March 2008.
- ^ Land Transport Authority (17 February 2015). "Gali Batu Depot". Archived from the original on 1 March 2018. Retrieved 1 March 2018.
- ^ "Speech by Mr Lui Tuck Yew at visit to DTL1 Chinatown Station on 17 January 2013". MOT. 17 January 2013. Archived from the original on 26 February 2020. Retrieved 19 September 2019.
- ^ "Two New Rail Lines and Three New Extensions to Expand Rail Network by 2030". Land Transport Authority. 17 January 2013. Archived from the original on 6 July 2014.
- ^ a b Ismail, Saifulbahri (15 August 2014). "Thomson–East Coast Line, connecting North and East, ready by 2024". Channel NewsAsia. Archived from the original on 16 August 2014.
- ^ "Downtown Line 3 Extension". Land Transport Authority. 15 August 2014. Archived from the original on 15 October 2014. Retrieved 15 August 2014.
- ^ Tan, Christopher (30 June 2020). "Work on Hume MRT station on Downtown Line to start in the fourth quarter". The Straits Times. Archived from the original on 19 September 2020. Retrieved 21 August 2020.
- ^ "Platform doors at Botanic Gardens MRT station malfunction, causing 7-hour disruption". Channel NewsAsia. Archived from the original on 3 May 2017. Retrieved 3 May 2017.
- ^ "Oct 21 debut for Downtown Line 3". The New Paper. 1 June 2017. Retrieved 2 August 2023.
- ^ "Downtown Line Overview". Land Transport Authority. Archived from the original on 31 March 2017. Retrieved 28 May 2017.
- ^ "LTA Awards Contract to Build World's First Four-In-One Depot". Land Transport Authority. 21 March 2016. Archived from the original on 13 February 2020. Retrieved 13 February 2020.
- ^ Gabriel, Anita (21 March 2016). "LTA awards S$1.99b contract to build world's first four-in-one depot". The Business Times. Archived from the original on 13 February 2020. Retrieved 13 February 2020.
- ^ Lim, Adrian (21 March 2016). "Korea-based construction firm to build four-in-one train and bus depot for $1.99 billion". The Straits Times. Archived from the original on 1 February 2022. Retrieved 14 November 2020.
- ^ Land Transport Authority (11 July 2008). "LTA Awards 6 Downtown Line Contracts Totalling $1.13 Billion" (Press release). Archived from the original on 27 May 2011.
- ^ Land Transport Authority (9 November 2007), Contract 901QP: Terms of Reference – via www.gebiz.gov.sg
- ^ "Downtown Line Train Arrives". Land Transport Authority. 12 October 2012. Archived from the original on 29 September 2013. Retrieved 16 November 2013.
- ^ "Shorter Waiting Time With 15 More Trains For Downtown Line". Land Transport Authority. 28 March 2013. Archived from the original on 11 April 2013. Retrieved 28 March 2013.
- ^ Sim, Royston (7 October 2013). "Land Transport Masterplan: Downtown Line Stage 1 to open on Dec 22". The Straits Times. Archived from the original on 3 December 2013. Retrieved 16 November 2013.
- ^ "4-in-1 depot save taxpayers 2bn". 23 February 2018. Archived from the original on 23 February 2018. Retrieved 3 March 2017.
- ^ Land Transport Authority; SBS Transit (26 April 2017). "Train Services on Downtown Line to Start Later at 7.30am on Sundays to Facilitate Systems Integration Testing". Land Transport Authority (Press release). Archived from the original on 19 September 2020. Retrieved 24 April 2020.
- ^ Siemens (11 February 2014). "Siemens-equipped driverless underground metro line in Singapore starts operations for Downtown Line 1" (Press release). Archived from the original on 4 March 2016. Retrieved 21 August 2016.
- ^ "como special issue" (PDF). Archived from the original (PDF) on 19 September 2015. Retrieved 25 March 2017.
- ^ Barrow, Keith (29 January 2013). "CBTC testing starts on Singapore Downtown Line". Archived from the original on 25 March 2017. Retrieved 25 March 2017.
- ^ "Singapore Down Town Line "DTL": Another milestone achievement for Faiveley Transport's Platform Doors and Gates activity". Faiveley Transport. 1 December 2009. Archived from the original on 18 April 2016.
- ^ Land Transport Authority (7 November 2008). "LTA Awards 6 Downtown Line Contracts Totalling $1.13 Billion" (Press release). Archived from the original on 17 September 2016. Retrieved 7 September 2016.
- ^ "The Challenges of Delivering the Downtown Line Signalling System". WUTC Singapore. Archived from the original on 4 April 2017. Retrieved 4 April 2017.
External links
- Downtown Line
- The Downtown Line - A commemorative book by LTA detailing the construction of the DTL
- Downtown Line Map
;