Jump to content

Kolkata Metro Line 6

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by 2409:4071:e1a:9dc::544a:3011 (talk) at 16:59, 26 January 2021 (→‎History). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Kolkata Metro Line 6

Kavi Subhash-Biman Bandar
Overview
Other name(s)
  • New Town metro
  • Airport Metro
  • Bypass Metro
StatusUnder Construction
OwnerMetro Railway, Kolkata
Line number6
LocaleKolkata Metropolitan Area, India
Termini
Connecting lines Blue Line   Green Line   Yellow Line 
Stations24
Websitehttps://mtp.indianrailways.gov.in
Service
TypeRapid transit
SystemKolkata Metro
Operator(s)Metro Railway, Kolkata
Depot(s)
  • NSCBI Airport (underconstruction)
  • New Garia (underconstruction)
  • New Town
Daily ridership500,000 (projected)
History
Commenced2012
Planned opening2021 (Kavi Subhash-Hemanta Mukhopadhay)
Technical
Line length29.87 kilometres (18.56 mi)[1]
Number of tracks2
Character
  • Surface – 1
  • Underground – 1
  • Elevated – 22
Track gauge1,676 mm (5 ft 6 in) Broad gauge
Electrification750 V DC[2] using third rail
Operating speed80 km/h (designed)
SignallingCommunications-based train control
Route map

Kavi Subhash
Satyajit Ray
Jyotirindra Nandi
Panchanangram Canal
Kavi Sukanta
Hemanta Mukhopadhyay
VIP Bazar
Ritwik Ghatak
Storm Water Outlet Canal
Barun Sengupta
Beleghata
Captain Bhery
Gour Kishore Ghosh
Nalban
IT Centre
Nabadiganta
Keshtopur Canal
Nazrul Tirtha Bus interchange
Swapnabhor
Biswa Bangla Convention Centre
Keshtopur Canal
Shiksha Tirtha
Mother's Wax Museum
Eco Park
Mangaldeep
City Centre-2
Chinar Park
VIP Road Bus interchange Green Line
Jai Hind

Line 6 of the Kolkata Metro is an under-construction rapid transit line that will connect New Garia with Netaji Subhas Chandra Bose International Airport via two satellite towns Salt Lake and New Town. There will be total of 24 stations. The line is targeted to open from Kavi Subhash to Hemanta Mukherjee in 2021.[3] This stretch will be one the most important stretches of metro because it will connect the southern and the eastern parts of the city with Kolkata Airport. Total distance of this route will be 29.87 km (18.56 mi).[1]

History

This project was sanctioned in the budget of 2010-11 by Mamata Banerjee with a project deadline of six years.[4] The execution of this project has been entrusted to RVNL at a cost of Rs 3951.98 crore. It will help to reduce travel time between the southern fringes of Kolkata to Netaji Subhas Chandra Bose International Airport and will have 23 elevated stations, 1 underground station and 1 at-grade. The terminal Airport station being the underground one.

Work for construction of the terminal station at New Garia for the 29.87-km Kavi Subhash-Biman Bandar (via Rajarhat) metro project finally resumed on 14 February 2017 with Rail Vikas Nigam Ltd (RVNL) demarcating the plot they require for the purpose.

The work has been delayed for years due to multiple issues. At first AAI objected the station above the ground, stating that this could be a threat for air traffic. Many underground utilities, power sub-station and water treatment plant had to be shifted. Encroachments and Land acquisition problems held up the project for multiple times.

The 5 km stretch from New Garia to Ruby Hospital was expected to start from 2018.[5] On 12 February 2018 Mr Ajay Vijayvargiya, General Manager Metro Railways announced a delay in inauguration of New Garia to Ruby stretch.

Stations

The stations, as declared of now, will be named after eminent personalities.[4][6][7] and will have 23 elevated stations, 1 underground station and 1 at-grade. The terminal Airport station will be the underground one. This station will also have a yard and it will be the largest underground facility of India and city's first. It will be 550m long and 41.6m wide and will facilitate stabling and reversal of rakes, but it will not be a carshed. One can interchange to Line 4 at Dum Dum Airport, Line 2 at VIP Road (Haldiram) and Salt Lake Sector V and Line 1 at Kavi Subhash. At Kavi Subhash, Rail Interchange will be also available (SDAH-NMKA Line).

On 4th January 2021 the state government decided to rename 9 metro stations in New Town area to their more prevailing names rather than using the old ones which were given during the planning phase. The state transport department has informed Housing Infrastructure Development Corporation (HIDCO) of the new names of the proposed nine metro stations between Nazrul Tirtha at the entry of New Town from Salt Lake Sector 5 till Chinar Park, the last station on the line before it turns right on VIP road towards Kolkata Airport.[8]

Line 6
No. Station Name Location Phase Opening Connections Layout Notes
English Bengali
1 Biman Bandar বিমান বন্দর NSCB International Airport 4 Under construction  Yellow Line  (Under construction)

Netaji Subhash Chandra Bose International Airport

Airport AC Bus Stand

Airport Gate No. 1 Bus Stop

Airport Gate No. 2 Bus Stop

Airport Gate No. 2.5 Bus Stop

Airport Gate No. 3 Bus Stop

Underground
2 VIP Road / Haldiram ভি আই পি রোড / হলদিরাম Teghoria  Green Line  (Planned)

Minibus Stand

Haldiram Bus Stop

Elevated
3 Chinar Park চিনার পার্ক New Town
4 City Centre II সিটি সেন্টার ২
5 Mangal Deep মঙ্গল দীপ Also known as Akanksha 5-point crossing
6 Eco Park ইকো পার্ক Also known as Nawabpur
7 Mother's Wax Museum মাদার্স ওয়াক্স মিউজিয়াম
8 Siksha Tirtha শিক্ষা তীর্থ Also known as Kala Kshetra
9 Biswa Bangla Convention Centre বিশ্ব বাংলা কনভেনশন সেন্টার Also known as Narkelbagan / Rabindra Tirtha
10 Swapno Bhor স্বপ্ন ভোর
11 Nazrul Tirtha নজরুল তীর্থ Also known as Newtown Bus Stand
12 Technopolis টেকনোপোলিস Salt Lake Also known as Bidhannagar Limit
13 Salt Lake Sector V সল্টলেক সেক্টর ৫ 3  Green Line  (Operational)

Wipro Bus Stop

Saltlake Bus Depot

Karunamoyee Bus Station(WBTC,CTC,SBSTC,NBSTC)

Located near IT Hub of Kolkata
14 Nicco Park নিক্কো পার্ক Serving Nicco Park
15 Gour Kishore Ghosh গৌর কিশোর ঘোষ Also known as Chingrighata / Sukanta Nagar
16 Beliaghata বেলেঘাটা Beliaghata Also known as Tangra Metropolitan Township
17 Barun Sengupta বরুণ সেনগুপ্ত Dhapa/Mathpukur 2 Also known as Metropolitan
18 Ritwik Ghatak ঋত্বিক ঘটক Science City Also known as Parama Island
19 VIP Bazar ভি আই পি বাজার VIP Bazar
20 Hemanta Mukherjee হেমন্ত মুখার্জি Ruby Island 1 Also known as Kasba Golpark / East Kolkata Township
21 Kavi Sukanta কবি সুকান্ত Kalikapur
22 Jyotirindra Nath Nandi জ্যোতিরীন্দ্র নাথ নন্দী Mukundapur Also known as Singhbari
23 Satyajit Ray সত্যজিৎ রায় SRFTI / Hiland Park Bengal Ambuja Bus Stop

Hiland Park Bus Stop

Peerless Hospital Bus Stop

Also known as Chak Garia
24 Kavi Subhash কবি সুভাষ New Garia 7 October 2010  Blue Line  (Operational)

New Garia Station

New Garia Station Bus Stand

At Grade

See also

Line 2 and 6 under construction at Salt Lake Sector V, November 2017

References

  1. ^ a b "New System Map of Kolkata Metro".
  2. ^ [1]
  3. ^ https://timesofindia.indiatimes.com/city/kolkata/work-on-fast-track-as-metro-eyes-new-links-in-next-2-yrs/articleshow/69717307.cms
  4. ^ "Metro sets June 2018 date for New Garia-Ruby line". The Times of India.
  5. ^ "New Garia to Biman Bandar via Rajarhat Metro extension".
  6. ^ "Kolkata Metro Line 6".
  7. ^ Mondal, Biswadeep (4 January 2021). "West Bengal govt renames nine New Town Metro stations". Times of India.{{cite news}}: CS1 maint: url-status (link)

External links